2005 Overlay Project/Project 05-2
Crosstown Boulevard improvements/04-33/04-32
State Aid Designations
Well #9/Project 04-52
Other Business
G:IDATAISTAFF\RHONDAAIAGENDAIPublic Works Comm Mlg..doc
5'\ND6VE~
/'..
\.J
1685 CROSSTOWN BOULEVARD N.W. . ANDOVER, MINNESOTA 55304 . (763) 755-5100
FAX (763) 755.8923 . WWW.CI.ANDOVER.MN.US
TO: Public Works Committee Members
CC: Jim Dickinson, City Administrator
FROM: David D. Berkowitz, City Engineer
SUBJECT: 1. 2005 Overlay Project/Project 05-2
DATE: February 28,2005
o
INTRODUCTION
There are three developments that are proposed to have street reconstruction this year as part of
the 2005 Overlay project. The three development areas are Valley View Estates, the north
portion of Valley View Estates 2nd Addition and the Russell Stack Addition (refer to feasibility
report included with your Council packet - please bring with you to the meeting). Staff met with
residents that are proposed to be assessed for concrete curb and gutter. They raised concerns that
staff would like to discuss with the Public Works Committee.
DISCUSSION
The Russell Stack Addition will consist of a standard mill and overlay project with no curb and
gutter. The storm sewer system in this development for the most part is a ditch system adjacent
to the roadway. Staff anticipates no resident objections or concerns in this area since there will be
no assessments for any of the improvements.
The north portion of Valley View Estates 2nd Addition has bituminous curb with no ditches. All
parcels in this development would be assessed for the concrete curb and gutter.
The Valley View Estates development has only 8 parcels out of 50+ that currently have
bituminous curb. Only those 8 parcels are proposed to have concrete curb and gutter constructed
along their property lines and be assessed for those costs. The remainder of the development
would have a standard mill and overlay which would not be assessed. This area does not have
ditches adjacent to the roadway. Existing drainage flows along the edge of the sodded yards to
catch basins or low areas adjacent to the roadway.
The current policy is that when a road is reconstructed, existing bituminous curb be replaced with
concrete curb and gutter. If no curb exists, no curb will be constructed.
o
There were to main concerns raised at the neighborhood meeting. The first concern: Why is the
City requiring concrete curb and gutter? The explanation is the curb conveys storm water runoff,
which improves drainage, the concrete curb provides structural support at the edge of the
roadway, and concrete has less maintenance and a longer life than bituminous curb.
/ "-
\, --.J
,~
u
~
Public Works Committee Members
February 28, 2005
Page 2 of2
The other main concern: Why is the City not requiring the remaining 50+ parcels in Valley View
Estates to have concrete curb and gutter if they do not have existing ditches, especially when they
believe there are more drainage problems in that area? Staffs response was the current policy
states that if bituminous curb exists, then concrete curb will replace it. If there is no curb, no
curb will be required at the time of reconstruction.
ACTIQN REQUIRED
This is for discussion. No action is required at this time.
Respectfully submitted,
~Q.
David D. Berkowitz
/ '.
<)
o
/ '\
V
1685 CROSSTOWN BOULEVARD N.W. . ANDOVER, MINNESOTA 55304 . (763) 755.5100
FAX (763) 755.8923 . WWW.CI.ANDOVER.MN.US
TO: Public Works Committee Members
CC: Jim Dickinson, City Administrator
FROM: David D. Berkowitz, City Engineer
SUBJECT: 2. Crosstown Boulevard Improvements/04-33/04-32
DATE: February 28,2005
INTRODUCTION
Intersection improvements at Crosstown Boulevard NW & 159th Avenue NW and Crosstown
Boulevard & Xeon Street NW are required by the Anoka County Highway Department as a
condition of plat approval for the adjacent developments. A plan will be presented for discussion
at the meeting.
DISCUSSION
Staff is currently working on the plans for the above-mentioned intersection improvements.
Additional right-of-way and/or a trail easement may be required to complete the project. Items
will be discussed in detail at the meeting.
ACTION REOUIRED
This is for discussion and information. No action required.
Respectfully submitted,
Q~.
David D. Berkowitz
CITY OF
NDOVE
~ "
( )
'. ,
1685 CROSSTOWN BOULEVARD N.W. . ANDOVER. MINNESOTA 55304 . (763) 755.5100
FAX (763) 755.8923 . WWW.CI.ANDOVER.MN.US
TO:
Public Works Committee Members
CC:
Jim Dickinson, City Administrator
David D. Berkowitz, City Engine~B
FROM:
Todd J. Haas, Asst. City Engineer
SUBJECT:
3. State Aid Designations
DATE:
February 28, 2005
INTRODUCTION
The Public Works Committee is requested to consider Municipal State Aid (MSA) designations
for 2005.
, - ''\
LJ DISCUSSION
As you know, as new local City streets are added each year, by Statute, 20% of the basic mileage
canbe designated. Currently the improved mileage total is 191.94, which includes County State
Aid Highways, MSA Streets, County Roads and local City streets. Once the calculations have
been made, .698 miles are available to designate. Listed below are a couple options to consider:
A. 152nd Lane NW between Nightingale Street NW and Tower Drive NW. Miles to be
designated = 0.30 miles
B. Verdin Street NW between South Coon Creek Drive NW and Crosstown Boulevard NW.
Miles to be designated = 0.60 miles
Note: Included in your packet is a map identifying the locations of the proposed
designations.
ACTION REOUIRED
The Public Works Committee is requested to review and recommend to the City Council the
MSA route to be designated.
Respectfully submitted,
, "
~~~
\.J
Attachment: Location Map
f
'.
1685 CROSSTOWN BOULEVARD N.W. . ANDOVER, MINNESOTA 55304. (763) 755.5100
FAX (763) 755.8923 . WWW.CI.ANDOVER.MN.US
TO: Public Works Committee Members
CC: Jim Dickinson, City Administrator
FROM: David D. Berkowitz, City Engineer
SUBJECT: 4. Well #9/Project 04-52
DATE: February 28,2005
, \
\... .i
INTRODUCTION
Well #9 and the transmission line to the Water Treatment Plant are proposed to be constructed
this summer.
DISCUSSION
The current plan will be presented that the meeting for discussion.
ACTION REQUIRED
This is for discussion and information. No action is required.
Respectfully submitted,
David D. Berkowitz
(i)~r;). I
.~-'.t
\. .-/