HomeMy WebLinkAbout2007 CIP2.007 — 201 i Capi tal Improvement Phan 1 685 Cro,5,5townblvd NW, AndoverMN5550+ 'hone: 765.755.5 , o0 rax. 765. 755.8923 www.ci.anJover.mn.us CITY OF ANDOVER 2007 — 2011 Capital Improvements Plan Table of Contents Introduction 2007 — 2011 Capital Improvement Plan Message ........................................................ ............................... 1 CIP Project Development & Process Authorization Schedule ..................................... ............................... 4 Graph — 2007 Expenditures By Department ................................................................. ............................... 6 Graph— CIP Expenditures By Year .............................................................................. ............................... 6 Five Year Summary of Expenditures By Department .................................................. ............................... 7 Five Year Summary of Revenue By Source ................................................................. ............................... 8 Five Year Summary of Projects By Department & Revenue Source ........................... ............................... 9 Improvements Five Year Summary of Expenditures By Department — Improvements ....................... ............................... 15 Five Year Summary of Revenue By Source — Improvements ...................................... ............................... 16 Five Year Summary of Projects By Department & Revenue Source — Improvements ............................... 17 Improvement Projects By Department CentralEquipment ................................................................................................. ............................... 21 CommunityCenter ................................................................................................. ............................... 22 Engineering............................................................................................................ ............................... 24 FacilityManagement .............................................................................................. ............................... 26 Parks& Recreation — Operations ........................................................................... ............................... 38 Parks& Recreation — Projects ................................................................................ ............................... 39 SanitarySewer ....................................................................................................... ............................... 60 StormSewer ........................................................................................................... ............................... 68 Streets/ Highways ................................................................................................. ............................... 70 Water...................................................................................................................... ............................... 107 Equipment Year Summary of Expenditures By Department — Equipment ..................................... ............................... 117 Five Year Summary of Revenue By Source — Equipment ........................................... ............................... 118 Five Year Summary of Projects By Department & Revenue Source — Equipment ...... ............................... 119 Equipment By Department CentralEquipment ................................................................................................. ............................... 122 CommunityCenter ................................................................................................. ............................... 125 Elections................................................................................................................. ............................... 128 Engineering............................................................................................................ ............................... 129 FacilityManagement .............................................................................................. ............................... 