HomeMy WebLinkAbout2009 CIP2009² 2013 Capital Improvement Plan 1685 Crosstown Blvd NW, Andover, MN 55304 Phone: 763.755.5100 Fax: 763.755.8923 www.ci.andover.mn.us This page left blank intentionally. CITY OF ANDOVER 2009 – 2013 Capital Improvements Plan Table of Contents Introduction 2009 – 2013 Capital Improvement Plan Message.......................................................................................1 CIP Project Development & Process Authorization Schedule....................................................................4 Graph – 2009 Expenditures By Department................................................................................................6 Graph – 2009 CIP Expenditures By Year....................................................................................................6 Five Year Summary of Expenditures By Department.................................................................................7 Five Year Summary of Revenue By Source................................................................................................8 Five Year Summary of Projects By Department & Revenue Source..........................................................9 Improvements Five Year Summary of Expenditures By Department – Improvements......................................................15 Five Year Summary of Revenue By Source – Improvements.....................................................................16 Five Year Summary of Projects By Department & Revenue Source – Improvements...............................17 Improvement Projects By Department Community Center................................................................................................................................20 Engineering...........................................................................................................................................21 Facility Management.............................................................................................................................23 Parks & Recreation – Operations..........................................................................................................37 Parks & Recreation – Projects...............................................................................................................39 Sanitary Sewer......................................................................................................................................46 Storm Sewer..........................................................................................................................................52 Streets / Highways................................................................................................................................53 Water.....................................................................................................................................................75 Equipment Year Summary of Expenditures By Department – Equipment....................................................................85 Five Year Summary of Revenue By Source – Equipment..........................................................................86 Five Year Summary of Projects By Department & Revenue Source – Equipment.....................................87 Equipment By Department Central Equipment................................................................................................................................90 Community Center................................................................................................................................94 Elections................................................................................................................................................95 Engineering...........................................................................................................................................96 Fire Department....................................................................................................................................97 Parks & Recreation – Operations..........................................................................................................108 Planning & Zoning................................................................................................................................116 Sanitary Sewer......................................................................................................................................117 Storm Sewer..........................................................................................................................................119 Street Signs...........................................................................................................................................121 Streets / Highways................................................................................................................................122 Water.....................................................................................................................................................127 Appendix Road & Bridge Fund Projected Fund Balance.............................................................................................129 Park Improvement Fund Projected Fund Balance.......................................................................................130 Trail Fund Projected Fund Balance.............................................................................................................131 Water System Financial Projections............................................................................................................132 Sewer System Financial Projections............................................................................................................134 This page left blank intentionally.   1685 CROSSTOWN BOULEVARD N.W. ANDOVER, MINNESOTA 55304 (763) 755-5100 FAX (763) 755-8923 WWW.CI.ANDOVER.MN.US TO: Mayor and Council Members FROM: Jim Dickinson, City Administrator / Finance Director SUBJECT: 2009 - 2013 Capital Improvement Plan DATE: October 21, 2008 INTRODUCTION On behalf of the City’s Management Team, I am pleased to present the City of Andover’s Capital Improvement Plan for years 2009 through 2013. The City’s management team and their respective staff worked diligently to produce a document that was both practical, substantive in addressing needed capital improvements and insightful regarding the underlying factors associated with the City’s rapidly changing suburban landscape. CAPITAL IMPROVEMENT PLAN GOALS AC CKNOWLEDGE AND OMMUNICATE I PUBLIC NFRASTRUCTURE PRIORITIES AND DYNAMICS EAR NSUREPPROPRIATE ESPONSES TO CHANGING INFRASTRUCTURE NEEDS AND DEMANDS DFACR EVELOP A INANCIALSSESSMENT OF APITALESOURCES AVAILABLE TO MEET FUTURE CAPITAL PROJECT PLANNING NEEDS ISV NSTITUTE A TRATEGICISION PREDICATED ON MAINTAINING A HIGH QUALITY SERVICE INFRASTRUCTURE CAPABLE OF MEETING THE NEEDS OF OUR CITIZENS FOR TODAY AND TOMORROW The purpose of the City’s Capital Improvement Plan (CIP) is to identify, prioritize and address community needs through careful long-term capital planning and balanced public investment in supporting physical infrastructure. To ensure that this commitment is both meaningful and achievable, appropriate capital improvement factors were given significant consideration in developing a CIP that addresses community priorities over the next five (5) years. The CIP will also provide a planning foundation for future needs assessments to ensure the City is appropriately responding to the critical infrastructure needs necessary for sustainable future growth. The CIP represents a beginning in terms of producing a comprehensive planning response to address changing capital needs by developing a project schedule that will lead to timely and cost-effective project completions. 1 DISCUSSION The 2009 - 2013 CIP has been prepared as a strategic planning tool to assist the City Council in identifying proposed capital improvement projects over the next five years. With the inclusion of preliminary financing sources, appropriate background information citing needs and projected cost estimates, this document will provide Council with the needed information to begin the process for planning improvements that meet the City’s physical infrastructure needs. Consequently, the CIP serves as a flexible guide plan to properly identify the critical components of the City's infrastructure, yet maintain flexibility in determining project timeframes, project scope and possible funding sources. The 2009 - 2013 CIP continues the emphasis of judiciously managing the City’s limited resources by prudently planning for known and/or anticipated future capital expenditures. A critical step in the plan adoption process is the collaborative nature of plan review that involves the leadership of the City Council, the input of appointed Commissions and staff, and most importantly, affected residents of the community. Consequently, the strategic value of this plan lies in the acknowledgement of future needs by the governing body and the effective communication of those needs to the general public during project development stages. Likewise, the availability and preliminary designation of fiscal resources to serve both current and future needs is critical to the achievement of plan outcomes that meet with Council approval. Following the approval of the plan, feasibility studies are performed, affected constituencies are notified to formally disseminate and receive public feedback on proposed project plans. This process culminates with the City Council considering all relevant information and making a final decision on whether to proceed with the proposed capital improvement. The public process that supports the advancement of these projects from inception to completion is engendered in the CIP project development and authorization schedule. Formalizing the steps in the CIP project advancement process serves a number of purposes and ensures that the Council and public are kept well informed regarding project purposes and desired outcomes, estimated project costs, funding sources, progress and final status. It should be emphasized that projects will require approval in various stages of project development by the City Council in accordance with approved policies. The objectives of the 2009 - 2013 Capital Improvement Plan are to present a comprehensive capital improvement program that communicates efforts: to ensure that community priorities are reflected in the capital investment plans of each City department; to provide a consolidated financial picture of anticipated expenditures and outline recommended funding strategies to underwrite anticipated capital improvements; to document and communicate capital improvement processes for City projects that will ensure consistency, a full appreciation of both the costs and benefits of proposed capital investments, and raises the level of public understanding regarding the City’s public improvement processes; to provide information on the fiscal impacts of capital investment plans on total City finances; and to effectively plan for public improvements that support community needs in the areas of private development infrastructure, transportation, public safety, parks and recreation, utilities, and commercial/industrial growth through fiscally responsible economic development initiatives. Accordingly, this document attempts to recognize known or perceived capital improvement needs, but as with any plan recognizes that social, economic and political considerations will by necessity determine 2 final project outcomes. The major categories of expenditures that are identified within the CIP include, but are not limited to: 1. New Public Facilities Planning 2. Street Construction, Maintenance and Reconstruction 3. Utility Construction, Maintenance and Reconstruction 4. Construction, Maintenance and Upgrade of Parks, Playgrounds and Trails 5. Capital Improvements to Existing Facilities 6. Private development infrastructure 7. Capital equipment and vehicle planning needs (Equipment purchases to be determined through normal budgetary process) The City Council, consequently, accepts this document with the provision that capital improvement planning is subject to the dynamics of community growth, political leadership and acknowledges that other unanticipated needs may take precedence over planned projects. RECOMMENDATION The 2009 - 2013 Capital Improvement Plan is the product of collaborative planning efforts by City staff, Park and Recreation Commission, Community Center Advisory Commission and the City Council. Projects have been introduced based on 1) anticipated future growth trends articulated in the City’s current Comprehensive Plan, 2) the natural cycle of deterioration and decay evident in all physically constructed and engineered improvements in the more established areas of the community and 3) capital deficiencies or infrastructure issues brought to the City's attention through a variety of sources. Capital expenditures identified within the CIP are the best estimates available, and once the CIP is adopted, will be reviewed and confirmed through individual feasibility reports where appropriate. I am appreciative of the commitment, good judgment and expertise that each department has contributed to the capital improvement planning process. Respectfully submitted, Jim Dickinson City Administrator 3 CIP PROJECT DEVELOPMENT AND PROCESS AUTHORIZATION SCHEDULE The following process is a Council/staff guideline for authorizing public improvement projects. As this process is controlled by State Statute and other influencing environmental factors, it is subject to change and should be viewed as a guide to assist the Council and public in understanding the public improvement process used by City staff. A separate Council meeting would facilitate each step in the process, and accomplishment of respective activities. As a result, the process time frame is a significant factor affecting City staff’s ability to properly manage and complete approved Council ordered projects within budget and on time. 1. Council Approval of Annual CIP Projects by City Resolution will authorize the following outcomes: a) Staff and/or Consultant preparation of project feasibility studies b) Staff preparation of detailed financial review of project funding sources c) Neighborhood Meeting may be held prior to Feasibility Study subject to need and type of project. TIME FRAME: October-November of each preceding year. 2. Presentation of Feasibility Study a) Feasibility Study Components: 1) Review of Project Engineering and Construction Estimates 2) Total Project Costs (All related project costs, i.e. land, soft costs) 3) Project Financial Plan/Fiscal Implications (Engineering/Finance) 4) Authorization to develop a Preliminary Assessment Roll, if any, for the Public Hearing. (Engineering) If Council accepts Feasibility Study, A Resolution “Accepting Feasibility Study and Setting Date for Public Hearing on the Project” when appropriate (Engineering Department) would initiate the following: 1) Notices mailed to affected Residents per statute requirements no less than 10 days before Public Hearing. (Engineering) 2) Public Hearing Notice is published. Two publications one week apart, with the second publication no less than three days before the hearing. (Engineering/City Clerk) TIME FRAME: February-March-April-May of current year. 3. Neighborhood Meeting – City staff will hold neighborhood project meetings, when appropriate, to review and present Project Feasibility Studies, answer questions and meet with affected property owners. These meetings will include a question and answer component designed specifically to bring awareness to the property owner, obtain citizen input and produce an understanding of the purposes behind the City’s attempts to construct public improvements in the affected area. TIME FRAME: Following the presentation of the Feasibility Study to Council, but prior to the holding of a Public Hearing by Council. 4. Council holds a Public Hearing when appropriate for following purposes: a) Presentation of Project (Engineering Department) b) Presentation of Preliminary Special Assessment Rolls and Financing Implications (Engineering/Finance Department) c) Council to hear Affected Resident Input d) Council determines whether to “order” the public improvement 4 A Council Resolution is drafted “Ordering the Project and Authorizing Preparation of Plans and Specifications” (Engineering Department). Council may ORDER THE IMPROVEMENT after the public hearing is closed or at a subsequent Council Meeting within 6 months of the public hearing date. (Statutory Requirement - Council Resolution ordering project must be approved on 4/5 Council vote if it is Council initiated project with assessments). If Council decides to reject the project as presented, a Council vote should be taken to officially determine the final status of the project. TIME FRAME: April-May-June of current year 5. Plans and Specifications are presented to Council for approval. (Engineering Department) a) A Council Resolution is drafted authorizing the following: 1) Accepting and Approving Project Plans and Specifications 2) Authorizing the Advertisement for Project Bids. Bids are developed and invitation to Bid is processed. Bid opening date is no less than 3 weeks after publication. (Engineering) 3) Authorize staff to pursue an appropriate funding mechanism to underwrite project costs TIME FRAME: May-June of each year 6. Council Acceptance of Project Bids and Awarding of Contracts would authorize the following outcomes: a) A Council Resolution is drafted “Accepting Project Bids and Awarding Contracts” (Engineering) b) Initiation of Project Construction and work (Engineering) TIME FRAME: April-May-June-July of current year. 7. Project Completion a) Council Acceptance of Project b) Final Presentation and Review of Project Costs versus Project Budget by Finance Department. c) If Special Assessments are financing a portion of the Project, A Council Resolution “Setting the Special Assessment Hearing for Project #” is adopted at this same meeting. (Engineering/Finance) TIME FRAME: Upon completion of project. 8. If Special Assessments would finance a portion of the projects costs, Council Holds a Special Assessment Hearing to review the following: a) Affected Property owners would be officially notified per statute no less than two weeks prior to Special Assessment Hearing. (Clerk/Engineering) b) Public Notice is published no less than two weeks prior to Special Hearing per statute (Clerk/Engineering) c) Staff prepares a proposed roll and Council Approves Final Assessment Roll (Engineering/Finance) d) Council consideration of Assessment Appeals and Requested Deferrals filed prior to hearing or during the hearing. e) Meets M.S. Chapter 429 statutory requirements A Council Resolution is drafted “Adopting Final Special Assessment Roll”(Engineering), and is adopted at this meeting. TIME FRAME: October/November of current year depending on finalization of project and status of completion. 