131 FireDepartment ..................................................................................................... ............................... 132 Parks& Recreation — Operations ........................................................................... ............................... 143 Planning& Zoning ................................................................................................. ............................... 153 SanitarySewer ....................................................................................................... ............................... 154 StormSewer ........................................................................................................... ............................... 155 StreetSigns ............................................................................................................ ............................... 157 Streets/ Highways ................................................................................................. ............................... 159 Appendix Road & Bridge Fund Projected Fund Balance ............................................................. ............................... 167 Park Improvement Fund Projected Fund Balance ........................................................ ............................... 168 TrailFund Projected Fund Balance .............................................................................. ............................... 169 Water System Financial Projections ............................................................................. ............................... 170 Sewer System Financial Projections ............................................................................. ............................... 171 1685 CROSSTOWN BOULEVARD N.W. • ANDOVER, MINNESOTA 55304 • (763) 755 -5100 FAX (763) 755 -8923 • WWW.CI.ANDOVER.MN.US TO: Mayor and Council Members FROM: Jim Dickinson, City Administrator / Finance Director SUBJECT: 2007 - 2011 Capital Improvement Plan DATE: December 5, 2006 INTRODUCTION On behalf of the City's Management Team, I am pleased to present the City of Andover's Capital Improvement Plan for years 2007 through 2011. The City's management team and their respective staff worked diligently to produce a document that was both practical, substantive in addressing needed capital improvements and insightful regarding the underlying factors associated with the City's rapidly changing suburban landscape. CAPITAL IMPROVEMENT PLAN GOALS ACKNOWLEDGE AND COMMUNICATE PUBLIC INFRASTRUCTURE PRIORITIES AND DYNAMICS ENSURE APPROPRIATE RESPONSES TO CHANGING INFRASTRUCTURE NEEDS AND DEMANDS DEVELOP A FINANCIAL ASSESSMENT OF CAPITAL RESOURCES AVAILABLE TO MEET FUTURE CAPITAL PROJECT PLANNING NEEDS INSTITUTE A STRATEGIC VISION PREDICATED ON MAINTAINING A HIGH QUALITY SERVICE INFRASTRUCTURE CAPABLE OF MEETING THE NEEDS OF OUR CITIZENS FOR TODAY AND TOMORROW The purpose of the City's Capital Improvement Plan (CIP) is to identify, prioritize and address community needs through careful long -term capital planning and balanced public investment in supporting physical infrastructure. To ensure that this commitment is both meaningful and achievable, appropriate capital improvement factors were given significant consideration in developing a CIP that addresses community priorities over the next five (5) years. The CIP will also provide a planning foundation for future needs assessments to ensure the City is appropriately responding to the critical infrastructure needs necessary for sustainable future growth. The CIP represents a beginning in terms of producing a comprehensive planning response to address changing capital needs by developing a project schedule that will lead to timely and cost - effective project completions. nTQCT NIU(IN The 2007 - 2011 CIP has been prepared as a strategic planning tool to assist the City Council in identifying proposed capital improvement projects over the next five years. With the inclusion of preliminary financing sources, appropriate background information citing needs and projected cost estimates, this document will provide Council with the needed information to begin the process for planning improvements that meet the City's physical infrastructure needs. Consequently, the CIP