5 CITY OF ANDOVER 2009 CIP Expenditures By Department Parks - Oper. Water 3.81% Parks - Proj. 25.77% Street Signs Cent Equip 0.66% 0.39% 0.92% Engineering 7.91% Storm Sewer 2.16% Facility Mgmt. 0.76% Fire 5.92% Streets/Highways 51.70% CITY OF ANDOVER 2009 CIP Expenditures By Year $13,722,000 2013 2012 $11,312,000 2011 $9,197,900 $3,862,500 2010 $3,803,000 2009 2008 Adopted $4,970,644 $-$3,000,000$6,000,000$9,000,000$12,000,000$15,000,000 6 City of Andover, MN Capital Plan 20092013 thru DEPARTMENT SUMMARY Department20092010201120122013Total Central Equipment35,0007,00065,000107,000 Community Center15,0007,000 22,000 Elections110,000 110,000 Engineering301,000384,000355,000356,000357,000 1,753,000 Facility Management29,00033,000332,0004,375,0001,985,000 6,754,000 Fire225,000360,000565,000609,000340,0002,099,000 Park & Rec - Operations145,000188,500119,00045,000155,000652,500 Park & Rec - Projects25,000225,000100,00025,000110,000485,000 Planning & Zoning25,000 25,000 Sanitary Sewer65,0003,007,0001,900,000 4,972,000 Storm Sewer82,000203,00054,00055,00056,000 450,000 Street Signs15,00015,000 Streets / Highways1,966,0002,204,0001,866,0003,016,0002,589,00011,641,000 Water980,00050,0002,785,900931,0008,065,00012,811,900 3,803,0003,862,5009,197,90011,312,00013,722,00041,897,400 GRAND TOTAL 7 City of Andover, MN Capital Plan 20092013 thru FUNDING SOURCE SUMMARY 20092010201120122013Total Source Assessments345,000260,000547,0001,505,000380,0003,037,000 Building Fund1,500,000 1,500,000 Capital Equipment Reserve300,000300,000 Capital Projects Levy74,000188,00077,000102,50080,000 521,500 Central Equipment Fund7,00065,00072,000 Community Center Operations15,0007,00032,00054,000 Construction Seal Coat Fund25,00025,00025,00025,00025,000 125,000 Equipment Bond375,0001,038,500639,000824,000450,0003,326,500 G.O. Bond4,265,000450,000 4,715,000 Municipal State Aid Funds425,000380,000275,000790,000775,0002,645,000 Park Improvement Funds25,000225,000100,00025,000110,000485,000 Road & Bridge Funds1,224,0001,203,0001,324,0001,537,0001,466,000 6,754,000 Sanitary Sewer Fund9,00065,000160,000234,000 Sewer Revenue Bonds2,000,000250,000 2,250,000 Sewer Trunk Fund124,000150,000710,000800,000150,0001,934,000 Storm Sewer Fund73,000113,00091,00055,00056,000 388,000 Water Fund50,00050,000120,00080,50065,000365,500 Water Revenue Bonds930,0002,665,9008,000,00011,595,900 Water Trunk Fund124,000150,000150,0001,021,000150,000 1,595,000 3,803,0003,862,5009,197,90011,312,00013,722,000 GRAND TOTAL 41,897,400 8 City of Andover, MN Capital Plan 20092013 thru PROJECTS & FUNDING SOURCES BY DEPARTMENT DepartmentProject#Priority20092010201120122013 Total Central Equipment Mobile Lifts09-48800-01135,00035,000 Equipment Bond35,00035,000 Replacement - Hotsy Pressure Washer11-48800-0137,000 7,000 Central Equipment Fund7,0007,000 Replacement - Service Truck13-48800-01230,00030,000 Central Equipment Fund30,00030,000 Replacement - Floor Sweeper13-48800-02335,000 35,000 Central Equipment Fund35,00035,000 35,0007,00065,000107,000 Central Equipment Total Community Center Storage Building10-44000-01215,00015,000 Community Center Operations15,00015,000 Battery Pack Replacement - Zamboni11-44000-0127,0007,000 Community Center Operations7,0007,000 15,0007,00022,000 Community Center Total Elections Voting Equipment10-41310-011110,000 110,000 Capital Projects Levy110,000110,000 110,000 110,000 Elections Total Engineering New Development Projects09-41600-011248,000300,000300,000300,000300,000 1,448,000 Sewer Trunk Fund124,000150,000150,000150,000150,000724,000 Water Trunk Fund124,000150,000150,000150,000150,000724,000 Pedestrian Trail Maintenance09-41600-02153,00054,00055,00056,00057,000275,000 Road & Bridge Funds53,00054,00055,00056,00057,000275,000 Replacement - Blazer #1110-41600-01230,00030,000 Equipment Bond30,00030,000 301,000384,000355,000356,000357,0001,753,000 Engineering Total Facility Management Building A - Seal Floor09-41900-0117,0008,0009,000 24,000 Capital Projects Levy7,0008,0009,00024,000 Annual Parking Lot Maintenance09-41900-02122,00023,00024,00025,00026,000 120,000 Capital Projects Levy22,00023,00024,00025,00026,000120,000 9 DepartmentProject#Priority20092010201120122013 Total Carpet Replacement10-41900-01210,00010,000 20,000 Capital Projects Levy10,00010,00020,000 Roof Replacements11-41900-011300,000 300,000 Capital Equipment Reserve300,000300,000 Surface Seal all Brick Structures12-41900-01175,000 75,000 Capital Projects Levy22,50022,500 Community Center Operations32,00032,000 Water Fund20,50020,500 Addition to Storage Building & Vehicle Maint. Shop12-41900-0212,200,0002,200,000 G.O. Bond2,200,0002,200,000 Fire St. #2 Addition with additional land purchase12-41900-032885,000885,000 G.O. Bond885,000885,000 Salt Storage Building12-41900-041400,000400,000 G.O. Bond400,000400,000 Recycling Building & Fence12-41900-051250,000250,000 G.O. Bond250,000250,000 Attached Storage Building12-41900-061250,000250,000 G.O. Bond250,000250,000 Relocate Fuel Station w/ Canopy12-41900-072280,000280,000 G.O. Bond280,000280,000 Land Purchase13-41900-0111,500,0001,500,000 Building Fund1,500,0001,500,000 Pedestrian Tunnel Under Crosstown Blvd.13-41900-021450,000450,000 G.O. Bond450,000450,000 29,00033,000332,0004,375,0001,985,0006,754,000 Facility Management Total Fire Replacement - Fire Engine #1109-42200-011225,000225,000 450,000 Equipment Bond225,000225,000450,000 Replacement - Fire Chief's Vehicle10-42200-01245,000 45,000 Equipment Bond45,00045,000 Replacement - Rescue #1110-42200-02250,000 50,000 Equipment Bond50,00050,000 Replacement - Fire Marshall Vehicle10-42200-03240,000 40,000 Equipment Bond40,00040,000 Replacement - Ladder Truck #1111-42200-011500,000500,000 1,000,000 Equipment Bond500,000500,0001,000,000 Replacement - Grass #3111-42200-02245,000 45,000 Equipment Bond45,00045,000 Water/Ice rescue boat11-42200-03120,000 20,000 Equipment Bond20,00020,000 Replacement - Utility #412-42200-01232,000 32,000 Equipment Bond32,00032,000 Replacement - Utility #512-42200-02232,000 32,000 Equipment Bond32,00032,000 Replacement - Grass #2112-42200-03245,000 45,000 Equipment Bond45,00045,000 Replacement - Tanker #1113-42200-012340,000 340,000 Equipment Bond340,000340,000 225,000360,000565,000609,000340,0002,099,000 Fire Total 10 DepartmentProject#Priority20092010201120122013 Total Park & Rec - Operations Replace/Repair Play Structures - Various Parks09-45000-01145,00045,00045,00045,00045,000 225,000 Capital Projects Levy45,00045,00045,00045,00045,000225,000 Trail Machine w/ Snow Removal Equipment09-45000-021100,000 100,000 Equipment Bond100,000100,000 Replacement - Toro Groundsmaster, #55910-45000-01123,000 23,000 Equipment Bond23,00023,000 Replacement - Large Capacity Lawnmower #58010-45000-021112,000 112,000 Equipment Bond112,000112,000 Zero turn mower10-45000-0318,500 8,500 Equipment Bond8,5008,500 Replacement - Trailer, T-55411-45000-0129,000 9,000 Equipment Bond9,0009,000 Replacement - One Ton Truck w/ Plow, #59911-45000-02265,000 65,000 Equipment Bond65,00065,000 Replacement - One Ton Truck w/ Plow #50313-45000-01265,000 65,000 Equipment Bond65,00065,000 Replacement - One Ton Crew Cab Pickup #50213-45000-02145,000 45,000 Equipment Bond45,00045,000 652,500 145,000188,500119,00045,000155,000 Park & Rec - Operations Total Park & Rec - Projects Annual Miscellaneous Park Projects09-45001-01125,00025,00025,00025,00025,000125,000 Park Improvement Funds25,00025,00025,00025,00025,000125,000 Skate Board Park10-45001-011200,000200,000 Park Improvement Funds200,000200,000 Sophie's South Park11-45001-01175,00075,000 Park Improvement Funds75,00075,000 Andover Lions Park13-45001-01185,00085,000 Park Improvement Funds85,00085,000 25,000225,000100,00025,000110,000485,000 Park & Rec - Projects Total Planning & Zoning Replacement - Ford Taurus #1510-41500-01225,00025,000 Equipment Bond25,00025,000 25,000 25,000 Planning & Zoning Total Sanitary Sewer Replacement - One Ton Truck w/ Plow #9010-48200-01165,000 65,000 Sanitary Sewer Fund65,00065,000 Crosstown Blvd Trunk Sewer Line11-48200-011400,000 400,000 Sewer Trunk Fund400,000400,000 Rural Reserve Trunk Sanitary Sewer11-48200-0212,250,0001,250,000 3,500,000 Assessments250,0001,000,0001,250,000 Sewer Revenue Bonds2,000,000250,0002,250,000 New Jet/Vac Truck11-48200-031357,000357,000 Sanitary Sewer Fund160,000160,000 Sewer Trunk Fund160,000160,000 Storm Sewer Fund37,00037,000 Yellow Pine Lift Station12-48200-011650,000 650,000 11 DepartmentProject#Priority20092010201120122013 Total Sewer Trunk Fund650,000650,000 4,972,000 65,0003,007,0001,900,000 Sanitary Sewer Total Storm Sewer Storm Sewer Improvements09-48300-01152,00053,00054,00055,00056,000270,000 Storm Sewer Fund52,00053,00054,00055,00056,000270,000 Trailer Mounted Grout Plant09-48300-02130,00030,000 Sanitary Sewer Fund9,0009,000 Storm Sewer Fund21,00021,000 Replacement - Elgin Street Sweeper #16910-48300-011150,000 150,000 Equipment Bond90,00090,000 Storm Sewer Fund60,00060,000 82,000203,00054,00055,00056,000450,000 Storm Sewer Total Street Signs Retro-Reflectometer09-43300-01115,00015,000 Equipment Bond15,00015,000 15,00015,000 Street Signs Total Streets / Highways Annual Street Seal Coat Project09-43100-011240,000245,000250,000255,000260,000 1,250,000 Construction Seal Coat Fund20,00020,00020,00020,00020,000100,000 Road & Bridge Funds220,000225,000230,000235,000240,0001,150,000 Annual Street Crack Seal Project09-43100-02185,00085,00085,00085,00085,000 425,000 Construction Seal Coat Fund5,0005,0005,0005,0005,00025,000 Road & Bridge Funds80,00080,00080,00080,00080,000400,000 Annual Street Mill and Overlay09-43100-0311,078,0001,039,0001,189,0001,462,0001,358,0006,126,000 Assessments270,000260,000297,000365,000340,0001,532,000 Road & Bridge Funds808,000779,000892,0001,097,0001,018,0004,594,000 Annual Pavement Markings09-43100-04121,00022,00023,00024,00025,000115,000 Road & Bridge Funds21,00022,00023,00024,00025,000115,000 Annual Curb Replacement09-43100-05142,00043,00044,00045,00046,000 220,000 Road & Bridge Funds42,00043,00044,00045,00046,000220,000 Municipal State Aid Routes / New & Reconstruct09-43100-061500,000380,000930,000815,0002,625,000 Assessments75,000140,00040,000255,000 Municipal State Aid Funds425,000380,000790,000775,0002,370,000 Replacement - Water Tanker #16310-43100-012100,000 100,000 Equipment Bond100,000100,000 Asphalt Paving Machine10-43100-02190,000 90,000 Equipment Bond90,00090,000 Replacement - Dump Truck w/ Snow Removal #19710-43100-031200,000 200,000 Equipment Bond200,000200,000 Intersection Upgrades11-43100-011275,000 275,000 Municipal State Aid Funds275,000275,000 Replacement - Dump Truck w/ Snow Removal #19812-43100-011150,000 150,000 Equipment Bond150,000150,000 Replacement - One Ton Truck w/ Plow #13212-43100-02165,000 65,000 Equipment Bond65,00065,000 1,966,0002,204,0001,866,0003,016,0002,589,00011,641,000 Streets / Highways Total 12 DepartmentProject#Priority20092010201120122013 Total Water Rehabilitation of Wells09-48100-01150,00050,00055,00060,00065,000 280,000 Water Fund50,00050,00055,00060,00065,000280,000 WTP Reclaim Tank Addition09-48100-031930,000 930,000 Water Revenue Bonds930,000930,000 Construct Clearwell at WTP11-48100-0112,665,900 2,665,900 Water Revenue Bonds2,665,9002,665,900 Replacement - One Ton Truck w/ Plow #10511-48100-02165,000 65,000 Water Fund65,00065,000 Construct Well #1012-48100-011181,000 181,000 Water Trunk Fund181,000181,000 Water Main along South Coon Creek Drive12-48100-021500,000 500,000 Water Trunk Fund500,000500,000 Demolish 500,000 Gallon Water Tower12-48100-031190,000 190,000 Water Trunk Fund190,000190,000 Construct Water Treatment Plant #213-48100-0118,000,000 8,000,000 Water Revenue Bonds8,000,0008,000,000 12,811,900 980,00050,0002,785,900931,0008,065,000 Water Total 3,803,0003,862,5009,197,90011,312,00013,722,00041,897,400 GRAND TOTAL 13 This page left blank intentionally. 14 City of Andover, MN Capital Plan 20092013 thru DEPARTMENT SUMMARY Department20092010201120122013Total Community Center15,00015,000 Engineering301,000354,000355,000356,000357,000 1,723,000 Facility Management29,00033,000332,0004,375,0001,985,000 6,754,000 Park & Rec - Operations45,00045,00045,00045,00045,000 225,000 Park & Rec - Projects25,000225,000100,00025,000110,000 485,000 Sanitary Sewer2,650,0001,900,0004,550,000 Storm Sewer52,00053,00054,00055,00056,000270,000 Streets / Highways1,966,0001,814,0001,866,0002,801,0002,589,00011,036,000 Water980,00050,0002,720,900931,0008,065,000 12,746,900 3,398,0002,589,0008,122,90010,488,00013,207,00037,804,900 GRAND TOTAL 15 City of Andover, MN Capital Plan 20092013 thru FUNDING SOURCE SUMMARY 20092010201120122013Total Source Assessments345,000260,000547,0001,505,000380,0003,037,000 Building Fund1,500,000 1,500,000 Capital Equipment Reserve300,000300,000 Capital Projects Levy74,00078,00077,000102,50080,000 411,500 Community Center Operations15,00032,00047,000 Construction Seal Coat Fund25,00025,00025,00025,00025,000125,000 G.O. Bond4,265,000450,000 4,715,000 Municipal State Aid Funds425,000380,000275,000790,000775,0002,645,000 Park Improvement Funds25,000225,000100,00025,000110,000 485,000 Road & Bridge Funds1,224,0001,203,0001,324,0001,537,0001,466,0006,754,000 Sewer Revenue Bonds2,000,000250,0002,250,000 Sewer Trunk Fund124,000150,000550,000800,000150,000 1,774,000 Storm Sewer Fund52,00053,00054,00055,00056,000270,000 Water Fund50,00050,00055,00080,50065,000 300,500 Water Revenue Bonds930,0002,665,9008,000,00011,595,900 Water Trunk Fund124,000150,000150,0001,021,000150,000 1,595,000 3,398,0002,589,0008,122,90010,488,00013,207,00037,804,900 GRAND TOTAL 16 City of Andover, MN Capital Plan 20092013 thru PROJECTS & FUNDING SOURCES BY DEPARTMENT DepartmentProject#Priority20092010201120122013 Total Community Center Storage Building10-44000-01215,00015,000 Community Center Operations15,00015,000 15,000 15,000 Community Center Total Engineering New Development Projects09-41600-011248,000300,000300,000300,000300,0001,448,000 Sewer Trunk Fund124,000150,000150,000150,000150,000724,000 Water Trunk Fund124,000150,000150,000150,000150,000724,000 Pedestrian Trail Maintenance09-41600-02153,00054,00055,00056,00057,000 275,000 Road & Bridge Funds53,00054,00055,00056,00057,000275,000 301,000354,000355,000356,000357,0001,723,000 Engineering Total Facility Management Building A - Seal Floor09-41900-0117,0008,0009,000 24,000 Capital Projects Levy7,0008,0009,00024,000 Annual Parking Lot Maintenance09-41900-02122,00023,00024,00025,00026,000 120,000 Capital Projects Levy22,00023,00024,00025,00026,000120,000 Carpet Replacement10-41900-01210,00010,000 20,000 Capital Projects Levy10,00010,00020,000 Roof Replacements11-41900-011300,000300,000 Capital Equipment Reserve300,000300,000 Surface Seal all Brick Structures12-41900-01175,000 75,000 Capital Projects Levy22,50022,500 Community Center Operations32,00032,000 Water Fund20,50020,500 Addition to Storage Building & Vehicle Maint. Shop12-41900-0212,200,000 2,200,000 G.O. Bond2,200,0002,200,000 Fire St. #2 Addition with additional land purchase12-41900-032885,000 885,000 G.O. Bond885,000885,000 Salt Storage Building12-41900-041400,000 400,000 G.O. Bond400,000400,000 Recycling Building & Fence12-41900-051250,000 250,000 G.O. Bond250,000250,000 Attached Storage Building12-41900-061250,000 250,000 G.O. Bond250,000250,000 Relocate Fuel Station w/ Canopy12-41900-072280,000 280,000 G.O. Bond280,000280,000 Land Purchase13-41900-0111,500,000 1,500,000 Building Fund1,500,0001,500,000 17 DepartmentProject#Priority20092010201120122013 Total Pedestrian Tunnel Under Crosstown Blvd.13-41900-021450,000 450,000 G.O. Bond450,000450,000 29,00033,000332,0004,375,0001,985,0006,754,000 Facility Management Total Park & Rec - Operations Replace/Repair Play Structures - Various Parks09-45000-01145,00045,00045,00045,00045,000 225,000 Capital Projects Levy45,00045,00045,00045,00045,000225,000 225,000 45,00045,00045,00045,00045,000 Park & Rec - Operations Total Park & Rec - Projects Annual Miscellaneous Park Projects09-45001-01125,00025,00025,00025,00025,000125,000 Park Improvement Funds25,00025,00025,00025,00025,000125,000 Skate Board Park10-45001-011200,000200,000 Park Improvement Funds200,000200,000 Sophie's South Park11-45001-01175,00075,000 Park Improvement Funds75,00075,000 Andover Lions Park13-45001-01185,00085,000 Park Improvement Funds85,00085,000 25,000225,000100,00025,000110,000485,000 Park & Rec - Projects Total Sanitary Sewer Crosstown Blvd Trunk Sewer Line11-48200-011400,000 400,000 Sewer Trunk Fund400,000400,000 Rural Reserve Trunk Sanitary Sewer11-48200-0212,250,0001,250,000 3,500,000 Assessments250,0001,000,0001,250,000 Sewer Revenue Bonds2,000,000250,0002,250,000 Yellow Pine Lift Station12-48200-011650,000 650,000 Sewer Trunk Fund650,000650,000 4,550,000 2,650,0001,900,000 Sanitary Sewer Total Storm Sewer Storm Sewer Improvements09-48300-01152,00053,00054,00055,00056,000270,000 Storm Sewer Fund52,00053,00054,00055,00056,000270,000 52,00053,00054,00055,00056,000270,000 Storm Sewer Total Streets / Highways Annual Street Seal Coat Project09-43100-011240,000245,000250,000255,000260,000 1,250,000 Construction Seal Coat Fund20,00020,00020,00020,00020,000100,000 Road & Bridge Funds220,000225,000230,000235,000240,0001,150,000 Annual Street Crack Seal Project09-43100-02185,00085,00085,00085,00085,000 425,000 Construction Seal Coat Fund5,0005,0005,0005,0005,00025,000 Road & Bridge Funds80,00080,00080,00080,00080,000400,000 Annual Street Mill and Overlay09-43100-0311,078,0001,039,0001,189,0001,462,0001,358,0006,126,000 Assessments270,000260,000297,000365,000340,0001,532,000 Road & Bridge Funds808,000779,000892,0001,097,0001,018,0004,594,000 Annual Pavement Markings09-43100-04121,00022,00023,00024,00025,000115,000 Road & Bridge Funds21,00022,00023,00024,00025,000115,000 Annual Curb Replacement09-43100-05142,00043,00044,00045,00046,000 220,000 Road & Bridge Funds42,00043,00044,00045,00046,000220,000 18 DepartmentProject#Priority20092010201120122013 Total Municipal State Aid Routes / New & Reconstruct09-43100-061500,000380,000930,000815,000 2,625,000 Assessments75,000140,00040,000255,000 Municipal State Aid Funds425,000380,000790,000775,0002,370,000 Intersection Upgrades11-43100-011275,000 275,000 Municipal State Aid Funds275,000275,000 11,036,000 1,966,0001,814,0001,866,0002,801,0002,589,000 Streets / Highways Total Water Rehabilitation of Wells09-48100-01150,00050,00055,00060,00065,000280,000 Water Fund50,00050,00055,00060,00065,000280,000 WTP Reclaim Tank Addition09-48100-031930,000930,000 Water Revenue Bonds930,000930,000 Construct Clearwell at WTP11-48100-0112,665,9002,665,900 Water Revenue Bonds2,665,9002,665,900 Construct Well #1012-48100-011181,000181,000 Water Trunk Fund181,000181,000 Water Main along South Coon Creek Drive12-48100-021500,000500,000 Water Trunk Fund500,000500,000 Demolish 500,000 Gallon Water Tower12-48100-031190,000190,000 Water Trunk Fund190,000190,000 Construct Water Treament Plant #213-48100-0118,000,0008,000,000 Water Revenue Bonds8,000,0008,000,000 980,00050,0002,720,900931,0008,065,00012,746,900 Water Total 3,398,0002,589,0008,122,90010,488,00013,207,00037,804,900 GRAND TOTAL 19 Capital Plan 20092013 thru of Andover, MN City 10-44000-01 Project # Storage Building Project Name Priority TypeImprovement2 - Medium Useful LifeContact 25 YearsComm Ctr Manager Category Building ConstructionDepartmentCommunity Center Description Storage Building / Garage for future equipment purchases. The building would be added to the north end of the field house using the existing wall as part of the new structure. Justification As the Community Center continues to grow and acquire more recreational equipment, tables, chairs etc., there will be a lack of storage space. We would only buy equipment if there was a need for it in the field house and if it would help increase rental hours. Some of the equipment would be rented out to users and create additional revenues. Expenditures20092010201120122013Total 15,00015,000 Construction 15,00015,000 Total Funding Sources20092010201120122013Total 15,00015,000 Community Center Operations 15,00015,000 Total Operational Impact/Other The additional space would provide storage for equipment and would need to have electricity and heat. This space would free up some space in what has already become a crowded field house storage room. 20 Capital Plan 20092013 thru of Andover, MN City 09-41600-01 Project # New Development Projects Project Name Priority TypeImprovement1 - High Useful LifeContact 50 YearsDPW / City Engineer Category New Development ProjectsDepartmentEngineering Description New developments include the construction of sanitary sewer, water main, storm sewers and streets. Since the majority of the improvement projects are being privately installed by the developer, the following expenditures are the city's share for trunk water and sewer improvements. Note: All private development construction is dependent upon market conditions, plat approval and normal City development procedures. Justification The development phasing is identified in the City's Comprehensive Plan. Expenditures20092010201120122013Total 248,000300,000300,000300,000300,0001,448,000 Construction 248,000300,000300,000300,000300,0001,448,000 Total Funding Sources20092010201120122013Total 124,000150,000150,000150,000150,000724,000 Sewer Trunk Fund 124,000150,000150,000150,000150,000724,000 Water Trunk Fund 248,000300,000300,000300,000300,0001,448,000 Total Operational Impact/Other Additional maintenance of streets, storm sewer, water main and sanitary sewer will result. Additional streets will be added for snowplowing. 