serves as a flexible guide plan to properly identify the critical components of the City's infrastructure, yet maintain flexibility in determining project timeframes, project scope and possible funding sources. The 2007 - 2011 CIP continues the emphasis of judiciously managing the City's limited resources by prudently planning for known and /or anticipated future capital expenditures. A critical step in the plan adoption process is the collaborative nature of plan review that involves the leadership of the City Council, the input of appointed Commissions and staff, and most importantly, affected residents of the community. Consequently, the strategic value of this plan lies in the acknowledgement of future needs by the governing body and the effective communication of those needs to the general public during project development stages. Likewise, the availability and preliminary designation of fiscal resources to serve both current and future needs is critical to the achievement of plan outcomes that meet with Council approval. Following the approval of the plan, feasibility studies are performed, affected constituencies are notified to formally disseminate and receive public feedback on proposed project plans. This process culminates with the City Council considering all relevant information and making a final decision on whether to proceed with the proposed capital improvement. The public process that supports the advancement of these projects from inception to completion is engendered in the CIP project development and authorization schedule. Formalizing the steps in the CIP project advancement process serves a number of purposes and ensures that the Council and public are kept well informed regarding project purposes and desired outcomes, estimated project costs, funding sources, progress and final status. It should be emphasized that projects will require approval in various stages of project development by the City Council in accordance with approved policies. The objectives of the 2007 - 2011 Capital Improvement Plan are to present a comprehensive capital improvement program that communicates efforts: ➢ to ensure that community priorities are reflected in the capital investment plans of each City department; ➢ to provide a consolidated financial picture of anticipated expenditures and outline recommended funding strategies to underwrite anticipated capital improvements; ➢ to document and communicate capital improvement processes for City projects that will ensure consistency, a full appreciation of both the costs and benefits of proposed capital investments, and raises the level of public understanding regarding the City's public improvement processes; ➢ to provide information on the fiscal impacts of capital investment plans on total City finances; and ➢ to effectively plan for public improvements that support community needs in the areas of private development infrastructure, transportation, public safety, parks and recreation, utilities, and commercial /industrial growth through fiscally responsible economic development initiatives. Accordingly, this document attempts to recognize known or perceived capital improvement needs, but as with any plan recognizes that social, economic and political considerations will by necessity determine 2 final project outcomes. The major categories of expenditures that are identified within the CIP include, but are not limited to: 1. New Public Facilities Planning 2. Street Construction, Maintenance and Reconstruction 3. Utility Construction, Maintenance and Reconstruction 4. Construction, Maintenance and Upgrade of Parks, Playgrounds and Trails 5. Capital Improvements to Existing Facilities 6. Private development infrastructure 7. Capital equipment and vehicle planning needs (Equipment purchases to be determined through normal budgetary process) The City Council, consequently, accepts this document with the provision that capital improvement planning is subject to the dynamics of community growth, political leadership and acknowledges that other unanticipated needs may take precedence over planned projects. RECOMMENDATION The 2007 - 2011 Capital Improvement Plan is the product of collaborative planning efforts by City staff, the Park and Recreation Commission and the City Council. Projects have been