21 Capital Plan 20092013 thru of Andover, MN City 09-41600-02 Project # Pedestrian Trail Maintenance Project Name Priority TypeImprovement1 - High Useful LifeContact 10 YearsDPW / City Engineer Category ImprovementsDepartmentEngineering Description This project provides maintenance such as patching, crack filling and restoration for the city's pedestrian and park trail system. Justification City trails are in need of general maintenance including bituminous patching, crack filling and restoration to maintain the high level of service to pedestrian walkers, bikers and roller bladers. A 5-year capital improvement plan was prepared for the City to identify and prioritize the necessary repairs. Expenditures20092010201120122013Total 53,00054,00055,00056,00057,000275,000 Improvement 53,00054,00055,00056,00057,000275,000 Total Funding Sources20092010201120122013Total 53,00054,00055,00056,00057,000275,000 Road & Bridge Funds 53,00054,00055,00056,00057,000275,000 Total Operational Impact/Other As the city trail system begins to age, general maintenance such as bituminous patching, crack filling and restoration becomes a necessity. The maintenance will allow for a longer service life for the trail system throughout the city. 22 Capital Plan 20092013 thru of Andover, MN City 09-41900-01 Project # Building A - Seal Floor Project Name Priority TypeImprovement1 - High Useful LifeContact 2 YearsDPW / City Engineer Category Facility ManagementDepartmentFacility Management Description Apply a sealant to the cement floor in Building A (large garage). Justification The cement floor in Building A spalds due to daily traffic and salt. Sealing of the floors should be repeated every 2 years to retain the integrity of the floor surface. Without this process, the cement floor would deteriorate and have to be replaced. It is much more cost effective to perform the maintenance than to replace the entire floor. Expenditures20092010201120122013Total 7,0008,0009,00024,000 Facility Maintenance 7,0008,0009,00024,000 Total Funding Sources20092010201120122013Total 7,0008,0009,00024,000 Capital Projects Levy 7,0008,0009,00024,000 Total Operational Impact/Other Proper maintenance extends the life of the cement floor, thus not having to replace it before its life expectancy is up. 23 Capital Plan 20092013 thru of Andover, MN City 09-41900-02 Project # Annual Parking Lot Maintenance Project Name Priority TypeImprovement1 - High Useful LifeContact 10 YearsDPW / City Engineer Category ImprovementsDepartmentFacility Management Description Yearly maintenance of the City parking lots is necessary to extend their useful lives. Parking lots that need maintaining include those at the City Hall complex, Public Works, Community Center, at City parks, and at the Fire Stations. Yearly maintenance may include crack sealing, seal coating, and mill and overlays. Maintenance will generally be completed with the street zones, or on an as needed basis. Justification Completing periodic maintenance on the City parking lots, similar to City streets, will extend the overall design life of the pavement and reduce and/or prolong costly repairs. Expenditures20092010201120122013Total 22,00023,00024,00025,00026,000120,000 Improvement 22,00023,00024,00025,00026,000120,000 Total Funding Sources20092010201120122013Total 22,00023,00024,00025,00026,000120,000 Capital Projects Levy 22,00023,00024,00025,00026,000120,000 Total Operational Impact/Other Maintaining the parking lots will result in less annual maintenance for public works and prolong the life of the pavements. 24 Capital Plan 20092013 thru of Andover, MN City 10-41900-01 Project # Carpet Replacement Project Name Priority TypeImprovement2 - Medium Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentFacility Management Description The replacement of carpet in appropriate areas of all City buildings where deemed necessary. An annual review of all areas will be done to determine the order of replacement. Justification The buildings get a lot of use and, despite the appropriate cleaning and maintenance, the carpeting will need to be replaced. Expenditures20092010201120122013Total 10,00010,00020,000 Facility Maintenance 10,00010,00020,000 Total Funding Sources20092010201120122013Total 10,00010,00020,000 Capital Projects Levy 10,00010,00020,000 Total Operational Impact/Other The carpet replacement will be needed in order to keep the buildings in good repair. Due to heavy use, it is anticipated that all carpeted areas will need to be replaced. 25 Capital Plan 20092013 thru of Andover, MN City 11-41900-01 Project # Roof Replacements Project Name Priority TypeImprovement1 - High Useful LifeContact 20 YearsDPW / City Engineer Category Facility ManagementDepartmentFacility Management Description Remove and replace the existing membrane on the following roofs: City Hall & Senior Center and Fire Stations 1 & 2. City Hall & Senior Center $220,000 Fire Station #1 $45,000 Fire Station #2 $35,000 Justification The roofs are coming of age and and have been receiving annual maintenance for cracking, minor leaks and seams popping. They will continue to be watched and inspected annually to determine when it becomes cost efficient to replace the whole roof. Expenditures20092010201120122013Total 300,000300,000 Improvement 300,000300,000 Total Funding Sources20092010201120122013Total 300,000300,000 Capital Equipment Reserve 300,000300,000 Total Operational Impact/Other Annual inspections and maintenance will be monitored to determine when it becomes cost effective to completely replace the entire roof. 26 Capital Plan 20092013 thru of Andover, MN City 12-41900-01 Project # Surface Seal all Brick Structures Project Name Priority TypeImprovement1 - High Useful LifeContact 5 yearsDPW / City Engineer Category Facility ManagementDepartmentFacility Management Description A surface sealing application would be initiated for all brick and/or block municipal buildings. The buildings include: City Hall, Public Works, Fire Station 1, 2, & 3, Sunshine Park Building, Prairie Knoll Park Building, Andover Station North Park Building, Community Center and all utility department buildings such as the pump houses and treatment facility. Justification This is a necessary maintenance item to ensure the long term integrity of the municipal buildings. Expenditures20092010201120122013Total 75,00075,000 Facility Maintenance 75,00075,000 Total Funding Sources20092010201120122013Total 22,50022,500 Capital Projects Levy 32,00032,000 Community Center Operations 20,50020,500 Water Fund 75,00075,000 Total Operational Impact/Other This will reduce the amount of long term maintenance and repair to the municipal buildings. 27 Capital Plan 20092013 thru of Andover, MN City 12-41900-02 Project # Addition to Storage Building & Vehicle Maint. Shop Project Name Priority TypeImprovement1 - High Useful LifeContact 30 Years +DPW / City Engineer Category Facility ManagementDepartmentFacility Management Description An addition to the north end of Bldg A and be the same in size, 100' x 250' with a 75' x 140' addition to the northwest side of the new vehicle storage garage for the vehicle maintenance shop. This building will be built with cement panels to match the present vehicle garage and would screen Public Works operations from the Community Center/YMCA as proposed in a joint meeting with the Mayor and City Council. Justification Due to the increase of vehicles, equipment and supplies now used by the City of Andover, this vehicle storage building and vehicle maintenance repair shop is badly needed. It is not cost effective to have vehicles or other equipment stored outside. Minnesota's four seasons are way too hard on them and it makes for a much cleaner operation. The vehicle maintenance repair shop has been needed for a long time. The area now used has doors that are not wide enough and work areas for the hydraulic hoist are way too small. Also with the amount of equipment now maintained by our staff, the area is much too small to run a completely safe operation. Expenditures20092010201120122013Total 2,200,0002,200,000 Improvement 2,200,0002,200,000 Total Funding Sources20092010201120122013Total 2,200,0002,200,000 G.O. Bond 2,200,0002,200,000 Total Operational Impact/Other This will impact the life of the vehicles and other equipment by being stored inside and to house our vehicle maintenance mechanics. Over the years, the cost savings have been shown when the proper maintenance of our equipment can be implemented. This building will provide a safe, productive, and healthy operational area for City employees that will benefit the City of Andover for many years. 28 Capital Plan 20092013 thru of Andover, MN City 12-41900-03 Project # Fire St. #2 Addition with additional land purchase Project Name Priority TypeImprovement2 - Medium Useful LifeContact 30 YearsFire Chief Category ImprovementsDepartmentFacility Management Description The addition of one bay to the apparatus area and expanding the existing parking lot to allow for more room and parking space. The project also includes a mill and overlay of the existing parking lots at Station #1 and #2. The additional land would be used to expand the station #2 site to include a training facility that will allow for the appropriate outdoor fire and rescue training, including all types of required live fire scenarios. Justification The additional space to the building will allow for all vehicles to be parked in front of an exit door. The firefighters will not have to move a vehicle in order to get another one out of the building. The additional bay will also make clean up operations after an event much easier. The firefighters will not have to move vehicles out of the building in order to clean hose and equipment. The additional parking space will provide for much needed hard surface training area and more vehicle parking. Replacement of the existing parking lots is necessary due to the heavy fire vehicle traffic. The current use of old houses to be demolished by burning for training purposes is becoming harder to do because of E.P.A. and P.C.A. standards and requirements. The concept of a county wide regional fire training center with joint funding should be considered as a viable option for the station #2 site. Expenditures20092010201120122013Total Land Acquisition 250,000250,000 Equipment 35,00035,000 Improvement 600,000600,000 885,000885,000 Total Funding Sources20092010201120122013Total G.O. Bond 885,000885,000 885,000885,000 Total Operational Impact/Other The additional space will make all fire operations more efficient at this building. Vehicles will not have to be moved in order to get others out and clean-up will be much easier and faster. As part of this project it is suggested that the City look to purchase additional land adjacent to station #2. The building addition is needed but now is the time to also plan for future fire department needs. The strategic planning would call for a fire department training site where outdoor and live burn training could be accomplished. The additional land would be used to expand the station #2 site to include a training facility that will allow for the appropriate outdoor fire and rescue training, including all types of required live fire scenarios. A training building used for rescue and live fire scenarios should also be considered. 29 Capital Plan 20092013 thru of Andover, MN City 12-41900-04 Project # Salt Storage Building Project Name Priority TypeImprovement1 - High Useful LifeContact 30 Years +DPW / City Engineer Category Facility ManagementDepartmentFacility Management Description This salt storage building would be 40' x 50' x 25' high. The City would be able to purchase a season's worth of salt and keep it stored inside this structure out of the elements. All environmental specifications would be met for this type of storage. This facility would be built to blend in with the rest of the City complex and not a sight distraction within the campus. Justification At the present time the City purchases salt from Anoka County, which has been done since the City was first adopted. This puts us at the mercy of the county operations, causing situations such as what time someone will be there to load our trucks and whether they have an adequate supply of salt on hand. We have had good working relations with the county, but they also would like to see us be able to store our own winter supply. Cost savings is also a large part of having our own storage. We can purchase product for less cost and eliminate the 15% administration cost. This building will pay for itself over a short period of time. Expenditures20092010201120122013Total 400,000400,000 Construction 400,000400,000 Total Funding Sources20092010201120122013Total 400,000400,000 G.O. Bond 400,000400,000 Total Operational Impact/Other Having this building right here on campus will save a great deal of personnel time, trucking, and fuel costs. The salt not used could be returned to the storage building and not dumped outside where it gets wet, damaged, or becomes an environmental problem. 30 Capital Plan 20092013 thru of Andover, MN City 12-41900-05 Project # Recycling Building & Fence Project Name Priority TypeImprovement1 - High Useful LifeContact 15-20 YearsDPW / City Engineer Category Facility ManagementDepartmentFacility Management Description This structure will have to be larger than the present building so more recycled materials can be stored inside reducing the chance of the lighter materials blowing out. There also needs to be more room for outside storage including a paved drive surface, it being completely fenced, better security lighting, and updated security camera's. The new location would be located north of the water treatment facility and the building would be constructed of materials that would blend in with the rest of the public works campus. Justification At the present location we have just plain run out of room! The recycling center will have to be moved if the new addition of the vehicle storage building is approved. Also as clean as we try to keep this area, it is probably not the best neighbor to the Community Center since items sometimes blow out of the recycling storage yard. Also it would be best to keep the large trucks off of Tower Drive for safety reason, due to narrow streets and a lot of pedestrian traffic. Expenditures20092010201120122013Total 250,000250,000 Construction 250,000250,000 Total Funding Sources20092010201120122013Total 250,000250,000 G.O. Bond 250,000250,000 Total Operational Impact/Other In the new location we will most likely be able to keep a closer watch on the area. It will still be within the area of the public works so there would be no extra cost in maintenance of the grounds and with a larger area it will be more customer friendly. 31 Capital Plan 20092013 thru of Andover, MN City 12-41900-06 Project # Attached Storage Building Project Name Priority TypeImprovement1 - High Useful LifeContact 25 YearsDPW / City Engineer Category Facility ManagementDepartmentFacility Management Description Three sided building approximately 25' x 50'. It would be used to store equipment not sensitive to the changing temperatures and weather conditions but out of direct sunlight. It would also help to screen the facility. Justification Part of the Public Works site expansion. Protect outdoor vehicles and equipment from changing weather conditions. Expenditures20092010201120122013Total 250,000250,000 Construction 250,000250,000 Total Funding Sources20092010201120122013Total 250,000250,000 G.O. Bond 250,000250,000 Total Operational Impact/Other 32 Capital Plan 20092013 thru of Andover, MN City 12-41900-07 Project # Relocate Fuel Station w/ Canopy Project Name Priority TypeImprovement2 - Medium Useful LifeContact 20 YearsDPW / City Engineer Category Facility ManagementDepartmentFacility Management Description Relocate the fueling station and install two (2) new 10,000 gallon fuel tanks and possibility keep the 2,000 gallon diesel fuel tank for an alternative fuel like E85. Also, install a canopy to cover the fuel pumps and Gasboy fuel monitoring equipment. Justification The canopy would keep the fuel pumps, gasboy equipment, operators dry and help keep sun, rain and snow damage to a minimum. It would also keep the fuel in the tanks from getting contaminated. The larger tanks will allow us to have tanker drops of 7,500 gallons of fuel, saving us money and the frequency of the drops that we now have. The tanks are approximately 18 years old and are warranteed for 30 years. The pumps were installed in 1999 and are in good shape. Expenditures20092010201120122013Total 280,000280,000 Improvement 280,000280,000 Total Funding Sources20092010201120122013Total 280,000280,000 G.O. Bond 280,000280,000 Total Operational Impact/Other The larger tanks will allow us to have a tanker drops of 7,500 gallons of fuel, saving us money and the frequency of the drops that we now have. 33 Capital Plan 20092013 thru of Andover, MN City 13-41900-01 Project # Land Purchase Project Name Priority TypeImprovement1 - High Useful LifeContact UnassignedDPW / City Engineer Category ImprovementsDepartmentFacility Management Description Purchase land west of the Public Works building to be used for a salt storage building, material storage, recycling center and future facility expansion. The City's is currently under contract to purchase this property. The City management team will be evaluating and assisting with the planning and future expansion for the Public Works Facility. Adequate property is necessary to insure that future needs of the community can be met. Justification This is the last opportunity to purchase this property and keep city facilities together in one complex. Future site expansion opportunities are limited without additional property. Expenditures20092010201120122013Total 1,500,0001,500,000 Land Acquisition 1,500,0001,500,000 Total Funding Sources20092010201120122013Total 1,500,0001,500,000 Building Fund 1,500,0001,500,000 Total Operational Impact/Other There is a large cost savings in keeping facilities together, in addition to, having our own salt storage area on the property. The recycling center would be moved away from the park and Community Center improving the general appearance of the area. It would also provide a large storage area for the seal coat rock, sweeping, etc. Open land areas in Andover will soon be a thing of the past. 34 &DSLWDO,PSURYHPHQW3ODQ 3URMHFW1DPH LAND PURCHASE IGHTINGALE N FOX ESTATES HOLLOW ES 4TH  ORIAL BLVD &LW\+DOO 3DUN&RPSOH[ ND   ATES 6XQVKLQH3DUN Location Map /(*(1' Project Location Lots/Parcels Park 03156301,260 Water Feet Right of Way City Limits 35 Capital Plan 20092013 thru of Andover, MN City 13-41900-02 Project # Pedestrian Tunnel Under Crosstown Blvd. Project Name Priority TypeImprovement1 - High Useful LifeContact 30 Years +DPW / City Engineer Category Facility ManagementDepartmentFacility Management Description This would be a pedestrian underpass walkway under Crosstown to accommodate pedestrian traffic from a possible development of a parking lot or other sports fields on the north side of Crosstown Boulevard that could crossunder Crosstown Boulevard to Sunshine Park Facilities or just connect to the cities trail system. Justification This item was discussed at a Council Workshop with the Public Works Department Managers February 16th 2006. For safety and for easy access for crossing Crosstown Boulevard from a future park and/or future parking lot on the north side of Crosstown Boulevard to Sunshine Park on the South side, or just getting to the city trail system the quickest and safest way will be a pedestrian underpass under Crosstown Boulevard. Expenditures20092010201120122013Total 450,000450,000 Improvement 450,000450,000 Total Funding Sources20092010201120122013Total 450,000450,000 G.O. Bond 450,000450,000 Total Operational Impact/Other Connecting of these area's through an underpass will not only benefit pedestrians crossing the roadway, but will also provide a safe passage for personnel and smaller equipment. 36 Capital Plan 20092013 thru of Andover, MN City 09-45000-01 Project # Replace/Repair Play Structures - Various Parks Project Name Priority TypeImprovement1 - High Useful LifeContact 10 YearsDPW / City Engineer Category Park ImprovementsDepartmentPark & Rec - Operations Description Repair to fall zones and achieve ADA accessibility. Replacement of playground equipment and other major replacements, such as short fences on ball fields, soccer goals, or any area of play that does not meet safety specifications. The proposed rebuilds for the next five years are as follows: 2009 - Meadowoods North Park & Tot Lot on 138th Lane NW 2010 - Timber Trails Park & Nordeen's Park 2011 - Pleasant Oaks Park & Woodland Meadows Park 2012 - Green Acres Park & Northwoods East Park 2013 - Langseth Park & Andover Lions Park Justification Old equipment no longer meets ADA requirements, such as entrapments, fall zones or handicap accessibility. Working to bring the parks up to meet all safety requirements. Expenditures20092010201120122013Total Equipment 45,00045,00045,00045,00045,000225,000 45,00045,00045,00045,00045,000225,000 Total Funding Sources20092010201120122013Total 45,00045,00045,00045,00045,000225,000 Capital Projects Levy 45,00045,00045,00045,00045,000225,000 Total Operational Impact/Other Less maintenance and will meet all safety requirements. 37 Capital Improvement Plan Project Name: POTENTIAL PARK RECONSTRUCTION 2010 2013 2011 2010 2009 ROUND LAKE 2011 COON CREEK 2012 COON CREEK 2012 2013 2009 Location Map L E G E N D Project Location Lots/Parcels 02,6255,25010,500 Park Feet Water 38 City Limits Capital Plan 20092013 thru of Andover, MN City 09-45001-01 Project # Annual Miscellaneous Park Projects Project Name Priority TypeImprovement1 - High Useful LifeContact UnassignedAsst.Public Works Director Category Park ImprovementsDepartmentPark & Rec - Projects Description This is for unforeseen or requested miscellaneous projects that may arise during the year, requested by the public, staff, City Council or the Parks and Recreation Commission for each year. Justification This gives flexibility to the City to do certain small-sized projects that may be warranted; for example, purchase of soccer goals. This funding has been recommended by the Park & Recreation Commission. Expenditures20092010201120122013Total 25,00025,00025,00025,00025,000125,000 Improvement 25,00025,00025,00025,00025,000125,000 Total Funding Sources20092010201120122013Total 25,00025,00025,00025,00025,000125,000 Park Improvement Funds 25,00025,00025,00025,00025,000125,000 Total Operational Impact/Other Allows the Park and Recreation Commission to address a variety of different needs throughout the year. 39 Capital Plan 20092013 thru of Andover, MN City 10-45001-01 Project # Skate Board Park Project Name Priority TypeImprovement1 - High Useful LifeContact 10 YearsDPW / City Engineer Category Park ImprovementsDepartmentPark & Rec - Projects Description Due to the poor condition and current location of the skate board equipment, the City needs to reinvest in a new permanent home for the skate board park with new skate equipment. The new location will be the northwest corner of Sunshine Park, just north of the existing small shelter between the existing trail and ball fields. Justification The existing skate board equipment has weakened structurally over the past few years due to the moving and set-up each spring and fall. Expenditures20092010201120122013Total 200,000200,000 Improvement 200,000200,000 Total Funding Sources20092010201120122013Total 200,000200,000 Park Improvement Funds 200,000200,000 Total Operational Impact/Other Routine maintenance will be required to upkeep the park. 40 &DSLWDO,PSURYHPHQW3ODQ 3URMHFW1DPH PROPOSED SKATE PARK  6XQVKLQH3DUN  PINEWOOD Location Map /(*(1' Project Location Lots/Parcels Park 0422040880 Water Feet Right of Way City Limits 41 Capital Plan 20092013 thru of Andover, MN City 11-45001-01 Project # Sophie's South Park Project Name Priority TypeImprovement1 - High Useful LifeContact 15 YearsAsst.Public Works Director Category Park ImprovementsDepartmentPark & Rec - Projects Description Install playground equipment and a basketball court. The park was dedicated as part of the development of Sophie's South. Since no park exists within the general area, it has been recommended to begin developing the park. Justification The improvements have been recommended by the Park & Recreation Commission. Expenditures20092010201120122013Total 75,00075,000 Improvement 75,00075,000 Total Funding Sources20092010201120122013Total 75,00075,000 Park Improvement Funds 75,00075,000 Total Operational Impact/Other Additional long-term maintenance and ultimately replacement will be necessary. 42 Capital Improvement Plan Project Name: SOPHIE'S SOUTH PARK Location Map L E G E N D City Limits Water Park 0220440880 Lots/Parcels Feet Right of Way 43 Project Location Capital Plan 20092013 thru of Andover, MN City 13-45001-01 Project # Andover Lions Park Project Name Priority TypeImprovement1 - High Useful LifeContact 25 YearsAsst.Public Works Director Category Park ImprovementsDepartmentPark & Rec - Projects Description 2013 - Install an 8 foot high outfield fencing with mow strips for ball field ($35,000). 2013 - Install new irrigation system ($50,000). Justification The installation of an outfield fence will allow the ball to stay in play and away from the trail. The installation of an irrigation system will give the players a safer playing surface. This project has been recommended by the Park & Recreation Commission. Expenditures20092010201120122013Total 85,00085,000 Improvement 85,00085,000 Total Funding Sources20092010201120122013Total 85,00085,000 Park Improvement Funds 85,00085,000 Total Operational Impact/Other Additional long-term maintenance and ultimately replacement will be necessary. 44 Capital Improvement Plan Project Name: ANDOVER LIONS PARK Location Map L E G E N D City Limits Water Park 04158301,660 Lots/Parcels Feet Right of Way 45 Project Location Capital Plan 20092013 thru of Andover, MN City 11-48200-01 Project # Crosstown Blvd Trunk Sewer Line Project Name Priority TypeImprovement1 - High Useful LifeContact 50 YearsDPW / City Engineer Category ImprovementsDepartmentSanitary Sewer Description Extend sanitary sewer trunk along Crosstown Boulevard from the railroad tracks east to Prairie Road. It will be necessary to jack the sanitary sewer underneath the railroad. Justification The trunk sanitary sewer will be extended to serve properties adjacent to Crosstown Boulevard and east the railroad tracks and ultimately east of Prairie Road. The extension has been recommended through the sanitary sewer report (2004 Sanitary Sewer Report) and the updated Comprehensive Plan. This project is contingent upon the development east of the railroad tracks. Expenditures20092010201120122013Total 400,000400,000 Improvement 400,000400,000 Total Funding Sources20092010201120122013Total 400,000400,000 Sewer Trunk Fund 400,000400,000 Total Operational Impact/Other Additional routine maintenance including televising and cleaning will be required. 46 Capital Improvement Plan 4VSNIGX2EQI CROSSTOWN BLVD SEWER LINE FIELDS OAKS MILLER'S WOODS 18 MILLER'S WOODS 2ND 158TH AVE MOORES ESTATES Moores Estates PRAIRIE OAKS Sophie's Park Location Map L E G E N D Project Location Lots/Parcels Park 03657301,460 Water Feet Right of Way 47 City Limits Capital Plan 20092013 thru of Andover, MN City 11-48200-02 Project # Rural Reserve Trunk Sanitary Sewer Project Name Priority TypeImprovement1 - High Useful LifeContact 50 YearsDPW / City Engineer Category UnassignedDepartmentSanitary Sewer Description Extension of trunk sanitary sewer from Bunker Lake Boulevard approximately parallel to Coon Crook to serve the Rural Reserve area. The sanitary sewer will be constructed through existing neighborhoods and along South Coon Creek Drive then north into the Rural Reserve Area. It is anticipated that the extension through the Rural Reserve may be constructed the following year, or as the market demands. Justification The trunk sanitary sewer will be extended to serve future development of the Rural Reserve. The timing of this extension will be market driven based upon developer timelines for the Rural Reserve. The extension has been recommended in the Trunk Sanitary Sewer Analysis for Designated Rural Reserve Areas prepared by WSB and Associates. Expenditures20092010201120122013Total 2,250,0001,250,0003,500,000 Construction 2,250,0001,250,0003,500,000 Total Funding Sources20092010201120122013Total 250,0001,000,0001,250,000 Assessments 2,000,000250,0002,250,000 Sewer Revenue Bonds 2,250,0001,250,0003,500,000 Total Operational Impact/Other Additional routine maintenance including televising and cleaning will be required. 48 Capital Improvement Plan 4VSNIGX2EQI RURAL RESERVE TRUNK SANITARY SEWER 7 59 9 20 20 20 20 78 N ENCHANTED DR 58 9 158TH LN 20 20 154TH LN 154TH AVE 7 78 VETERAN'S MEMORIAL BLVD VETERAN'S MEMORIAL BLVD 18 78 149TH LN 6392( 18 9 0%/) 146TH LN 146TH AVE 146TH AVE 78 18 7 140TH AVE 18 78 9 139TH AVE 138TH LN 138TH AVE 137TH LN BUNKER LAKE BLVD 116 116 116 116 Location Map L E G E N D Project Location Lots/Parcels 01,5503,1006,200 Park Feet Water 49 City Limits Capital Plan 20092013 thru of Andover, MN City 12-48200-01 Project # Yellow Pine Lift Station Project Name Priority TypeImprovement1 - High Useful LifeContact 50 YearsDPW / City Engineer Category ImprovementsDepartmentSanitary Sewer Description Install a lift station at Yellow Pine Street to divert flow from the Bluebird Street trunk line to the Pinewood trunk line. The wet well for this lift station was constructed in 2005 as a part of the Crosstown Boulevard Improvements Project. Justification This lift station will allow additional capacity in the Bluebird Street trunk line to serve adjacent properties until the year 2020. This project is development dependent. Expenditures20092010201120122013Total 650,000650,000 Improvement 650,000650,000 Total Funding Sources20092010201120122013Total 650,000650,000 Sewer Trunk Fund 650,000650,000 Total Operational Impact/Other Routine monitoring and maintenance of the lift station will be required. 50 Capital Improvement Plan 4VSNIGX2EQI YELLOW PINE LIFT STATION SHAW'S GLEN MOORES ESTATES Moores Estates GREY OAKS PRAIRIE OAKS Chesterton Commons Park Sophie's Park 78 City Hall Park Complex #1 18 78 Sunshine Park Location Map L E G E N D Project Location Lots/Parcels Park 05501,1002,200 Water Feet Right of Way 51 City Limits Capital Plan 20092013 thru of Andover, MN City 09-48300-01 Project # Storm Sewer Improvements Project Name Priority TypeImprovement1 - High Useful LifeContact 30 Years +DPW / City Engineer Category UtilitiesDepartmentStorm Sewer Description Each year, areas of the City are identified where improvements are required to maintain our storm sewer system. Maintenance items include replacement of failing culverts, catch basins, and storm sewer pipes, erosion issues at storm sewer outfalls, and dredging of ponds and ditches. Justification Maintaining the City's storm sewer system improves water quality and public safety, and reduces the need for costly repairs in the future. Repairing and maintaining these systems also allows public works to focus on and comply with requirements of the NPDES program, such as pipe cleaning, inspections, and sweeping. Expenditures20092010201120122013Total 52,00053,00054,00055,00056,000270,000 Improvement 52,00053,00054,00055,00056,000270,000 Total Funding Sources20092010201120122013Total 52,00053,00054,00055,00056,000270,000 Storm Sewer Fund 52,00053,00054,00055,00056,000270,000 Total Operational Impact/Other Repairing problem areas in the storm sewer system will reduce the yearly maintenance needs placed on the public works personnel. 52 Capital Plan 20092013 thru of Andover, MN City 09-43100-01 Project # Annual Street Seal Coat Project Project Name Priority TypeImprovement1 - High Useful LifeContact 8 YearsDPW / City Engineer Category Park ImprovementsDepartmentStreets / Highways Description This project provides for a seal coat of the streets. Due to rapidly escalating fuel and material prices, funding is not available to complete maintenance on entire zones on an annual basis. Each year, staff will determine an area that can be seal coated within the alloted budget based upon current estimated project costs. Justification Seal coating will extend the useful life of roads by protecting the bituminous from oxidation due to adverse weather conditions (sun, rain, wind, snow, etc.). The prevention of oxidation will prolong the useful life of the pavement and defer the need for a costly reconstruction. Seal coating also improves the skid resistance of the roadway surface by increasing the friction between vehicle tires and the roadway. New developments and reconstructed areas requiring seal coating are not shown on the attached maps. These areas are typically seal coated within three to four years after they are paved. Expenditures20092010201120122013Total 240,000245,000250,000255,000260,0001,250,000 Construction 240,000245,000250,000255,000260,0001,250,000 Total Funding Sources20092010201120122013Total Construction Seal Coat Fund 20,00020,00020,00020,00020,000100,000 Road & Bridge Funds 220,000225,000230,000235,000240,0001,150,000 240,000245,000250,000255,000260,0001,250,000 Total Operational Impact/Other Extending the life of the street will reduce routine maintenance (Crack sealing, pot hole patching, overlays, etc.) and extend the overall design life of the pavement. 53 Capital Plan 20092013 thru of Andover, MN City 09-43100-02 Project # Annual Street Crack Seal Project Project Name Priority TypeImprovement1 - High Useful LifeContact 8 YearsDPW / City Engineer Category Streets/HighwaysDepartmentStreets / Highways Description This project provides for crack sealing of the streets. Due to rapidly escalating fuel and material prices, funding is not available to complete maintenance on entire zones on an annual basis. Each year, staff will determine an area that can be crack sealed within the alloted budget based upon current estimated project costs. Justification The sealing of street cracks will significantly extend the useful life of the streets. This will extend the time frame when a costly street reconstruction project will be necessary. The sealing of cracks in the street surface reduces/eliminates water from entering the road base and subgrade. This process reduces the freeze/thaw cycles of the subgrade, maintaining the integrity of the road. Crack sealing is completed in a particular zone one year prior to seal coating. This allows the crack sealing material to cure and minimize bleed through once seal coated. New developments and reconstructed areas requiring crack seal are not shown on the attached maps. These areas are typically crack sealed three years after they are paved. Expenditures20092010201120122013Total Construction 85,00085,00085,00085,00085,000425,000 85,00085,00085,00085,00085,000425,000 Total Funding Sources20092010201120122013Total Construction Seal Coat Fund 5,0005,0005,0005,0005,00025,000 Road & Bridge Funds 80,00080,00080,00080,00080,000400,000 85,00085,00085,00085,00085,000425,000 Total Operational Impact/Other Sealing the street cracks will reduce routine maintenance by eliminating the source of degradation resulting from moisture in the road subgrade. 54 Capital Plan 20092013 thru of Andover, MN City 09-43100-03 Project # Annual Street Mill and Overlay Project Name Priority TypeImprovement1 - High Useful LifeContact 20 YearsDPW / City Engineer Category Streets/HighwaysDepartmentStreets / Highways Description The Street Mill and Overlay projects will consist of milling the existing street surface and constructing a new asphalt surface. Minor shouldering and restoration work will be included with the project. In developments that have existing bituminous curb or no curb or ditch, concrete curb and gutter will be constructed. 25% of the total project costs are assessed to the benefiting properties in each development. This program helps to maintain the integrity and value of the communities street infrastructure. Areas to be reconstructed are shown on the attached maps and are listed below. The timing of reconstruction of developments more than two years out may be revised as street conditions and ratings are reviewed on an annual basis. Additional developments may be added to the schedule or projects moved up if it is advantageous to reconstruct them in conjunction with other nearby projects. 2009 - Woodland Meadows - North Half 2010 - Woodland Meadows - South Half 2011 - Rolling Forest, Nordeen's Addition, Genthon Ponds, Flintwood Street 2012 - Stenquist Addition, Johnson's Oakmount Terrace, Ivywood Estates 2013 - Prairie Meadows, Alladin Acres, Enchanted Drive Area, Aztec St/158th Ave Justification The streets in these neighborhoods are generally in excess of 20 years old and are in need of rehabilitation. The intent of this Street Mill and Overlay is to provide the community with a high quality transportation system and maintain a constant upkeep of the City's street infrastructure. Expenditures20092010201120122013Total 1,078,0001,039,0001,189,0001,462,0001,358,0006,126,000 Construction 1,078,0001,039,0001,189,0001,462,0001,358,0006,126,000 Total Funding Sources20092010201120122013Total Assessments 270,000260,000297,000365,000340,0001,532,000 Road & Bridge Funds 808,000779,000892,0001,097,0001,018,0004,594,000 1,078,0001,039,0001,189,0001,462,0001,358,0006,126,000 Total Operational Impact/Other The rehabilitation of the streets will reduce the routine maintenance (Crack sealing, pot hole patching, etc..) in the area. Long term, this reconditioning will prolong the structural stability of the roadway making for a longer serviceable life. 55 Capital Improvement Plan 4VSNIGX2EQI ANNUAL MILL AND OVERLAY (2009) WOODLAND MEADOWS - NORTH HALF Location Map L E G E N D Project Location Lots/Parcels Park 03857701,540 Water Feet Right of Way 56 City Limits Capital Improvement Plan 4VSNIGX2EQI ANNUAL MILL AND OVERLAY (2010) WOODLAND MEADOWS - SOUTH HALF 59 WOODLAND MEADOWS 2ND ADD Location Map L E G E N D Project Location Lots/Parcels Park 03857701,540 Water Feet Right of Way 57 City Limits Capital Improvement Plan 4VSNIGX2EQI ANNUAL MILL AND OVERLAY (2011) NORDEEN'S ADDITION Location Map L E G E N D Project Location Lots/Parcels Park 03557101,420 Water Feet Right of Way City Limits 58 Capital Improvement Plan Project Name: ANNUAL MILL AND OVERLAY (2011) GENTHON PONDS AND FLINTWOOD STREET Location Map L E G E N D Project Location Lots/Parcels Park 03857701,540 Water Feet Right of Way City Limits 59 Capital Improvement Plan Project Name: ANNUAL MILL AND OVERLAY (2011) ROLLING FOREST Location Map L E G E N D Project Location Lots/Parcels Park 03557101,420 Water Feet Right of Way 60 City Limits Capital Improvement Plan Project Name: ANNUAL MILL AND OVERLAY (2012) IVYWOOD ESTATES Location Map L E G E N D Project Location Lots/Parcels Park 0312.56251,250 Water Feet Right of Way City Limits 61 Capital Improvement Plan Project Name: ANNUAL MILL AND OVERLAY (2012) JOHNSON'S OAKMOUNT TERRACE Location Map L E G E N D Project Location Lots/Parcels Park 02505001,000 Water Feet Right of Way City Limits 62 Capital Improvement Plan Project Name: ANNUAL MILL AND OVERLAY (2012) STENQUIST ADDITION Location Map L E G E N D Project Location Lots/Parcels Park 0312.56251,250 Water Feet Right of Way 63 City Limits Capital Improvement Plan 4VSNIGX2EQI ANNUAL MILL AND OVERLAY (2013) PRAIRIE MEADOWS 9 DEER OAKS SYLVESTER ADD PRAIRIE MEADOWS TIMBER MEADOWS Location Map L E G E N D Project Location Lots/Parcels Park 0237.5475950 Water Feet Right of Way 64 City Limits Capital Improvement Plan 4VSNIGX2EQI ANNUAL MILL AND OVERLAY (2013) ALADDIN ACRES, ENCHANTED DR AREA, AND AZTEC ST / 158TH AVE SILVER MEADOWS WEST ALADDIN ACRES N ENCHANTED DR FOX MEADOWS Fox Meadows Location Map L E G E N D Project Location Lots/Parcels Park 03106201,240 Water Feet Right of Way 65 City Limits Capital Plan 20092013 thru of Andover, MN City 09-43100-04 Project # Annual Pavement Markings Project Name Priority TypeImprovement1 - High Useful LifeContact 1-2 YearsDPW / City Engineer Category ImprovementsDepartmentStreets / Highways Description The pavement striping for City streets is conducted one time per year. This includes centerline striping and shoulder striping. Striping enhances the safety of the roadway by directing traffic to the correct lane movement. The Federal Highway Administration is currently reviewing reflective standards for pavement markings. In the near future the City may have to stripe twice per year to meet new standards. If this is approved, it will double the cost of pavement markings per year. Justification Striping is required through the local and state agencies. A reflective standard is required. Restriping annually maintains the pavement markings to the required standards. Expenditures20092010201120122013Total 21,00022,00023,00024,00025,000115,000 Improvement 21,00022,00023,00024,00025,000115,000 Total Funding Sources20092010201120122013Total 21,00022,00023,00024,00025,000115,000 Road & Bridge Funds 21,00022,00023,00024,00025,000115,000 Total Operational Impact/Other The pavement markings are contracted out each year adding virtually no operational impact. 66 Capital Plan 20092013 thru of Andover, MN City 09-43100-05 Project # Annual Curb Replacement Project Name Priority TypeImprovement1 - High Useful LifeContact 30 YearsDPW / City Engineer Category Streets/HighwaysDepartmentStreets / Highways Description Damaged and failing concrete curb and gutter throughout the City needs to be repaired or replaced to help maintain the integrity of the roadway system. Replacing damaged or failing sections of curb and gutter helps with drainage of the roadway and prolongs the life of the street system. Justification The majority of the concrete curb and gutter throughout the City is in relatively good condition. However, there are isolated areas that need rehabilititation every year. Failing or damaged sections of concrete curb and gutter are removed and replaced. Replacing damaged sections of concrete curb and gutter maintains the integrity of and prolongs the life of the City's street infrastructure. Expenditures20092010201120122013Total 42,00043,00044,00045,00046,000220,000 Construction 42,00043,00044,00045,00046,000220,000 Total Funding Sources20092010201120122013Total 42,00043,00044,00045,00046,000220,000 Road & Bridge Funds 42,00043,00044,00045,00046,000220,000 Total Operational Impact/Other Repairing failing or damaged sections of curb and gutter reduces the routine maintenance required by the public works department. 