introduced based on 1) anticipated future growth trends articulated in the City's 2020 Comprehensive Plan, 2) the natural cycle of deterioration and decay evident in all physically constructed and engineered improvements in the more established areas of the community and 3) capital deficiencies or infrastructure issues brought to the City's attention through a variety of sources. Capital expenditures identified within the CIP are the best estimates available, and once the CIP is adopted, will be reviewed and confirmed through individual feasibility reports where appropriate. I am appreciative of the commitment, good judgment and expertise that each department has contributed to the capital improvement planning process. Respectfully submitted, Jim Dickinson City Administrator / Finance Director 3 CIP PROJECT DEVELOPMENT AND PROCESS AUTHORIZATION SCHEDULE The following process is a Council /staff guideline for authorizing public improvement projects. As this process is controlled by State Statute and other influencing environmental factors, it is subject to change and should be viewed as a guide to assist the Council and public in understanding the public improvement process used by City staff. A separate Council meeting would facilitate each step in the process, and accomplishment of respective activities. As a result, the process time frame is a significant factor affecting City staff s ability to properly manage and complete approved Council ordered projects within budget and on time. 1. Council Approval of Annual CIP Projects by City Resolution will authorize the following outcomes: a) Staff and /or Consultant preparation of project feasibility studies b) Staff preparation of detailed financial review of project funding sources c) Neighborhood Meeting may be held prior to Feasibility Study subject to need and type of project. TIME FRAME: October - November of each preceding year. 2. Presentation of Feasibility Study a) Feasibility Study Components: 1) Review of Project Engineering and Construction Estimates 2) Total Project Costs (All related project costs, i.e. land, soft costs) 3) Project Financial Plan /Fiscal Implications (Engineering /Finance) 4) Authorization to develop a Preliminary Assessment Roll, if any, for the Public Hearing. (Engineering) • If Council accepts Feasibility Study, A Resolution "Accepting Feasibility Study and Setting Date for Public Hearing on the Project" when appropriate (Engineering Department) would initiate the following: 1) Notices mailed to affected Residents per statute requirements no less than 10 days before Public Hearing. (Engineering) 2) Public Hearing Notice is published. Two publications one week apart, with the second publication no less than three days before the hearing. (Engineering /City Clerk) TIME FRAME: February- March - April -May of current year. 3. Neighborhood Meeting — City staff will hold neighborhood project meetings, when appropriate, to review and present Project Feasibility Studies, answer questions and meet with affected property owners. These meetings will include a question and answer component designed specifically to bring awareness to the property owner, obtain citizen input and produce an understanding of the purposes behind the City's attempts to construct public improvements in the affected area. TIME FRAME: Following the presentation of the Feasibility Study to Council, but prior to the holding of a Public Hearing by Council. 4. Council holds a Public Hearing when appropriate for following purposes: a) Presentation of Project (Engineering Department) b) Presentation of Preliminary Special Assessment Rolls and Financing Implications (Engineering /Finance Department) c) Council to hear Affected Resident Input d) Council determines whether to "order" the public improvement 4 • A Council Resolution is drafted "Ordering the Project and Authorizing Preparation of Plans and Specifications" (Engineering Department). Council may ORDER THE IMPROVEMENT after the public hearing is closed or at a subsequent Council Meeting within 6 months of the public hearing date. (Statutory Requirement - Council Resolution ordering project must be approved on 415 Council vote if it is Council initiated project with assessments). • If Council decides to reject the project as presented, a Council