67 Capital Plan 20092013 thru of Andover, MN City 09-43100-06 Project # Municipal State Aid Routes / New & Reconstruct Project Name Priority TypeImprovement1 - High Useful LifeContact 20 YearsDPW / City Engineer Category Streets/HighwaysDepartmentStreets / Highways Description The following projects are proposed to be constructed and/or rehabilitated to meet State Aid Standards. The rehabilitation projects will consist of milling the existing street surface, constructing concrete curb and gutter where it does not exist, repairing storm sewer systems, and improving storm drainage. 2009: 157th Avenue (Prairie Road - University Avenue) $500,000 2010: 1.5" Overlay on Prairie Road (Andover Blvd - Crosstown Blvd) $380,000 2012: South Coon Creek Drive (Round Lake Blvd - Crosstown) $930,000 2013: Nightingale Street (Crosstown Blvd - 161st Ave) $817,000 Justification 2009: 157th Avenue (Prairie Road - University Ave) - Upgrade needed to maintain integrity of State Aid roadway infrastructure. 2010: 1.5" Overlay on Prairie Road (Andover Blvd - 157th Ave) - Upgrade needed to maintain integrity of State Aid roadway infrastructure. 2012: South Coon Creek Drive (Round Lake Blvd - Crosstown) - Upgrade needed to maintain integrity of State Aid roadway infrastructure. 2013: Nightingale Street (Crosstown Blvd - 161st Ave) - Upgrade needed to maintain integrity of State Aid roadway infrastructure. Expenditures20092010201120122013Total Construction 500,000380,000930,000815,0002,625,000 500,000380,000930,000815,0002,625,000 Total Funding Sources20092010201120122013Total 75,000140,00040,000255,000 Assessments 425,000380,000790,000775,0002,370,000 Municipal State Aid Funds 500,000380,000930,000815,0002,625,000 Total Operational Impact/Other Rehabilitating the roads will reduce the amount of routine maintenance along these sections of roadway and provide a safer and higher quality transportation system. 68 Capital Improvement Plan Project Name: MUNICIPAL STATE AID ROUTES RECONSTRUCT 2009 Location Map L E G E N D Project Location Lots/Parcels Park 04008001,600 Water Feet Right of Way 69 City Limits Capital Improvement Plan 4VSNIGX2EQI MUNICIPAL STATE AID ROUTES OVERLAY 2010 MOORES ESTATES Moores Estates Nordeen's Landlocked Park NORDEEN ADDITION PRAIRIE OAKS Sophie's Park Prairie BARNES ROLLING OAKS 2ND ADD Knoll Park Oak Bluff Park 145TH LN BARNES ROLLING OAKS Location Map L E G E N D Project Location Lots/Parcels Park 07501,5003,000 Water Feet Right of Way City Limits 70 Capital Improvement Plan 4VSNIGX2EQI MUNICIPAL STATE AID ROUTES RECONSTRUCT 2012 WOODLAND ESTATES 6392( 9 0%/) Round Lake Boat Landing KENSINGTON ESTATES SHADY KNOLL 18 Creekridge Park WOODLAND GOLF KADLEC 2ND ADD VILLAS CROSSTOWN MEADOWS WOODLAND POND Green SMITHS QUICKSTROM Acres 2ND ADD Park ADD GREEN ACRES KENSINGTON North WoodsRed Oaks ESTATES 5TH North WoodsWest Park West Park East Park Rose Park RED OAKS MANOR 3RD ADD 140TH AVE 18 RED OAKS MANOR WOODLAND CREEK NORTHWOODS ADDITION 2ND ADD PLAT 2 RED OAKS RED OAKS MANOR 4TH MANOR 2ND ADD NORTHGLEN 138TH LN WOODLAND CREEK RED OAKS MANOR CREEKHAVEN 5TH ADD TOWNHOMES 137TH LN Location Map L E G E N D Project Location Lots/Parcels Park 07501,5003,000 Water Feet Right of Way 71 City Limits Capital Improvement Plan 4VSNIGX2EQI MUNICIPAL STATE AID ROUTES RECONSTRUCT 2013 20 20 SHADY OAK COVE 78 MAPLE HOLLOW CHESTERTON PRAIRIE COMMONS COVE NORTH 2ND ANOKA CO HWY R/W PLAT 02 158TH LN Woodland Crossings CHESTERTON Park OAK VIEW PARK COMMONS NORTH CARDINAL RIDGE SHAW'S GLEN GREY OAKS NIGHTINGALE ESTATES 2ND NIGHTINGALE 154TH LN WOODLAND 154TH AVE ESTATES 3RD NIGHTINGALE Chesterton ESTATES Commons Park FOX ESTATES 6TH ADD HOLLOW WOODLAND ESTATES 4TH 78 VETERAN'S MEMORIAL BLVD Woodland Estates Park VETERAN'S MEMORIAL BLVD City Hall Park Complex #1 WOODLAND ESTATES 2ND 18 Location Map L E G E N D Project Location Lots/Parcels Park 06251,2502,500 Water Feet Right of Way 72 City Limits Capital Plan 20092013 thru of Andover, MN City 11-43100-01 Project # Intersection Upgrades Project Name Priority TypeImprovement1 - High Useful LifeContact 25 YearsDPW / City Engineer Category ImprovementsDepartmentStreets / Highways Description 2011 - Construction of a traffic signal at South Coon Creek Drive and Round Lake Blvd. Minor lane widening may be needed but turn lane construction would not be included in this project ($275,000). Justification Intersection upgrades are necessary due to the increased development and demands on the transportation system, the need for safety improvements, and to comply with Anoka County Highway Department requirements. Expenditures20092010201120122013Total 275,000275,000 Construction 275,000275,000 Total Funding Sources20092010201120122013Total 275,000275,000 Municipal State Aid Funds 275,000275,000 Total Operational Impact/Other Improvements will improve the flow of traffic and will improve the safety of vehicles, pedestrians and bicyclists. 73 Capital Improvement Plan 4VSNIGX2EQI INTERSECTION UPGRADES 0%/) Round Lake Boat Landing ANDOVER BOUNDRY COMM PLAT 1 South Coon Creek Dr & Round Lake Blvd (2011) Creekridge Park WOODLAND GOLF WANDERSEE KADLEC 2ND ADD ADD VILLAS ROSELLAS ADD Location Map L E G E N D Project Location Lots/Parcels Park 03507001,400 Water Feet Right of Way 74 City Limits Capital Plan 20092013 thru of Andover, MN City 09-48100-01 Project # Rehabilitation of Wells Project Name Priority TypeImprovement1 - High Useful LifeContact 7 YearsDPW / City Engineer Category ImprovementsDepartmentWater Description The motor, pump and column pipe are taken out for inspection and worn parts are replaced. The well is televised to determine the depth and condition. If the well is at or close to the original drill depth everything is put back in place. The well may need to be cleaned out to the original depth if there is a substantial decrease in the depth. Justification To make sure the well is operational to what it is designed for and to correct any problems that may affect our ability to produce the amount of water needed to meet the demand. A complete inspection and maintenance overhall is performed on each well a minimum of once every seven (7) years. Well #3 is in line for this type of rehabilitation. This maintenance will also maximize the pumping rate of the well. Even though this is a peaking well and other issues are related to it, the maintenance is required to make sure the well works efficiently. Expenditures20092010201120122013Total 50,00050,00055,00060,00065,000280,000 Improvement 50,00050,00055,00060,00065,000280,000 Total Funding Sources20092010201120122013Total 50,00050,00055,00060,00065,000280,000 Water Fund 50,00050,00055,00060,00065,000280,000 Total Operational Impact/Other This would be done at such a time that it would not affect the demand needs of the system. Typically done late fall. 75 Capital Plan 20092013 thru of Andover, MN City 09-48100-03 Project # WTP Reclaim Tank Addition Project Name Priority TypeImprovement1 - High Useful LifeContact 30 YearsDPW / City Engineer Category ImprovementsDepartmentWater Description Add an additional 200,000 gallon reclaim tank and process piping to the water plant. Justification In order to maintain a certain level of operations and meet the demands of the water population, an additional 200,000 gallon reclaim tank is needed. Staff has noticed that during the high peaking months of May through September, the water plant needs to backwash the filters on a daily basis. With the single reclaim tank now in operation, the daily operations will run into difficulty with backwashing filters during the peak times. As the population continues to increase, more demand is put on the system to function at a high rate of production. With an increase in tank size, the operations can continue without much interruption when backwashing the filters. Expenditures20092010201120122013Total 930,000930,000 Improvement 930,000930,000 Total Funding Sources20092010201120122013Total 930,000930,000 Water Revenue Bonds 930,000930,000 Total Operational Impact/Other With additional storage for backwashing, the filtering process can be done without shutting down certain wells in order to keep the filters from over loading. With an increase in reclaim tank capacity, the water plant filters would be able to operate continuously thus keeping the amount of water filtered at it's highest capacity. 76 Capital Plan 20092013 thru of Andover, MN City 11-48100-01 Project # Construct Clearwell at WTP Project Name Priority TypeImprovement1 - High Useful LifeContact 50 YearsDPW / City Engineer Category ImprovementsDepartmentWater Description Construct a 2 million gallon clearwell adjacent to the water treatment plant. Justification In order to adequately supply treated water at an acceptable pressure to the entire distribution system in Andover, a two million gallon clearwell must be constructed near the water treatment plant. The existing 500,000 water tower in the southwest part of town would be demolished as part of this process. Construction of this clearwell and demolition of the existing 500,000 gallon tower would eliminate the low pressure zone currently in the southwest part of town. Expenditures20092010201120122013Total 2,665,9002,665,900 Construction 2,665,9002,665,900 Total Funding Sources20092010201120122013Total 2,665,9002,665,900 Water Revenue Bonds 2,665,9002,665,900 Total Operational Impact/Other Additional maintenance and monitoring would be required of the Sewer and Water department. 77 Capital Plan 20092013 thru of Andover, MN City 12-48100-01 Project # Construct Well #10 Project Name Priority TypeImprovement1 - High Useful LifeContact 25 YearsDPW / City Engineer Category ImprovementsDepartmentWater Description Construct well #10 in Shadowbrook 2nd Addition on an existing city-owned lot to provide municipal water due to the increased demand. Justification As the City's population continues to grow, the demand for municipal water increases. Continuing to add wells to the City's water system is essential to meet the demand. Expenditures20092010201120122013Total 181,000181,000 Improvement 181,000181,000 Total Funding Sources20092010201120122013Total 181,000181,000 Water Trunk Fund 181,000181,000 Total Operational Impact/Other Increase energy and operating costs to the water system. 78 Capital Improvement Plan 4VSNIGX2EQI CONSTRUCT WELL NO. 10 (2012) CONSTRUCT WATER TREATMENT PLANT (2013) Location Map L E G E N D Project Location Lots/Parcels Park 0175350700 Water Feet Right of Way 79 City Limits Capital Plan 20092013 thru of Andover, MN City 12-48100-02 Project # Water Main along South Coon Creek Drive Project Name Priority TypeImprovement1 - High Useful LifeContact 50 YearsDPW / City Engineer Category ImprovementsDepartmentWater Description Install a 12" water main along South Coon Creek Drive from 145th Avenue to Crosstown Boulevard. Justification Construction of a water main along South Coon Creek Drive will allow the existing water distribution system between the east and west sides of town to be looped. The only existing connection between the two parts of town is along Bunker Lake Boulevard. Looping of the system will allow treated water to be continuously supplied to all residents in town on the water system. It will also help alleviate the pressure variance that is experienced between the east and west sides of town. Coon Creek Boulevard is scheduled for reconstruction in 2012. It would be advantageous to construct the water main concurrently with the roadway reconstruction. Expenditures20092010201120122013Total 500,000500,000 Improvement 500,000500,000 Total Funding Sources20092010201120122013Total 500,000500,000 Water Trunk Fund 500,000500,000 Total Operational Impact/Other Additional maintenance and flushing requirements for the water main system will result. Construction of this system would make management of the water distribution system for the City as a whole easier by eliminating the two pressure zones. 80 Capital Improvement Plan 4VSNIGX2EQI WATER MAIN ALONG SOUTH COON CREEK BLVD 6392( 9 0%/) Round Lake Boat Landing KENSINGTON ESTATES SHADY KNOLL 18 Creekridge Park WOODLAND GOLF VILLAS CROSSTOWN MEADOWS WOODLAND POND Green SMITHS Acres 2ND ADD Park GREEN ACRES KENSINGTON North Woods Red Oaks ESTATES 5TH North Woods West Park West Park East Park RED OAKS MANOR 3RD ADD 18 RED OAKS MANOR WOODLAND CREEK NORTHWOODS ADDITION 2ND ADD PLAT 2 RED OAKS RED OAKS MANOR 4TH MANOR 2ND ADD Location Map L E G E N D Project Location Lots/Parcels Park 06501,3002,600 Water Feet Right of Way 81 City Limits Capital Plan 20092013 thru of Andover, MN City 12-48100-03 Project # Demolish 500,000 Gallon Water Tower Project Name Priority TypeImprovement1 - High Useful LifeContact UnassignedDPW / City Engineer Category ImprovementsDepartmentWater Description Demolish the existing 500,000 gallon water tower located on the west side of town. Justification The existing 500,000 gallon water tower will be demolished and replaced by a new two million gallon water tower so the City's water distribution system can be managed under one pressure zone, providing treated water to all residents on the system. Expenditures20092010201120122013Total 190,000190,000 Improvement 190,000190,000 Total Funding Sources20092010201120122013Total 190,000190,000 Water Trunk Fund 190,000190,000 Total Operational Impact/Other Maintenance of the existing water tower will no longer be required. 82 Capital Plan 20092013 thru of Andover, MN City 13-48100-01 Project # Construct Water Treatment Plant #2 Project Name Priority TypeImprovement1 - High Useful LifeContact 30 YearsDPW / City Engineer Category ImprovementsDepartmentWater Description Construct Water Treatment Plant No. 2 in Shadowbrook Development. Justification According to the Water Comprehensive Plan, the time table for the second water treatment facility will be needed at this time. The water treatment plant that went on line in October 2003 is nearing the designed maximum for the amount of water treated per day. By adding this plant in the Shadowbrook area, flows and pressures will also increase benefiting the entire system. This will also minimize the need to operate wells 2 and 3 that are having some quality issues. Expenditures20092010201120122013Total 8,000,0008,000,000 Construction 8,000,0008,000,000 Total Funding Sources20092010201120122013Total 8,000,0008,000,000 Water Revenue Bonds 8,000,0008,000,000 Total Operational Impact/Other There will be additional costs for operating, such as electricity, natural gas and chemicals. 83 Capital Improvement Plan 4VSNIGX2EQI CONSTRUCT WELL NO. 10 (2012) CONSTRUCT WATER TREATMENT PLANT (2013) Location Map L E G E N D Project Location Lots/Parcels Park 0175350700 Water Feet Right of Way 84 City Limits City of Andover, MN Capital Plan 20092013 thru DEPARTMENT SUMMARY Department20092010201120122013Total Central Equipment35,0007,00065,000107,000 Community Center7,000 7,000 Elections110,000 110,000 Engineering30,000 30,000 Fire225,000360,000565,000609,000340,000 2,099,000 Park & Rec - Operations100,000143,50074,000110,000427,500 Planning & Zoning25,00025,000 Sanitary Sewer65,000357,000422,000 Storm Sewer30,000150,000 180,000 Street Signs15,000 15,000 Streets / Highways390,000215,000 605,000 Water65,00065,000 405,0001,273,5001,075,000824,000515,000 4,092,500 GRAND TOTAL 85 City of Andover, MN Capital Plan 20092013 thru FUNDING SOURCE SUMMARY 20092010201120122013Total Source Capital Projects Levy110,000110,000 Central Equipment Fund7,00065,000 72,000 Community Center Operations7,0007,000 Equipment Bond375,0001,038,500639,000824,000450,000 3,326,500 Sanitary Sewer Fund9,00065,000160,000234,000 Sewer Trunk Fund160,000160,000 Storm Sewer Fund21,00060,00037,000 118,000 Water Fund65,00065,000 405,0001,273,5001,075,000824,000515,0004,092,500 GRAND TOTAL 86 City of Andover, MN Capital Plan 20092013 thru PROJECTS & FUNDING SOURCES BY DEPARTMENT DepartmentProject#Priority20092010201120122013 Total Central Equipment Mobile Lifts09-48800-01135,00035,000 Equipment Bond35,00035,000 Replacement - Hotsy Pressure Washer11-48800-0137,000 7,000 Central Equipment Fund7,0007,000 Replacement - Service Truck13-48800-01230,00030,000 Central Equipment Fund30,00030,000 Replacement - Floor Sweeper13-48800-02335,000 35,000 Central Equipment Fund35,00035,000 35,0007,00065,000107,000 Central Equipment Total Community Center Battery Pack Replacement - Zamboni11-44000-0127,0007,000 Community Center Operations7,0007,000 7,0007,000 Community Center Total Elections Voting Equipment10-41310-011110,000 110,000 Capital Projects Levy110,000110,000 110,000 110,000 Elections Total Engineering Replacement - Blazer #1110-41600-01230,000 30,000 Equipment Bond30,00030,000 30,000 30,000 Engineering Total Fire Replacement - Fire Engine #1109-42200-011225,000225,000450,000 Equipment Bond225,000225,000450,000 Replacement - Fire Chief's Vehicle10-42200-01245,00045,000 Equipment Bond45,00045,000 Replacement - Rescue #1110-42200-02250,00050,000 Equipment Bond50,00050,000 Replacement - Fire Marshall Vehicle10-42200-03240,00040,000 Equipment Bond40,00040,000 Replacement - Ladder Truck #1111-42200-011500,000500,0001,000,000 Equipment Bond500,000500,0001,000,000 Replacement - Grass #3111-42200-02245,00045,000 87 DepartmentProject#Priority20092010201120122013 Total Equipment Bond45,00045,000 Water/Ice rescue boat11-42200-03120,000 20,000 Equipment Bond20,00020,000 Replacement - Utility #412-42200-01232,000 32,000 Equipment Bond32,00032,000 Replacement - Utility #512-42200-02232,000 32,000 Equipment Bond32,00032,000 Replacement - Grass #2112-42200-03245,000 45,000 Equipment Bond45,00045,000 Replacement - Tanker #1113-42200-012340,000340,000 Equipment Bond340,000340,000 2,099,000 225,000360,000565,000609,000340,000 Fire Total Park & Rec - Operations Trail Machine w/ Snow Removal Equipment09-45000-021100,000100,000 Equipment Bond100,000100,000 Replacement - Toro Groundsmaster, #55910-45000-01123,00023,000 Equipment Bond23,00023,000 Replacement - Large Capacity Lawnmower #58010-45000-021112,000112,000 Equipment Bond112,000112,000 Zero turn mower10-45000-0318,5008,500 Equipment Bond8,5008,500 Replacement - Trailer, T-55411-45000-0129,0009,000 Equipment Bond9,0009,000 Replacement - One Ton Truck w/ Plow, #59911-45000-02265,00065,000 Equipment Bond65,00065,000 Replacement - One Ton Truck w/ Plow #50313-45000-01265,00065,000 Equipment Bond65,00065,000 Replacement - One Ton Crew Cab Pickup #50213-45000-02145,00045,000 Equipment Bond45,00045,000 100,000143,50074,000110,000427,500 Park & Rec - Operations Total Planning & Zoning Replacement - Ford Taurus #1510-41500-01225,000 25,000 Equipment Bond25,00025,000 25,000 25,000 Planning & Zoning Total Sanitary Sewer Replacement - One Ton Truck w/ Plow #9010-48200-01165,00065,000 Sanitary Sewer Fund65,00065,000 New Jet/Vac Truck11-48200-031357,000357,000 Sanitary Sewer Fund160,000160,000 Sewer Trunk Fund160,000160,000 Storm Sewer Fund37,00037,000 65,000357,000422,000 Sanitary Sewer Total Storm Sewer Trailer Mounted Grout Plant09-48300-02130,00030,000 Sanitary Sewer Fund9,0009,000 Storm Sewer Fund21,00021,000 88 DepartmentProject#Priority20092010201120122013 Total Replacement - Elgin Street Sweeper #16910-48300-011150,000 150,000 Equipment Bond90,00090,000 Storm Sewer Fund60,00060,000 180,000 30,000150,000 Storm Sewer Total Street Signs Retro-Reflectometer09-43300-01115,00015,000 Equipment Bond15,00015,000 15,00015,000 Street Signs Total Streets / Highways Replacement - Water Tanker #16310-43100-012100,000 100,000 Equipment Bond100,000100,000 Asphalt Paving Machine10-43100-02190,00090,000 Equipment Bond90,00090,000 Replacement - Dump Truck w/ Snow Removal #19710-43100-031200,000 200,000 Equipment Bond200,000200,000 Replacement - Dump Truck w/ Snow Removal #19812-43100-011150,000 150,000 Equipment Bond150,000150,000 Replacement - One Ton Truck w/ Plow #13212-43100-02165,000 65,000 Equipment Bond65,00065,000 390,000215,000605,000 Streets / Highways Total Water Replacement - One Ton Truck w/ Plow #10511-48100-02165,000 65,000 Water Fund65,00065,000 65,000 65,000 Water Total 405,0001,273,5001,075,000824,000515,0004,092,500 GRAND TOTAL 89 Capital Plan 20092013 thru of Andover, MN City 09-48800-01 Project # Mobile Lifts Project Name Priority TypeEquipment1 - High Useful LifeContact 15 YearsDPW / City Engineer Category EquipmentDepartmentCentral Equipment Description Mobile lifts used for lifting vehicles during service, inspections and repairs. Justification The existing stationary lifts cannot lift the large plow trucks and fire trucks for service, inspections, and repairs. The mobile lifts can also be tucked away when not in use. Expenditures20092010201120122013Total 35,00035,000 Equipment 35,00035,000 Total Funding Sources20092010201120122013Total 35,00035,000 Equipment Bond 35,00035,000 Total Operational Impact/Other Mobile lifts will provide a more efficient process to service City vehicles by allowing large fire trucks and plow trucks to be lifted, in addition to, mowers and other maintenance equipment. 90 Capital Plan 20092013 thru of Andover, MN City 11-48800-01 Project # Replacement - Hotsy Pressure Washer Project Name Priority TypeEquipment3 - Low Useful LifeContact 10 YearsDPW / City Engineer Category Facility ManagementDepartmentCentral Equipment Description New stationary pressure washer fueled by natural gas. Justification A new washer would operate more efficiently and save time and money by having fewer break downs. The new washer would run on natural gas rather than on kerosene. Expenditures20092010201120122013Total 7,0007,000 Equipment 7,0007,000 Total Funding Sources20092010201120122013Total 7,0007,000 Central Equipment Fund 7,0007,000 Total Operational Impact/Other Less break downs, saving time and money. Not having to send people out to buy fuel for it would also save money. Harder to get parts for. 91 Capital Plan 20092013 thru of Andover, MN City 13-48800-01 Project # Replacement - Service Truck Project Name Priority TypeEquipment2 - Medium Useful LifeContact 10 YearsDPW / City Engineer Category Streets/HighwaysDepartmentCentral Equipment Description Replace Unit #371, a 2001 S10 Ext Cab 4x4 truck with 52,000 miles. This truck averages about 7,000 miles a year and by 2013 it will have approximately 80,000 miles. The new truck would be a crew cab and also have a tailgate lift. Justification To assist mechanics with jobs outside the shop such as parts runs, schooling, vehicle repair and moving equipment around, a larger and roomier vehicle is needed. The current vehicle would make a good intern or spare vehicle or kept as a runner/drop truck. Expenditures20092010201120122013Total 30,00030,000 Vehicles 30,00030,000 Total Funding Sources20092010201120122013Total 30,00030,000 Central Equipment Fund 30,00030,000 Total Operational Impact/Other A bigger vehicle would increase operating costs - fuel and maintenance. 92 Capital Plan 20092013 thru of Andover, MN City 13-48800-02 Project # Replacement - Floor Sweeper Project Name Priority TypeEquipment3 - Low Useful LifeContact 15 YearsDPW / City Engineer Category Facility ManagementDepartmentCentral Equipment Description Replace Unit #324, a 1991 Floor Sweeper/Scrubber. With the addition of new buildings in the future, it will be more economical to purchase a new unit that is faster and more efficient. Justification The floors are not cleaned as often as they should be because the current sweeper's washing and vacuum systems are worn out and parts are getting harder to find. The sweeper works well outside because we only use the broom portion of the machine. The present machine works well for the area that we now have but if we expand the area, we will need to be able to clean the area faster and do it more efficiently. Expenditures20092010201120122013Total 35,00035,000 Equipment 35,00035,000 Total Funding Sources20092010201120122013Total 35,00035,000 Central Equipment Fund 35,00035,000 Total Operational Impact/Other A new machine would have less maintenance issues even with using it more often. 93 Capital Plan 20092013 thru of Andover, MN City 11-44000-01 Project # Battery Pack Replacement - Zamboni Project Name Priority TypeEquipment2 - Medium Useful LifeContact 7 YearsComm Ctr Manager Category Facility ManagementDepartmentCommunity Center Description Replacement Battery Pack for the Electric Zamboni. Justification The battery pack that drives the Zamboni should to be replaced every 5-7 years. Over time, the batteries will hold less and less of a charge and eventually have to be replaced. Expenditures20092010201120122013Total 7,0007,000 Vehicles 7,0007,000 Total Funding Sources20092010201120122013Total 7,0007,000 Community Center Operations 7,0007,000 Total Operational Impact/Other The Zamboni is a necessary part of the operations of the ice arena, and without it we would not be able to keep the facility open. The hope is that with the preventative maintenance program that is in place, we can achieve the maximum amount of time available on the battery pack before it has to be replaced. 94 Capital Plan 20092013 thru of Andover, MN City 10-41310-01 Project # Voting Equipment Project Name Priority TypeEquipment1 - High Useful LifeContact 15 YearsCity Clerk Category EquipmentDepartmentElections Description New electronic voting equipment for 10 precincts. Justification A Federal mandate to comply with HAVA - Help America Vote Act. The current equipment is non-compliant. Expenditures20092010201120122013Total 110,000110,000 Equipment 110,000110,000 Total Funding Sources20092010201120122013Total 110,000110,000 Capital Projects Levy 110,000110,000 Total Operational Impact/Other Continued storage and maintenance of all the equipment. 95 Capital Plan 20092013 thru of Andover, MN City 10-41600-01 Project # Replacement - Blazer #11 Project Name Priority TypeEquipment2 - Medium Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentEngineering Description Replace Unit #11, a 1995 S10 Blazer with 65,000 miles. The Engineering Department puts about 5,000 miles per year on this vehicle, and after 14 years, it will have approximately 75,000 miles on it. This unit could make a good intern vehicle or spare vehicle if needed. Justification This vehicle is an Engineering Tech inspection vehicle and needs to be available for inspections and surveying. Expenditures20092010201120122013Total 30,00030,000 Equipment 30,00030,000 Total Funding Sources20092010201120122013Total 30,00030,000 Equipment Bond 30,00030,000 Total Operational Impact/Other Lower maintenance costs and downtime. 96 Capital Plan 20092013 thru of Andover, MN City 09-42200-01 Project # Replacement - Fire Engine #11 Project Name Priority TypeEquipment1 - High Useful LifeContact 20 YearsFire Chief Category EquipmentDepartmentFire Description Replace Unit #4882, a 1991 Pierce Lance pumper truck with 25,900 miles. The expected life span of this vehicle is between 20 and 25 years. The truck is starting to have higher and higher maintenance costs and should be replaced within the next three to five years. This will make for an ideal back up pumper as is required by the I.S.O. if the city can afford to keep this vehicle. We would look to sell the existing back up pumper #12 currently located at station #1. Justification The current engine is working fine but is starting to have more day to day repairs. As with any vehicle that is 16 years old, some parts can be harder to find and take longer to receive for needed repairs. The fire department can not afford to have vehicles down for extended periods of time. IT would be appropriate to start the replacement of a number of vehicles that were originally purchased in 1990/91. The intent is to replace those vehicles purchased in 1990 over an appropriate period of time and in a priority order so that the vehicles do not get to be a maintenance Burdon and are still able to be used as first response emergency vehicles. Expenditures20092010201120122013Total 225,000225,000450,000 Vehicles 225,000225,000450,000 Total Funding Sources20092010201120122013Total 225,000225,000450,000 Equipment Bond 225,000225,000450,000 Total Operational Impact/Other The new technology will allow firefighters to respond and conduct fire suppression activities, rescue operations, and other required activities in a safer and more efficient manner. The maintenance costs can be lowered as well. Some of the new technology items include increasing the capability to transport more firefighters to the scene, internal plumbed foam suppressant system, climate controlled cab can be used for firefighter rehabilitation, much better visibility when driving to emergencies, better maneuverability, and new designs make it much easier to enter and exit the cab area. In addition the new emergency lighting standards will make it easier to see the truck while responding and also while parked at the scene. 97 Capital Plan 20092013 thru of Andover, MN City 10-42200-01 Project # Replacement - Fire Chief's Vehicle Project Name Priority TypeEquipment2 - Medium Useful LifeContact 10 YearsFire Chief Category EquipmentDepartmentFire Description Replace Unit #4806, a 2002 Chevrolet Tahoe with 58,100 miles and is used by the Fire Chief. Justification In order to keep the first line emergency responding vehicles in the proper operating conditions, it is important to replace equipment when needed. The current vehicle has worked very well and should be evaluated for repair history and maintenance costs as the replacement date gets closer. The annual mileage put on this vehicle is approximately 10,000. The vehicle is still in good shape and should be evaluated for replacement as scheduled. Expenditures20092010201120122013Total 45,00045,000 Equipment 45,00045,000 Total Funding Sources20092010201120122013Total 45,00045,000 Equipment Bond 45,00045,000 Total Operational Impact/Other The Chief's vehicle is used by the Chief to respond to emergency incidents. The vehicle has to be in good shape and able to provide safe and protective transportation when responding to all types of incidents. The vehicle also carries all of the Chief's protective gear and equipment needed to help conduct fire investigations. The Chief regularly uses the vehicle to conduct interviews while on the scene with property owners and also uses the truck to provide a place for fire victims to sit out of the elements while they are waiting for relatives or the Red Cross to respond to the scene. 98 Capital Plan 20092013 thru of Andover, MN City 10-42200-02 Project # Replacement - Rescue #11 Project Name Priority TypeEquipment2 - Medium Useful LifeContact 15 YearsFire Chief Category EquipmentDepartmentFire Description Replace Unit #4899, a 1997 GMC truck with 15,165 miles. This truck is used as the primary response vehicle to all medical incidents for station #1. This truck responds to about 300 calls per year and is the busiest vehicle in use by the fire department other than the Chief's and Fire Marshal's vehicles. Justification The current truck has very little maintenance issues as of 2008. Because this is the primary vehicle used to respond to medical calls for station #1 it is very important to keep this vehicle in top condition and always available to respond. The anticipated life span is 15 years and may be able to be extended if the maintenance costs stay in line. It would be a benefit to Station #1 if the new vehicle would be purchased with a four door cab rather than the current extended cab so that additional firefighters could respond to major medical incidents. Expenditures20092010201120122013Total 50,00050,000 Equipment 50,00050,000 Total Funding Sources20092010201120122013Total 50,00050,000 Equipment Bond 50,00050,000 Total Operational Impact/Other If the replacement vehicle is a four door cab, station #1 firefighters could respond with only one vehicle to major incidents such as a heart attack, and would not have to take two vehicles to the scene in order to get the appropriate staffing there. The replacement vehicle will also respond to vehicle crash scenes with additional equipment needed that could be stored on this truck. 99 Capital Plan 20092013 thru of Andover, MN City 10-42200-03 Project # Replacement - Fire Marshall Vehicle Project Name Priority TypeEquipment2 - Medium Useful LifeContact 10 YearsFire Chief Category EquipmentDepartmentFire Description Replace Unit #4801, a 1997 S10 Blazer with over 60,000 miles and used by the Fire Marshall. Justification The Fire Marshall's vehicle is anticipated to have approximately 70,000 miles on it by the year 2010, and the ability to respond to an emergency with a dependable vehicle needs to be considered. There have been more maintenance issues with this vehicle, and although most have been minor, the occurrences are increasing and the costs will also start to increase as the vehicle gets older. Expenditures20092010201120122013Total 40,00040,000 Vehicles 40,00040,000 Total Funding Sources20092010201120122013Total 40,00040,000 Equipment Bond 40,00040,000 Total Operational Impact/Other The new vehicle will be used for day to day inspections and also emergency responses when the Fire Marshall is available to assist at the incident including medical calls. It is crucial that the Fire Marshall's vehicle be in good operating order to perform all of the functions needed. This vehicle is also used to help conduct all of the fire investigations and the appropriate equipment needs to be stored in the vehicle. The fire department needs to have a very dependable vehicle to perform all of the functions listed. 100 Capital Plan 20092013 thru of Andover, MN City 11-42200-01 Project # Replacement - Ladder Truck #11 Project Name Priority TypeEquipment1 - High Useful LifeContact 20 YearsFire Chief Category EquipmentDepartmentFire Description Replace Unit #4885, a 1991 Pierce 75' ladder truck with 17,250 miles. The new ladder truck would be a 100 foot aerial platform, which includes a bucket at the end of the ladder for firefighter safety. The 100 foot reach will allow for the fire department to perform rescue and suppression activities in buildings that we can not currently reach. Justification The city is required by the I.S.O. to have this type of vehicle available for use because of the building heights allowed in Andover. The new platform style truck versus the current straight ladder will be much safer for firefighter activities and fire suppression activities. The new vehicles have safety sensors and weight distribution gauges that will keep the operators from making mistakes while operating the truck that could be very costly or dangerous. The newer buildings in Andover are getting taller with more green space between the building and a hard surface making it much more difficult to reach some of them because of the height restrictions of the current ladder truck. Expenditures20092010201120122013Total 500,000500,0001,000,000 Equipment 500,000500,0001,000,000 Total Funding Sources20092010201120122013Total 500,000500,0001,000,000 Equipment Bond 500,000500,0001,000,000 Total Operational Impact/Other The use of an aerial device can be very dangerous if not performed properly. A new platform truck will allow firefighters to perform the most dangerous of activities as required from time to time, and know that they have the right piece of equipment to do the job. The larger and taller buildings now being built in Andover will require this type of equipment. The current ladder truck has been fairly dependable with not many major repairs needed. The maintenance costs are going up for this vehicle and the trade in value may be going down as the truck gets older. The new bucket style of truck will also be much safer conditions for firefighters performing suppression activities. The new ladder truck can be equipped to have pre-plumbed breathing air in the bucket for extended use and also high intensity lighting mounted on the bucket will greatly increase site visibility. Firefighters will no longer have to carry heavy equipment up the ladder but rather can swing the bucket down to the ground to pick it up. The larger cab design will allow for transporting more firefighters and also can be used for rehabilitation of staff when needed. The bucket design will also allow for two master stream devices mounted near the top of the bucket to be used for extinguishment for very large types of fires. The over head visibility at the scene will also help the incident commander make vital decisions regarding the tactics and strategies to be used. 101 Capital Plan 20092013 thru of Andover, MN City 11-42200-02 Project # Replacement - Grass #31 Project Name Priority TypeEquipment2 - Medium Useful LifeContact 20 YearsFire Chief Category EquipmentDepartmentFire Description Replace Unit #4893, a 1991 Ford 4x4 grass vehicle with 21,670 miles. This also has been used as medical response truck for station #3. Now that the fire department has a separate vehicle that will be used to respond to medical calls, the new grass trucks will be designed to function for one primary purpose and will allow for new wildfire technologies to be put on the truck. Justification The fire department has now purchased new vehicles for rescue calls only and this will allow for the new grass trucks to have an extended life expectancy. The current grass vehicles have worked very hard responding to both wildfire and medical types of calls during most of the life of the trucks. The grass trucks also have many engine hours on them due to idling conditions while at grass fires and medical calls. By using separate vehicles for each function both the grass fire vehicle and assigned medical vehicle will last for at least 15 years or more. Expenditures20092010201120122013Total 45,00045,000 Equipment 45,00045,000 Total Funding Sources20092010201120122013Total 45,00045,000 Equipment Bond 45,00045,000 Total Operational Impact/Other The fire department will be looking to purchase a smaller and more maneuverable vehicle when it is time to replace the grass trucks. The current full size pick up trucks, while capable of handling larger tanks and more weight, can be difficult to use when the need to negotiate around obstacles during wildfires arises. The grass vehicles will be a four wheel drive type and should probably have winches mounted on the front of the vehicle. The smaller and more maneuverable vehicles should be less expensive but yet perform much better when using the off road functions and features. 102 Capital Plan 20092013 thru of Andover, MN City 11-42200-03 Project # Water/Ice rescue boat Project Name Priority TypeEquipment1 - High Useful LifeContact 15 YearsFire Chief Category EquipmentDepartmentFire Description A small boat designed and built to perform water and ice rescues. Justification Andover does not currently have a rescue boat. The boat would be used to perform ice and water rescues. The boat will make these specific types of rescues safer for all responders. The boat will allow firefighters to perform rescue work rather than waiting for a boat to arrive and perform recovery work. Expenditures20092010201120122013Total 20,00020,000 Equipment 20,00020,000 Total Funding Sources20092010201120122013Total 20,00020,000 Equipment Bond 20,00020,000 Total Operational Impact/Other Boat will make an easier and safer rescue for all responders and parties being rescued. The boat will save lives and make it safer for firefighters who have to enter the water or crawl on the ice. The current method of having firefighters wear wet suits and try to swim or crawl on the ice to the victim is not very safe or recommended if we can avoid it. The boat will help get the rescuer and victim out of the situation faster and safer. 103 Capital Plan 20092013 thru of Andover, MN City 12-42200-01 Project # Replacement - Utility #4 Project Name Priority TypeEquipment2 - Medium Useful LifeContact 15 YearsFire Chief Category EquipmentDepartmentFire Description Replace Unit #4804, a 2000 GMC Sonoma ext. cab 4x4 small utility pick up with 21,000 miles. This truck is used as a station response vehicle by the Officers assigned to each station. The fire department has three of these vehicles and each are fully equipped to be first responder vehicles to all types of incidents that the fire department will respond to. Justification The utility vehicles are used by Fire Department Officers to respond directly to the scene of the incident so that they can evaluate for additional equipment needed and also render immediate first aid and care to those who need it. The first responding vehicles are usually on the scene within five to six minutes of the original page as compared to seven or eight minutes for a vehicle responding from the fire station. The time span is critical for all types of major events. Knowing as quickly as possible what the conditions and situations at the scene will make for a much safer response by other vehicles and helps all others prepare for the incident as the first fire officer has already informed incoming trucks what is going on. Expenditures20092010201120122013Total 32,00032,000 Vehicles 32,00032,000 Total Funding Sources20092010201120122013Total Equipment Bond 32,00032,000 32,00032,000 Total Operational Impact/Other With their vehicle responding directly to the scene, the fire officer can cancel others if they are not needed and or slow them to routine so that the response is safer for responders and others who are on the highway. Having a fire officer at an incident early is very beneficial for size up and planning tactics prior to all of the other fire vehicles getting there. All fire conditions can be evaluated and thought out by the fire officer so that he or she can be better prepared to oversee fire suppression activities. 