vote should be taken to officially determine the final status of the project. TIME FRAME: April- May -June of current year 5. Plans and Specifications are presented to Council for approval. (Engineering Department) a) A Council Resolution is drafted authorizing the following: 1) Accepting and Approving Project Plans and Specifications 2) Authorizing the Advertisement for Project Bids. Bids are developed and invitation to Bid is processed. Bid opening date is no less than 3 weeks after publication. (Engineering) 3) Authorize staff to pursue an appropriate funding mechanism to underwrite project costs TIME FRAME: May -June of each year 6. Council Acceptance of Project Bids and Awarding of Contracts would authorize the following outcomes: a) A Council Resolution is drafted "Accepting Project Bids and Awarding Contracts" (Engineering) b) Initiation of Project Construction and work (Engineering) TIME FRAME: April- May- June -July of current year. 7. Project Completion a) Council Acceptance of Project b) Final Presentation and Review of Project Costs versus Project Budget by Finance Department. c) If Special Assessments are financing a portion of the Project, A Council Resolution "Setting the Special Assessment Hearing for Project #" is adopted at this same meeting. (Engineering /Finance) TIME FRAME: Upon completion of project. 8. If Special Assessments would finance a portion of the projects costs, Council Holds a Special Assessment Hearing to review the following: a) Affected Property owners would be officially notified per statute no less than two weeks prior to Special Assessment Hearing. (Clerk/Engineering) b) Public Notice is published no less than two weeks prior to Special Hearing per statute (Clerk /Engineering) c) Staff prepares a proposed roll and Council Approves Final Assessment Roll (Engineering/Finance) d) Council consideration of Assessment Appeals and Requested Deferrals filed prior to hearing or during the hearing. e) Meets M.S. Chapter 429 statutory requirements • A Council Resolution is drafted "Adopting Final Special Assessment Roll "(Engineering), and is adopted at this meeting. TIME FRAME: October/November of current year depending on finalization of project and status of completion. 5 CITY OF ANDOVER 2007 CIP Expenditures By Department Water Comm Ctr 1.00% Fire ° 0 28% 2.21% Sanitary Sewer Parks & Rec -Prof. � 11.42% 0.45% Street Signs � 0.15% Engineering 7.24% Storm Sewer 0.91 ° / — Facility Mgmt. 0.73% Streets /H ig hways 73.81% CITY OF ANDOVER 2007 CIP Expenditures By Year 2011 $4,282,016 2010 $7,957,486 2009 $9,159,888 2008 $7,993,799 2007 $5,514,842 2006 Adopted 5,690,013 $- $370007000 $670007000 $970007000 $127 0007000 0 City of Andover, MN Capital Plan 2007 thru 2011 DEPARTMENT SUMMARY Department 2007 2008 2009 2010 2011 Total Central Equipment 257,000 35,000 28,000 320,000 Community Center 15,500 7,000 7,000 15,000 44,500 Elections 100,000 100,000 Engineering 399,000 290,000 349,000 351,000 352,000 11741,000 Facility Management 40,000 1,843,217 1,882,000 341,000 34,000 41140,217 Fire 122,000 345,000 400,000 890,000 11757,000 Park & Rec - Operations 99,500 105,500 175,000 40,000 114,000 534,000 Park & Rec - Projects 630,000 217,000 110,000 675,000 25,000 1,657,000 Planning & Zoning 20,000 20,000 Sanitary Sewer 25,000 700,000 650,000 2,250,000 1,250,000 4,875,000 Storm Sewer 50,000 131,000 52,000 203,000 54,000 490,000 Street Signs 8,400 75,000 83,400 Streets / Highways 4,070,442 2,820,082 2,102,888 2,607,486 2,370,016 13,970,914 Water 55,000 1,340,000 3,175,000 550,000 55,000 5,175,000 GRAND TOTAL 5,514,842 7,993,799 9,159,888 7,957,486 4,282,016 34,908,031 7 City of Andover, MN Capital Plan 2007 tnru 2011 FUNDING SOURCE SUMMARY Source 2007 2008 2009 2010 2011 Total Assessments 873,092 331,896 228,765 691,417 1,302,267 3,427,437 Building Fund 515,217 515,217 Capital Equipment Reserve 242,000 242,000 Capital Projects Levy 78,400 143,000 22,000 23,000 24,000 290,400 Central Equipment Fund 7,000 35,000 28,000 70,000 Community Center Operations 15,500 7,000 7,000 15,000 44,500 Construction Seal Coat Fund 51,079 55,590 185,289 67,364 14,146 373,468 DNR Grant 62,500 62,500 Equipment Bond 711,500 900,500 776,000 890,000 74,000 3,352,000 Federal Funds 488,000 488,000 G.O. Bond 1,250,000 2,100,000 300,000 3,650,000 General Fund 10,000 57,000 50,000 58,000 50,000 225,000 Municipal State Aid Funds 542,000 1,055,400 275,000 567,000 643,000 3,082,400 Park Improvement Funds 567,500 217,000 110,000 675,000 25,000 1,594,500 R & B - Crack Seal & Seal Coat 326,393 314,706 478,539 746,452 653,801 2,519,891 R & B - Overlays 718,478 610,490 686,295 724,253 693,802 3,433,318 R & B - Pedestrian Trail 48,000 49,000 50,000 51,000 52,000 250,000 R & B - Reserve 201,300 57,000 59,000 61,000 63,000 441,300 Sanitary Sewer Fund 300,000 300,000 Sewer Revenue Bonds 650,000 650,000 Sewer Trunk Fund 207,000 520,500 124,000 2,150,000 400,000 3,401,500 Storm Sewer Fund 50,000 131,000 52,000 203,000 54,000 490,000 Trail Funds 210,000 210,000 Water Fund 55,000 63,000 50,000 50,000 55,000 273,000 Water Revenue Bonds 2,950,000 2,950,000 Water Trunk Fund 299,100 1,173,500 299,000 650,000 150,000 2,571,600 GRAND TOTAL 5,514,842 7,993,799 91159,888 7,957,486 4,282,016 34,908,031 City of Andover, MN Capital Plan 2007 thru 2011 PROJECTS & FUNDING SOURCES BY DEPARTMENT Department Project# Priority 2007 2008 2009 2010 2011 Total Central Equipment Canopy for Fuel Island 09- 48800 -01 3 250,000 250,000 G. 0. Bond 250,000 250,000 Replacement - Hotsy Pressure Washer 09- 48800 -02 3 7,000 7,000 Central Equipment Fund 7,000 7,000 Replacement - Floor Sweeper 10- 48800 -01 1 35,000 35,000 Central Equipment Fund 35,000 35,000 Replacement - Service Truck 10- 48800 -02 2 28,000 28,000 Central Equipment Fund 28,000 28,000 Central Equipment Total 2579000 359000 289000 320,000 Community Center Walk Behind Floor Scrubber 07- 44000 -01 1 7,500 7,500 Community Center Operations 7,500 7,500 Carpet - West Side Entrance 07- 44000 -02 2 8,000 8,000 Community Center Operations 8,000 8,000 Kitchen Equipment - Fryer /Grill 08- 44000 -01 2 7,000 7,000 Community Center Operations 7,000 7,000 Battery Pack Replacement - Zamboni 09- 44000 -01 2 7,000 7,000 Community Center Operations 7,000 7,000 Storage Building 10- 44000 -01 2 15,000 15,000 Community Center Operations 15,000 15,000 Community Center Total 159500 79000 79000 159000 44,500 Elections Voting Equipment 08- 41310 -01 1 100,000 100,000 Capital Projects Levy 100,000 100,000 Elections Total 1009000 100,000 Engineering New Development Projects 07- 41600 -01 1 351,000 241,000 248,000 300,000 300,000 15440,000 Sewer Trunk Fund 175,500 120,500 124,000 150,000 150,000 720,000 Water Trunk Fund 175,500 120,500 124,000 150,000 150,000 720,000 Pedestrian Trail Maintenance 07- 41600 -02 1 48,000 49,000 50,000 51,000 52,000 250,000 R & B - Pedestrian Trail 48,000 49,000 50,000 51,000 52,000 250,000 Replacement - Blazer #11 09- 41600 -01 2 30,000 30,000 Equipment Bond 30,000 30,000 Replacement - Total Station 09- 41600 -02 1 21,000 21,000 Equipment Bond 21,000 21,000 Department Project# Priority 2007 2008 2009 2010 2011 Total Engineering Total 2909000 3499000 3519000 Facility Management Carpet Replacement 07- 41900 -01 General Fund 10,000 Annual Parking Lot Maintenance 07- 41900 -02 Capital Projects Levy 10,000 Communication Radios 07- 41900 -03 Capital Projects Levy 10,000 Surface Seal all Brick Structures 08- 41900 -01 Capital Projects Levy 22,000 Water Fund 24,000 Land Purchase 08- 41900 -02 Building Fund 22, 000 Building A - Seal Floor 08- 41900 -03 General Fund 1 10,000 Salt Storage Building 08- 41900 -04 G.O. Bond Recycling Building & Fence 08- 41900 -05 G.O. Bond Attached Storage Building 08- 41900 -06 G.O. Bond 1 Fire St. #2 Addition and Parking Lot Improve. 08- 41900 -07 G.O. Bond Addition to Storage Building & Vehicle Maint. Shop 09- 41900 -01 G.O. Bond Pedestrian Tunnel Under Crosstown Blvd. 10- 41900 -01 G.O. Bond Facility Management Total Fire Rescue Truck 07- 42200 -01 Equipment Bond New Mobile Data Terminals in Fire Trucks 07- 42200 -02 Equipment Bond 515,217 Thermal Imaging Camera 07- 42200 -03 Equipment Bond 515,217 Replacement - Hydraulic Rescue Equipment 07- 42200 -04 Equipment Bond 8,000 Hose Washer /Tester 07- 42200 -05 Equipment Bond 7,000 Replacement - Fire Marshall Vehicle 08- 42200 -01 Equipment Bond 15,000 Replacement - Fire Tanker #31 08- 42200 -02 Equipment Bond Water /Ice rescue boat 08- 42200 -03 Equipment Bond 350,000 Replacement - Fire Engine #11 09- 42200 -01 Equipment Bond 350,000 Replacement - Ladder Truck #11 10- 42200 -01 Equipment Bond 