104 Capital Plan 20092013 thru of Andover, MN City 12-42200-02 Project # Replacement - Utility #5 Project Name Priority TypeEquipment2 - Medium Useful LifeContact 15 YearsFire Chief Category EquipmentDepartmentFire Description Replace Unit #4805, a 2000 GMC Sonoma ext. cab 4x4 small utility pick up with 22,600 miles. This truck is used as a station response vehicle by the Officers assigned to each station. The fire department has three of these vehicles and each are fully equipped to be first responder vehicles to all types of incidents that the fire department will respond to. Justification The utility vehicles are used by Fire Department Officers to respond directly to the scene of the incident so that they can evaluate for additional equipment needed and also render immediate first aid and care to those who need it. The first responding vehicles are usually on the scene within five to six minutes of the original page as compared to seven or eight minutes for a vehicle responding from the fire station. The time span is critical for all types of major events. Knowing as quickly as possible what the conditions and situations at the scene will make for a much safer response by other vehicles and helps all others prepare for the incident as the first fire officer has already informed incoming trucks what is going on. Expenditures20092010201120122013Total 32,00032,000 Vehicles 32,00032,000 Total Funding Sources20092010201120122013Total Equipment Bond 32,00032,000 32,00032,000 Total Operational Impact/Other With their vehicle responding directly to the scene, the fire officer can cancel others if they are not needed and or slow them to routine so that the response is safer for responders and others who are on the highway. Having a fire officer at an incident early is very beneficial for size up and planning tactics prior to all of the other fire vehicles getting there. All fire conditions can be evaluated and thought out by the fire officer so that he or she can be better prepared to oversee fire suppression activities. 105 Capital Plan 20092013 thru of Andover, MN City 12-42200-03 Project # Replacement - Grass #21 Project Name Priority TypeEquipment2 - Medium Useful LifeContact 20 YearsFire Chief Category EquipmentDepartmentFire Description Replace Unit #4892, a 1991 Ford 4x4 grass vehicle with 21,000 miles This has also been used as a medical response unit for Station #2. Now that the fire department has a separate vehicle that will be used to respond to medical calls, the new grass trucks will be designed to function for one primary purpose and will allow for new wildfire technologies to be put on the truck. Justification The fire department has now purchased new vehicles for rescue calls only and this will allow for the new grass trucks to have an extended life expectancy. The current grass vehicles have worked very hard responding to both wildfire and medical types of calls during most of the life of the trucks. The grass trucks also have many engine hours on them due to idling conditions while at grass fires and medical calls. By using separate vehicles for each function, both the grass fire vehicle and assigned medical vehicle will last for at least 15 years or more. Expenditures20092010201120122013Total 45,00045,000 Vehicles 45,00045,000 Total Funding Sources20092010201120122013Total 45,00045,000 Equipment Bond 45,00045,000 Total Operational Impact/Other The fire department will be looking to purchase a smaller and more maneuverable vehicle when it is time to replace the grass trucks. The current full size pick up trucks, while capable of handling larger tanks and more weight, can be difficult to use when the need to negotiate around obstacles during wildfires arises. The grass vehicles will be a four wheel drive type and should probably have winches mounted on the front of the vehicle. The smaller and more maneuverable vehicles should be less expensive but yet perform much better when using the off road functions and features. 106 Capital Plan 20092013 thru of Andover, MN City 13-42200-01 Project # Replacement - Tanker #11 Project Name Priority TypeEquipment2 - Medium Useful LifeContact 20 YearsFire Chief Category EquipmentDepartmentFire Description Replace Unit #4889, a 1991 International tanker with 8,300 miles and about 900 engine hours. Justification This vehicle will be 22 years old in 2013. The all wheel drive vehicle has worked extremely well as a tanker that can be used at all types of fires including wildfires, where the off road capabilities have proven to be very valuable. There have been no significant problems with this vehicle and the replacement need has to be re-evaluated in 2013 but it is very important that we keep this vehicle current and up to date with the latest firefighting technologies. The current vehicle has a rear mounted pumping system that requires constant maintenance and usually more than one person to operate the truck and pump at a fire scenario. The proposed new tanker will have remote operational capabilities that will make operating the truck with only one person a reality. The current manually-operated pump has many drawbacks and limitations due to the need for more than one person to operate efficiently and safely. Expenditures20092010201120122013Total Vehicles 340,000340,000 340,000340,000 Total Funding Sources20092010201120122013Total Equipment Bond 340,000340,000 340,000340,000 Total Operational Impact/Other The new vehicle will probably have a larger tank and also the capability for only one person to operate during a fire situation. The maintenance costs for a newer vehicle will also have a budget impact in that there should be much less maintenance costs for the first half of the lifespan of the vehicle. The newer vehicle will also be expected to last longer because of the updates in the manufacturing process. The newer styles and metal fabrication help to reduce rusting and deterioration of the vehicle. The new vehicle should be produced so that the driver can dump water from chutes installed on both sides and from the rear of the truck. Currently water can be discharged only from a large rear outlet or with the manual pump system installed at the back of the truck. 107 Capital Plan 20092013 thru of Andover, MN City 09-45000-02 Project # Trail Machine w/ Snow Removal Equipment Project Name Priority TypeEquipment1 - High Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentPark & Rec - Operations Description Trail machine is used in cleaning the trails system and the city sidewalks through out the city all year long. Justification The present machine is just too small for clearing the trails that are next to the roads in the winter time. The current machine is to light and doesn't have the traction or power to push through the snow and ice. Expenditures20092010201120122013Total 100,000100,000 Equipment 100,000100,000 Total Funding Sources20092010201120122013Total 100,000100,000 Equipment Bond 100,000100,000 Total Operational Impact/Other Get the job done faster, safer and more efficient. Additions to the fleet will increase maintenance and operating costs. 108 Capital Plan 20092013 thru of Andover, MN City 10-45000-01 Project # Replacement - Toro Groundsmaster, #559 Project Name Priority TypeEquipment1 - High Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentPark & Rec - Operations Description Replace Unit #559, a 1999 Toro Groundsmaster 328 with 1,839 hours. Justification This unit is run year round and averages about 300 hours a year. With additional parks being added each year, the average number of operational hours that each machine puts on will increase. Expenditures20092010201120122013Total 23,00023,000 Equipment 23,00023,000 Total Funding Sources20092010201120122013Total 23,00023,000 Equipment Bond 23,00023,000 Total Operational Impact/Other Higher maintenance cost, possibly more break downs and lower trade-in value. 109 Capital Plan 20092013 thru of Andover, MN City 10-45000-02 Project # Replacement - Large Capacity Lawnmower #580 Project Name Priority TypeEquipment1 - High Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentPark & Rec - Operations Description Replace Unit #580, a 1999 Toro 580 large capacity mower with 2,444 hours. This machine is averaging 200 - 300 hours per year and by 2010 it will have approximately 3,000 hours. Justification Maintenance costs are starting to accumulate and it should be traded in while it still has some value. Maintenance costs rose $3.58 per hour over the previous year. Expenditures20092010201120122013Total 112,000112,000 Equipment 112,000112,000 Total Funding Sources20092010201120122013Total 112,000112,000 Equipment Bond 112,000112,000 Total Operational Impact/Other Higher maintenance cost, possibly more break downs and lower trade-in value. 110 Capital Plan 20092013 thru of Andover, MN City 10-45000-03 Project # Zero turn mower Project Name Priority TypeEquipment1 - High Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentPark & Rec - Operations Description Purchase an additional zero turn mower. Justification A zero turn mower is more efficient when mowing around the buildings, trees and other obstacles that are found in the city parks and campus grounds. This would also extend the life of the current Toro mowers. Expenditures20092010201120122013Total 8,5008,500 Equipment 8,5008,500 Total Funding Sources20092010201120122013Total 8,5008,500 Equipment Bond 8,5008,500 Total Operational Impact/Other The zero turn mowers are faster to operate around buildings and trees thus saving time and money by being more productive. The zero turn mower is about 1/3 the cost of a Toro Groundsmaster. 111 Capital Plan 20092013 thru of Andover, MN City 11-45000-01 Project # Replacement - Trailer, T-554 Project Name Priority TypeEquipment2 - Medium Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentPark & Rec - Operations Description Replace Unit #T-554 , a tandem axle trailer with GVW rating of 10,000 - 12,000 lbs. It was recently sand blasted and repainted top to bottom extending its useful life a few more years. Justification This is the main trailer for the Parks Department. It was the first and only trailer that was designed for hauling mowers and it has worked out great. Expenditures20092010201120122013Total 9,0009,000 Equipment 9,0009,000 Total Funding Sources20092010201120122013Total 9,0009,000 Equipment Bond 9,0009,000 Total Operational Impact/Other More parks can only mean moving more equipment to them. 112 Capital Plan 20092013 thru of Andover, MN City 11-45000-02 Project # Replacement - One Ton Truck w/ Plow, #599 Project Name Priority TypeEquipment2 - Medium Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentPark & Rec - Operations Description Replace Unit # 599, a 2000 F450 1-ton with 43,750 miles. These trucks are on the move all year and average about 5,000 miles per year. Justification This truck is used everyday; hauling material, equipment, people and also plowing snow in the winter. The plowing of snow puts a lot of wear and tear on the engine, transmission and other drive line components. Expenditures20092010201120122013Total 65,00065,000 Vehicles 65,00065,000 Total Funding Sources20092010201120122013Total 65,00065,000 Equipment Bond 65,00065,000 Total Operational Impact/Other Being that this is a front line unit, we need to know that we can count on it everyday. Cost to operate it have only gone up $.04 per mile last year but those costs will continue to rise in the coming years. With preventative maintenance, we might be able to extend its useful life. 113 Capital Plan 20092013 thru of Andover, MN City 13-45000-01 Project # Replacement - One Ton Truck w/ Plow #503 Project Name Priority TypeEquipment2 - Medium Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentPark & Rec - Operations Description Replace Unit #503, a 2001 Ford F-450 dump truck with a 9' Fisher snow plow with 53,800 miles on it. Justification This unit will be 12 years old and should have approximately 70,000 miles on it. The maintenance cost will be monitored to determine when this vehicle should be replaced. Expenditures20092010201120122013Total 65,00065,000 Equipment 65,00065,000 Total Funding Sources20092010201120122013Total 65,00065,000 Equipment Bond 65,00065,000 Total Operational Impact/Other Less cost per mile to operate and less break downs. 114 Capital Plan 20092013 thru of Andover, MN City 13-45000-02 Project # Replacement - One Ton Crew Cab Pickup #502 Project Name Priority TypeEquipment1 - High Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentPark & Rec - Operations Description Replace Unit #502, a 2002 F350 crew cab pickup with 45,000 miles on it. Justification This truck is used for pulling a large trailer around the city with mowing equipment in the spring, summer and fall along with the summer part-time help. In the winter months, it is pulling equipment that is used to clear the ice skating rinks. A crew cab that can transport a mowing crew and all their equipment is an ideal situation. Expenditures20092010201120122013Total 45,00045,000 Equipment 45,00045,000 Total Funding Sources20092010201120122013Total 45,00045,000 Equipment Bond 45,00045,000 Total Operational Impact/Other Less cost per mile to operate and fewer break downs. Operating Budget Impact20092010201120122013Total 45,00045,000 Maintenance 45,00045,000 Total 115 Capital Plan 20092013 thru of Andover, MN City 10-41500-01 Project # Replacement - Ford Taurus #15 Project Name Priority TypeEquipment2 - Medium Useful LifeContact 10 YearsComm. Dev. Director Category EquipmentDepartmentPlanning & Zoning Description Replace Unit #15, a 1995 Taurus with 70,400 miles. This unit averages 3,000 to 5,000 miles a year. Justification By 2010, this vehicle will have 76,000 miles on it. This vehicle could be used as an intern vehicle or for city employees attending seminars/training. Expenditures20092010201120122013Total 25,00025,000 Equipment 25,00025,000 Total Funding Sources20092010201120122013Total 25,00025,000 Equipment Bond 25,00025,000 Total Operational Impact/Other A new vehicle will decrease maintenance costs and improve productivity. This car could be kept and used for interns and possibly replace one of the old blazers that has 168,000 miles on it. The Central Equipment Department would like to recommend looking at an alternative fuel vehicle/hybrid. 116 Capital Plan 20092013 thru of Andover, MN City 10-48200-01 Project # Replacement - One Ton Truck w/ Plow #90 Project Name Priority TypeEquipment1 - High Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentSanitary Sewer Description Replace Unit #90, a 1997 Dodge W250 with snow removal equipment and 60,000 miles. Justification This truck will be monitored over the next couple of years to determine the appropriate time for replacement. It will be replaced with a one ton truck and modern snow removal equipment to make snow removal faster and more efficient. Expenditures20092010201120122013Total 65,00065,000 Equipment 65,00065,000 Total Funding Sources20092010201120122013Total 65,00065,000 Sanitary Sewer Fund 65,00065,000 Total Operational Impact/Other The new truck will have decreased maintenance issues and the modern snow equipment will make snow removal faster and more efficient. 117 Capital Plan 20092013 thru of Andover, MN City 11-48200-03 Project # New Jet/Vac Truck Project Name Priority TypeEquipment1 - High Useful LifeContact 15-20 YearsDPW / City Engineer Category EquipmentDepartmentSanitary Sewer Description The new vehicle is a combination jet/vac unit, Model 2115 Positive Displacement Unit (PD Unit) used for cleaning sanitary and storm sewers. This unit will carry up to 2000 gallons of water and 600 feet of jetting hose. Justification Approximately 13 miles or 15% of the sanitary sewer system is trunk mains with diameters of 12" - 36". These trunk mains are flowing near capacity in some areas at the present time. By removing the sedimentation in these pipes the flow line will drop giving more room for additional flows. In turn this could put on hold the addition of the designated lift station to by pass certain areas for a year or more. This type of unit can also clean flared end sections in back yards and sedimentation ponds within a reasonable distance. This would allow some areas to be cleaned without having to enter properties. Also with two trucks in operation more of the storm and sanitary sewer systems could be maintained to meet goals as set up in the NPDES program. At the present time most of the departments efforts are geared towards the storm sewer system because of the many failures and neglect that has taken place in the past. There are thirty six square miles of storm sewer systems and ninety miles of sanitary systems. The storm sewers are maintained from the spring of the year and ending in the fall. The sanitary system is then maintained during the winter months when conditions are less than favorable. Expenditures20092010201120122013Total Equipment 357,000357,000 357,000357,000 Total Funding Sources20092010201120122013Total 160,000160,000 Sanitary Sewer Fund 160,000160,000 Sewer Trunk Fund Storm Sewer Fund 37,00037,000 357,000357,000 Total Operational Impact/Other This truck will help save time with cleaning of the system. It will also allow the system to be cleaned under heavy flows which cannot be done with the machine currently being used. This type of VAC truck will allow the operators to clean more of the system without having to stop because the truck cannot handle the flows. It would save time by not having to plug mains and risk backups into basements because of some unforeseen difficulty. By having two jet vac trucks in operation at the same time, more of the storm and sanitary sewer systems could be maintained on an annual basis to meet goals as set by the department and NPDES program. 118 Capital Plan 20092013 thru of Andover, MN City 09-48300-02 Project # Trailer Mounted Grout Plant Project Name Priority TypeEquipment1 - High Useful LifeContact 15-20 YearsDPW / City Engineer Category UtilitiesDepartmentStorm Sewer Description This trailer mounted grout plant is a concrete spray patcher that is capable of spraying concrete on the insides of manhole structures to seal holes or other types of openings with high pressure concrete to eliminate or slow the problems of infiltration. Justification Over the past few years, utility crews have been kept very busy with the repair of manholes where the problem of infiltration is occuring. Not only does the structure need to be repaired but the street as well. When infiltration occurs, the material under the road surface and curb is washed into the storm sewer leaving a void under the roadway. The road surface and curb needs to be removed and re-done to meet the road standards. This would also be used for the repair of sanitary sewer manholes where the adjustment rings are failing. Expenditures20092010201120122013Total 30,00030,000 Equipment 30,00030,000 Total Funding Sources20092010201120122013Total 9,0009,000 Sanitary Sewer Fund 21,00021,000 Storm Sewer Fund 30,00030,000 Total Operational Impact/Other With the addition of this equipment, the labor of doing repairs will be cut in half and it will be used as preventative maintenance. Structures throughout the city, both storm and sanitary sewers, will be spray-lined to help prevent the failure of the structures and road surfaces. 119 Capital Plan 20092013 thru of Andover, MN City 10-48300-01 Project # Replacement - Elgin Street Sweeper #169 Project Name Priority TypeEquipment1 - High Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentStorm Sewer Description Replace Unit #169, a 2000 Elgin sweeper with approximately 3,427 hours. Justification The maintenance cost of this machine has risen $0.77 per hour in the last year alone. Maintenance costs continue to rise and it will need to be monitored as to the timing of replacement. Expenditures20092010201120122013Total 150,000150,000 Vehicles 150,000150,000 Total Funding Sources20092010201120122013Total 90,00090,000 Equipment Bond 60,00060,000 Storm Sewer Fund 150,000150,000 Total Operational Impact/Other We will need to monitor the costs closely over the next few years and make a decision at that time. This machine only runs about a month and a half a year. 120 Capital Plan 20092013 thru of Andover, MN City 09-43300-01 Project # Retro-Reflectometer Project Name Priority TypeEquipment1 - High Useful LifeContact 15-20 YearsDPW / City Engineer Category Streets/HighwaysDepartmentStreet Signs Description Retro-Reflectometer is a hand held device that measures the retro-reflectivity of street signs. Justification In Decemebr of 2007, the FHWA set final regulations on maintaining retro-reflectivity standards for traffic signs. The City must put in place a program to ensure compliance by 2012. By 2017, all signs must meet the retro-reflectivity minimum standards. This will take several years to complete. This equipment is hand held and will be used in the field by the City's sign personnel. Expenditures20092010201120122013Total 15,00015,000 Equipment 15,00015,000 Total Funding Sources20092010201120122013Total 15,00015,000 Equipment Bond 15,00015,000 Total Operational Impact/Other 121 Capital Plan 20092013 thru of Andover, MN City 10-43100-01 Project # Replacement - Water Tanker #163 Project Name Priority TypeEquipment2 - Medium Useful LifeContact 15 YearsDPW / City Engineer Category EquipmentDepartmentStreets / Highways Description Replace Unit #163, a 1986 water tanker with 65,200 miles. Justification The old tanker was partially refurbished a few years ago because the floor and tank had rusted out. A new water truck would handle the job tasks better and more efficiently. A recently purchased water tanker with its cab over design and short turning radius has been a great asset to the public works staff. Expenditures20092010201120122013Total 100,000100,000 Vehicles 100,000100,000 Total Funding Sources20092010201120122013Total 100,000100,000 Equipment Bond 100,000100,000 Total Operational Impact/Other The design of the new water tanker make it very efficient to operate and pleasure to use. The front adjustable nozzle is particularly liked by the public works staff. 122 Capital Plan 20092013 thru of Andover, MN City 10-43100-02 Project # Asphalt Paving Machine Project Name Priority TypeEquipment1 - High Useful LifeContact 20 YearsDPW / City Engineer Category EquipmentDepartmentStreets / Highways Description Asphalt paving machine used for overlay and trails. The City currently does not own a paver which we have an increasing need for due to the deterioration of city streets. Justification Due to increasing repairs to city streets, the city has a need to own a paver. It could also be used for trails. Expenditures20092010201120122013Total 90,00090,000 Equipment 90,00090,000 Total Funding Sources20092010201120122013Total 90,00090,000 Equipment Bond 90,00090,000 Total Operational Impact/Other Not having to rent one, being able to use it when it fits in to our time schedule rather than having to see when one is available to rent. Share cost with another city is an option. 123 Capital Plan 20092013 thru of Andover, MN City 10-43100-03 Project # Replacement - Dump Truck w/ Snow Removal #197 Project Name Priority TypeEquipment1 - High Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentStreets / Highways Description Replace unit #197, a 1996 LT9000 tandem axle dump truck and snow removal equipment with 60,400 miles on it. Justification This is one of the remaining few units with a manual transmission in it. It's difficult and tiring to operate the snow removal equipment and change gears at the same time. Less operations in the cab will keep the driver alert for longer periods of time during those long snow removal days and nights. Expenditures20092010201120122013Total 200,000200,000 Equipment 200,000200,000 Total Funding Sources20092010201120122013Total 200,000200,000 Equipment Bond 200,000200,000 Total Operational Impact/Other Changing to an automatic transmission and newer snowplow controls will give us more attentive and less fatigued drivers after many hours of service. 124 Capital Plan 20092013 thru of Andover, MN City 12-43100-01 Project # Replacement - Dump Truck w/ Snow Removal #198 Project Name Priority TypeEquipment1 - High Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentStreets / Highways Description Replace unit #198, a 2000 dump truck with front mounted snow removal equipment with almost 26,500 miles on it. We estimate that by 2012 this truck will have around 50,000 miles on it. Justification This truck will be 12 years old and will be getting close to the end of its life cycle. It will be re-evaluated each year to determine when to replace it. Expenditures20092010201120122013Total 150,000150,000 Equipment 150,000150,000 Total Funding Sources20092010201120122013Total 150,000150,000 Equipment Bond 150,000150,000 Total Operational Impact/Other Less cost per mile to operate and better use of snow plow equipment. 125 Capital Plan 20092013 thru of Andover, MN City 12-43100-02 Project # Replacement - One Ton Truck w/ Plow #132 Project Name Priority TypeEquipment1 - High Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentStreets / Highways Description Replace unit #132, a 2001 Ford F-450 dump truck with a 9 foot Fisher snow plow with 69,000 miles on it.. This unit plows cul-de-sacs and hauls equipment and materials through out the year. Justification This truck will be 11 years old by then and will have 100,000 miles on it. Currently it has 69,000 miles on it and cost per mile to operate will most likely be on the rise. It will be re-evaluated each year to determine when to replace it. Expenditures20092010201120122013Total 65,00065,000 Equipment 65,00065,000 Total Funding Sources20092010201120122013Total 65,00065,000 Equipment Bond 65,00065,000 Total Operational Impact/Other Less cost per mile to operate but it might work out as a good summer time vehicle. Operating Budget Impact20092010201120122013Total 58,00058,000 Maintenance 58,00058,000 Total 126 Capital Plan 20092013 thru of Andover, MN City 11-48100-02 Project # Replacement - One Ton Truck w/ Plow #105 Project Name Priority TypeEquipment1 - High Useful LifeContact 10 YearsDPW / City Engineer Category EquipmentDepartmentWater Description Replace unit #105, a 1994 Ford F-250 pick up truck with snow removal equipment and 104,780 miles. Justification By 2011, this truck will be 17 years old with over 115,000 miles on it. This truck will be replaced with a 1-ton truck with modern snow removal equipment. Expenditures20092010201120122013Total 65,00065,000 Equipment 65,00065,000 Total Funding Sources20092010201120122013Total 65,00065,000 Water Fund 65,00065,000 Total Operational Impact/Other A new truck wil have lower maintenance cost and better snow removal equipment. Both items will save time and money. 127 This page left blank intentionally. 128 CITY OF ANDOVER Road & Bridge Funds - Rollup Projected Fund Balance 200820092010201120122013TOTALS Projected Sources of Revenue Est. Annual MSA Construction Allocation$ 155,000$ 766,802$ 766,802$ 766,802$ 766,802$ 766,802$ 3,989,010 2001 State Aid Road Bond Pymt - Principal (155,000) (160,000) (170,000) (175,000) (185,000) (195,000) (1,040,000) Available MSA Construction for Other Commitments 606,802 596,802 591,802 581,802 571,802 2,949,010 - Est. Annual Maintenance Allocation 328,630 328,630 328,630 328,630 328,630 328,630 1,971,780 2001 State Aid Road Bond Pymt - Interest (85,120) (78,583) (71,568) (64,063) (56,050) (47,354) (402,738) General Fund Commitment (179,618) (185,007) (190,557) (196,273) (196,273) (202,162) (1,149,890) Available MSA Maintenance for Other Commitments 63,892 65,040 66,505 68,294 76,307 79,114 419,152 Total MSA Available for other Commitments 63,892 671,842 663,307 660,096 658,109 650,916 63,892 Federal Funds - - - - - - - Assessments* 242,889 345,000 260,000 297,000 505,000 380,000 2,029,889 Tax Levy 1,157,606 1,202,909 1,247,330 1,292,131 1,338,953 1,387,885 7,626,814 Total Revenues Available 1,464,387 2,219,751 2,170,637 2,249,227 2,502,062 2,418,801 9,720,595 Projected Commitments MSA - New & Reconstruct Routes - 500,000 380,000 930,000 815,000 2,625,000 - MSA - Intersection Upgrades 200,000 275,000 475,000 - - - - MSA - Rail Road Quiet Zones 160,000 160,000 - - - - - R & B - Pavement Markings 20,000 21,000 22,000 23,000 24,000 25,000 135,000 R & B - Curb Replacement 41,000 42,000 43,000 44,000 45,000 46,000 261,000 R & B - Rail Road Quiet Zones 170,000 170,000 - - - - - R & B - New & Reconstruct Routes - - - - - - - R & B - Intersection Upgrades 25,000 25,000 - - - - - R & B - Seal Coating 286,865 220,000 225,000 230,000 235,000 240,000 1,436,865 R & B - Crack Sealing 148,924 80,000 80,000 80,000 80,000 80,000 548,924 R & B - Overlays 971,557 1,078,000 1,039,000 1,189,000 1,462,000 1,358,000 7,097,557 Pedestrian Trail Maintenance 52,000 53,000 54,000 55,000 56,000 57,000 327,000 Total Commitments 2,075,346 1,994,000 1,843,000 1,896,0002,832,0002,621,000 13,261,346 Revenues Over (Under) Expenditures (610,959) 225,751 327,637 353,227 (329,938) (202,199)$(3,540,751) Fund Balance as of December 31, 2007 3,182,170 Fund Balance Brought Forward 2,571,211 2,796,962 3,124,600 3,477,826 3,147,888 Ending Fund Balance$2,571,211$ 2,796,962$ 3,124,600$ 3,477,826$ 3,147,888$ 2,945,689 * Assuming collected in same year 129 CITY OF ANDOVER Park Improvement Fund Projected Fund Balance 200820092010201120122013TOTALS Projected Sources of Revenue Park Dedication Fee $2,794 per unit platted units 50 50 50 50 50 - Anticipated Park Dedication Fee$ 139,700$ 139,700$ 139,700$ 139,700$ 139,700$ 698,500 $ - Commercial / Residential - Andover Station NEst.78,733 78,733 100,000 47,461 - - 304,927 DNR Grant - - - - - - - Capital Projects Levy - Park Improvements 57,680 57,680 57,680 57,680 57,680 57,680 346,080 Total Revenues Available 136,413 276,113 297,380 244,841 197,380 197,380 1,349,507 Projected Commitments Annual Miscellaneous Projects 25,000 25,000 25,000 25,000 25,000 25,000 150,000 Debt Service Payments DS - Ballfields (Final 2015) 147,727 129,659 129,659 129,659 129,659 129,659 796,022 Andover Station North - Bldg - City 38,491 38,491 Andover Station North - Playground 35,000 35,000 Andover Station North - Playground - LY 25,064 25,064 Strootman Park - LY 6,817 6,817 Crooked Lake Boat Landing - LY 20,952 20,952 Woodland Crossing Park 45,000 45,000 Skate Board Park 200,000 200,000 Sophies South Park 75,000 75,000 Andover Lions Park85,00085,000 Total Commitments 344,051 154,659 354,659 229,659 154,659 239,659 1,477,346 Revenues Over (Under) Expenditures (207,638) 121,454 (57,279) 15,182 42,721 (42,279) Fund Balance as of December 31, 2007 161,510 Fund Balance Brought Forward (46,128) 75,326 18,047 33,229 75,950 Ending Fund Balance *$ (46,128)$75,326$18,047$33,229$ 75,950$ 33,671 *Target - $50,000 to create a contingency for any project overages. Note: Debt Service has priority, platted units will have to be determined prior to any projects moving forward. Debt service payments are assessments for the construction of ballfields at Andover Station North. Payments are based on 5.5% interest for 8 years. 130 CITY OF ANDOVER Trail Fund Projected Fund Balance 200820092010201120122013TOTALS Projected Sources of Revenue Trail Fee $626 per unit platted units 50 50 50 - 50 50 Trail Fee$ 31,300$ 31,300$ 31,300$ 156,500 $ -$ 3 1,300$ 3 1,300 - - - - - - - Total Revenues Available 31,300 31,300 31,300 156,500 - 3 1,300 3 1,300 Projected Commitments - - - - - Total Commitments - - - - - -$ - Revenues Over (Under) Expenditures 31,300 31,300 31,300 - 3 1,300 3 1,300 Fund Balance as of December 31, 2007 3 2,541 Fund Balance Brought Forward 63,841 95,141 126,441 3 2,541 3 2,541 Ending Fund Balance *$ 95,141$ 126,441$ 157,741 $ 3 2,541$ 6 3,841$ 6 3,841 *Target - 10% of current years commitments to create a contingency for any project overages. ** It is anticipated that all projects will not be fully expended by the end of the year, and future projects will be contingent on additional revenues. 131 CITY OF ANDOVER Water System Financial Projections ActualEstimateForcast Year 200520062007200820092010201120122013 Inflation Factor3.0%3.0%3.0%3.0%3.0%3.0%3.0%3.0%3.0% Ave. Use (gal per user per qtr) 37,859 38,935 40,90040,900 40,900 40,900 40,900 40,900 40,900 Acres Added 50 50 35 35 35 35 35 35 35 New Connections 50 50 50 50 50 50 New Customers 100 100 50 50 50 50 Residential Accounts 5,541 5,723 5,857 Commercial/Institutional Accts 116 131 131 Total Accounts 5,657 5,854 5,988 6,088 6,188 6,238 6,288 6,338 6,388 Rates Base Rate$8.87$9.14$9.78$10.27$10.78$11.32$11.89$12.48$13.11 Use Rate$1.31$1.35$1.44$1.54$1.65$1.76$1.89$2.02$2.16 Connection Charge$2,503$2,704$2,920$3,154$3,406$3,679$3,973$4,291$4,634 Area Charge$2,294$2,477$2,675$2,889$3,120$3,370$3,639$3,930$4,245 Connection/Area8.0%8.0%8.0%8.0%8.0%8.0%8.0%8.0%8.0% Base Rate5.0%3.0%5.0%5.0%5.0%5.0%5.0%5.0%5.0% Use Rate7.0%7.0%7.0%7.0%7.0%7.0%7.0% Operations Revenues Use+Base 1,581,838 1,719,086 1,907,861 1,783,247 1,935,075 2,081,879 2,239,770 2,409,582 2,592,213 Meters 46,316 22,563 17,503 25,000 25,000 25,000 25,000 25,000 25,000 Permit Fees 11,350 3,100 4,500 5,000 5,000 5,000 5,000 5,000 5,000 Penalties 21,638 30,129 9,849 20,000 20,000 20,000 20,000 20,00020,000 Interest 14,174 25,152 138,461 280,000 281,146 281,146 281,146 286,146 20,000 Xfer In 57,671 163,469 165,643 48,916 52,829 57,056 61,620 -167,424 Other 5,692 4,258 11,746 17,200 4,000 4,000 4,000 4,000 4,000 Bond Proceeds - -6,570,000 - - - - - Total 1,681,008 1,971,712 8,717,591 2,293,916 2,435,864 2,465,941 2,627,745 2,806,784 2,727,833 Expenses Operations 1,035,752 1,162,950 1,115,163 1,048,967 1,156,394 1,191,086 1,226,818 1,263,623 1,301,532 Debt Service 754,392 746,721 847,685 1,014,228 1,015,585 1,113,019 1,116,305 7,873,830 1,099,690 Capital Outlay 66,196 33,487 6,500 35,000 50,000 50,000 120,000 80,500 65,000 Replac Res / Transfer Out 145,874 150,250 - -141,625 - - - - Total 1,856,340 1,943,158 2,110,973 2,244,069 2,372,229 2,354,105 2,463,123 9,217,953 2,466,221 Cash Balance Balance Brought Forward1,222,232 1,046,900 1,075,454 7,682,072 7,731,919 7,795,554 7,907,390 8,072,011 1,660,843 Net Increase (Decrease) (175,332) 28,554 6,606,618 49,847 63,635 111,836 164,621 (6,411,169) 261,612 Balance 1,046,900 1,075,454 7,682,072 7,731,919 7,795,554 7,907,390 8,072,011 1,660,843 1,922,454 Cash in Escrow 6,493,774 6,493,774 6,493,774 6,493,774 6,493,774 - - Unreserved Cash Balance 1,188,298 1,238,145 1,301,780 1,413,616 1,578,237 1,660,843 1,922,454 132 CITY OF ANDOVER Water System Financial Projections ActualEstimateForcast Year 200520062007200820092010201120122013 Infrastructure / Trunk Revenues Connection Charges961,261 302,053 624,068 157,700 170,316 183,941 198,657 231,713214,549 Area Charges 109,204 117,941 127,376 137,566 148,571 - - -101,115 Interest 79,891 109,258 177,021 50,000 25,000 25,000 25,000 25,000 25,000 Special Assessment 130,910 44,596 58,079 50,000 50,000 - - - - Replacement Reserve - - - - - - - - - Other 2,210 -23,745 - - - - - - Total 1,174,272 455,907 882,913 358,815 354,520 326,882 351,032 377,115 405,284 Expenses Debt Service - - - - - - - - - Capital Outlay 976,847 49,137 168,560 616,500 124,000 150,000 150,000 1,021,000 150,000 Xfer Out 57,671 163,469 165,643 48,916 52,829 57,05661,620 -167,424 Total 216,561976,847 226,231 779,969 289,643 198,916 202,829 1,078,056 211,620 Fund Balance Balance Brought Forward 2,093,346 2,290,771 2,530,117 3,186,799 2,765,645 2,830,522 2,958,488 3,106,691 2,405,750 Annual Surplus/Deficit 197,425 239,346 656,682 (421,154) 64,877 127,966 148,203 (700,941) 193,664 Balance 2,290,771 2,530,117 3,186,799 2,765,645 2,830,522 2,958,488 3,106,691 2,405,750 2,599,414 FB Designations Replacement Reserve1,147,000 1,147,000 1,147,000 1,147,000 1,147,000 1,147,000 1,147,000 1,147,000 1,147,000 Working Cash Flow 1,143,771 1,383,117 2,039,799 1,618,645 1,683,522 1,811,488 1,959,691 1,258,750 1,452,414 2,290,771 2,530,117 3,186,799 2,765,645 2,830,522 2,958,488 3,106,691 2,405,750 2,599,414 Capital Projects Wells Rehab Wells 45,000 50,000 50,000 55,000 60,000 65,000 Construct Test Wells #10 & 11 88,000 Cunstruct Well # 10 181,000 Trunk New Development Projects 120,500 124,000 150,000 150,000 150,000 150,000 Water Main along South Coon Creek 500,000 Plant Land Purchase50,000 Paint water tower358,000 Construct Clear Well @ WTP 2,665,900 Surface Seal Brick Structures 18,000 20,500 Demo tower 190,000 WTP reclaim tank addition 930,000 Construct WTP #2 8,000,000 Equipment 30,000 65,000 Total 1,104,000 200,000 2,935,900 1,101,500 8,215,000 - - -709,500 Funded by Operations 60,000 93,000 50,000 50,000 120,000 80,500 65,000 -105,000 Funded by Infrastructure/Trunk 299,100 616,500 124,000 150,000 150,000 1,021,000 150,000 -170,250 Funded by debt - - - -930,000 -2,665,900 -8,000,000 Total 359,100 709,500 1,104,000 200,000 2,935,900 1,101,500 8,215,000 -275,250 Debt Rate5.00%5.00%5.00%5.50%5.50%5.50%5.50%5.50%5.50% Term 10 10 10 10 15 15 15 15 15 AADS - - - -92,652 -265,592 -797,005 Cumulative DS 92,652358,244358,244 - - - - -92,652 Current DS WTP 741,393 746,720 745,663 1,014,374 1,015,585 1,020,367 1,023,653 7,515,586 741,446 17.5% of Connection / Area Charges is used to support the WTP 133 CITY OF ANDOVER Sewer System Financial Projections Estimate ActualForcast 200520062007200820092010201120122013 Year Inflation Factor - expenses3.0%3.0%3.0%3.0%3.0%3.0%3.0%3.0%3.0% Acres Added 50 50 35 35 35 35 35 35 35 New Connections 50 50 50 50 50 50 New Customers 100 100 50 50 50 50 Residential Accounts 6,435 6,559 6,773 Commercial SACs 1,215 1,246 1,270 Total Services 7,650 7,805 8,043 8,143 8,243 8,293 8,343 8,393 8,443 Rates Base Rate$49.75$51.74$53.81$55.96$57.64$59.37$61.15$62.98$64.87 Connection Charge$361$372$387$402$418$435$452$470$489 Area Charge$1,340$1,379$1,434$1,491$1,551$1,613$1,678$1,745$1,815 Connection/Area2.8%3.0%4.0%4.0%4.0%4.0%4.0%4.0%4.0% Base Rate4.0%4.0%4.0%4.0%3.0%3.0%3.0%3.0%3.0% Operations Revenues Base Use 1,469,656 1,607,561 1,759,045 1,805,270 1,900,506 1,969,422 2,040,698 2,114,365 2,190,790 Penalties 19,646 27,362 12,418 15,000 15,000 15,000 15,000 15,000 15,000 Interest 33,192 51,555 80,096 50,000 55,000 55,000 55,000 55,000 55,000 Other 7,624 2,950 207 15,400 10,000 10,000 10,000 10,000 10,000 Total 1,530,118 1,689,428 1,851,766 1,885,670 1,980,506 2,049,4222,120,6982,194,365 2,270,790 Expenses Operations 1,143,982 1,152,359 1,174,041 1,332,223 1,449,353 1,492,834 1,537,619 1,583,747 1,631,260 Debt Service 7,000 - - - - - - - - Capital Outlay 61,173 - 6,500 55,000 9,000 65,000 160,000 - - Replacement Reserve - 300,000 394,000 350,000 350,000 400,000 400,000 400,000 400,000 Total 1,212,155 1,452,359 1,574,541 1,737,223 1,808,353 1,957,834 2,097,619 1,983,747 2,031,260 Cash Balance Balance Brought Forward 871,661 1,189,624 1,426,693 1,703,918 1,852,365 2,024,518 2,116,106 2,139,186 2,349,804 Annual Surplus/Deficit 317,963 237,069 277,225 148,447 172,153 91,588 23,079 210,618 239,530 Balance 1,189,624 1,426,693 1,703,918 1,852,365 2,024,518 2,116,106 2,139,186 2,349,804 2,589,334 Infrastructure/Trunk Revenues Connection Charges 350,165 70,080 205,556 20,100 20,900 21,750 22,600 23,500 24,450 Area Charges - - -52,18554,285 56,455 58,730 61,075 63,525 Interest 37,532 72,424 126,348 60,000 60,000 60,000 60,000 60,000 60,000 Replacement Reserve - 300,000 350,000 350,000 350,000 400,000 400,000 400,000 400,000 Special Assessments 94,484 42,687 28,493 30,000 30,000 30,000 30,000 30,000 30,000 Other 48,122 - 428 - - - - - - Total 530,303 485,191 710,825 512,285 515,185 568,205 571,330 574,575 577,975 Expenses Debt Service - 14,626 - - - - 265,336 298,503 298,503 Capital Outlay 455,017 - 86,672 170,500 124,000 150,000 710,000 800,000 150,000 Total 455,017 14,626 86,672 170,500 124,000 150,000 975,336 1,098,503 448,503 Fund Balance Balance Brought Forward 984,126 1,059,412 1,529,977 2,154,130 2,495,915 2,887,100 3,305,305 2,901,299 2,377,371 Annual Surplus (Deficit) 75,286 470,565 624,153341,785 391,185 418,205 (404,006) (523,928) 129,472 Balance 1,059,412 1,529,977 2,154,130 2,495,915 2,887,100 3,305,305 2,901,299 2,377,371 2,506,843 FB Designations Replacement Reserve - - 350,000 700,000 1,000,000 1,300,000 1,600,000 1,900,000 2,200,000 Working Cash Flow 1,059,412 1,529,977 1,804,130 1,795,915 1,887,100 2,005,305 1,301,299 477,371 306,843 1,059,412 1,529,977 2,154,130 2,495,915 2,887,100 3,305,305 2,901,299 2,377,371 2,506,843 Capital Projects Infrastructure New Development Projects 120,500 124,000 150,000 150,000 150,000 150,000 Land Purchase 50,000 Crosstown Blvd Trunk 400,000 Yellow Pine Lift Station 650,000 Rural Reserve Sanitary Trunk 2,000,000 250,000 Equipment 30,000 9,000 65,000 320,000 Total - - - 200,500 133,000 215,000 2,870,000 1,050,000 150,000 Funded by Operations - - - 30,000 9,000 65,000 160,000 - 150,000 710,000 800,000 150,000 Funded by Infrastructure/Trunk - - - 170,500124,000 Funded by debt - - - - - 2,000,000 250,000 - - - - 200,500 133,000 215,000 2,870,000 1,050,000 150,000 Debt Interest Rate5.00%5.00%5.00%5.50%5.50%5.50%5.50%5.50%5.50% Term101010101010101010 DS Annualized - - - - - - 265,336 33,167 - Total Annual Debt Service - - - - - - 265,336 298,503 298,503 Total Annual Debt Service - - - - - - 265,336 265,336 265,336 - - - - - 33,167 33,167 134