3999000 2909000 3499000 3519000 3529000 1,741,000 2 10,000 10,000 10,000 10,000 10,000 50,000 10,000 10,000 10,000 10,000 10,000 50,000 1 20,000 21,000 22,000 23,000 24,000 110,000 20,000 21,000 22, 000 23,000 24,000 110,000 1 10,000 10,000 10,000 10,000 1 40,000 40,000 22, 000 22, 000 18,000 18,000 1 515,217 515,217 515,217 515,217 1 7,000 8,000 15,000 7,000 8,000 15,000 1 350,000 350,000 350,000 350,000 1 250,000 250,000 250,000 250,000 1 200,000 200,000 200,000 200,000 2 450,000 450,000 450,000 450,000 1 1,850,000 1,850,000 1,850,000 1,850,000 1 300,000 300,000 300,000 300,000 409000 198439217 198829000 3419000 349000 4,140, 217 1 40,000 40,000 40,000 40,000 2 30,000 30,000 30,000 30,000 1 14,000 14,000 14,000 14,000 2 30,000 30,000 30,000 30,000 2 8,000 8,000 8,000 8,000 2 30,000 30,000 30,000 30,000 1 295,000 295,000 295,000 295,000 1 20,000 20,000 20,000 20,000 1 400,000 400,000 400,000 400,000 1 850,000 850,000 850,000 850,000 10 Department Project# Priority 2007 2008 2009 2010 2011 Total Replacement - Fire Chief's Vehicle Equipment Bond 10- 42200 -02 2 40,000 40,000 40,000 40,000 Fire Total 1229000 3459000 4009000 8909000 Park & Rec - Operations Replace /Repair Play Structures - Various Parks 07- 45000 -01 2 40,000 40,000 40,000 40,000 40,000 Capital Projects Levy 40,000 General Fund 40,000 40,000 40,000 40,000 Replacement - Self- Propelled 48" Sweeper 07- 45000 -02 2 20,000 Equipment Bond 20,000 Zero Turn Mower 07- 45000 -03 1 7,500 Equipment Bond 7,500 Replacement - Toro Groundsmaster 328 07- 45000 -04 1 32,000 Equipment Bond 32,000 Truck - 3/4 Ton Crew Cab 08- 45000 -01 1 35,000 Equipment Bond 35,000 Replacement - Mower Trailer 08- 45000 -02 1 8,500 Equipment Bond 8,500 Replacement - Toro Groundmaster 08- 45000 -03 1 22,000 Equipment Bond 22,000 Replacement - Large Capacity Lawnmower 09- 45000 -01 1 112,000 Equipment Bond 112,000 Replacement - Toro Groundsmaster 09- 45000 -02 1 23,000 Equipment Bond 23,000 Replacement - Trailer 11- 45000 -01 2 9,000 Equipment Bond 9,000 Replacement - One Ton Pick Up w /Plow 11- 45000 -02 2 65,000 Equipment Bond 65,000 Park & Rec - Operations Total 999500 1059500 1759000 409000 1149000 Park & Rec - Projects Andover Station North Complex 07- 45001 -01 1 385,000 35,000 Park Improvement Funds 385,000 35,000 Terrace Park 07- 45001 -02 1 55,000 Park Improvement Funds 55,000 Crooked Lake Boat Landing 07- 45001 -03 1 125,000 DNR Grant 62,500 Park Improvement Funds 62,500 Strootman Park 07- 45001 -04 1 40,000 Park Improvement Funds 40,000 Annual Miscellaneous Projects 07- 45001 -99 1 25,000 25,000 25,000 25,000 25,000 Park Improvement Funds 25,000 25,000 25,000 25,000 25,000 Forest Meadows Park 08- 45001 -01 1 25,000 Park Improvement Funds 25,000 Sophies South Park 08- 45001 -02 1 75,000 Park Improvement Funds 75,000 Woodland Crossing Park 08- 45001 -03 1 57,000 Park Improvement Funds 57,000 Andover Lions Park 09- 45001 -01 1 85,000 Park Improvement Funds 85,000 Hawkridge Park Improvements 10- 45001 -01 1 500,000 11 1,757,000 200,000 40,000 160,000 20,000 20,000 7,500 7,500 32,000 32, 000 35,000 35,000 8,500 8,500 22,000 22, 000 112,000 11Z000 23,000 23,000 9,000 9,000 65,000 65,000 534,000 420,000 420,000 55,000 55,000 125,000 62, 500 62, 500 40,000 40,000 125,000 125,000 25,000 25,000 75,000 75,000 57,000 57,000 85,000 85,000 500,000 Department Project# Priority 2007 2008 2009 2010 2011 Total Park Improvement Funds 500,000 500,000 Prairie Knoll Park - Phase III 10- 45001 -02 1 150,000 150,000 Park Improvement Funds 150,000 150,000 Park & Rec - Projects Total 6309000 2179000 1109000 6759000 259000 1,657,000 t anning & Zoning Replacement - Ford Taurus #15 08- 41500 -01 2 20,000 20,000 Equipment Bond 20,000 20,000 Planning & Zoning Total 209000 20,000 Sanitary Sewer Lift Staion #1 Upgrade 07- 48200 -01 1 25,000 25,000 Sewer Trunk Fund 25,000 25,000 New Jet/Vac Truck 08- 48200 -01 1 300,000 300,000 Sanitary Sewer Fund 300,000 300,000 Crosstown Blvd Trunk Sewer Line 08- 48200 -02 1 400,000 400,000 Sewer Trunk Fund 400,000 400,000 Yellow Pine Lift Station 09- 48200 -01 1 650,000 650,000 Sewer Revenue Bonds 650,000 650,000 Rural Reserve Trunk Sanitary Sewer 10- 48200 -01 1 2,250,000 1,250,000 3,500,000 Assessments 250,000 1,000,000 1,250,000 Sewer Trunk Fund 2, 000, 000 250,000 2,250,000 Sanitary Sewer Total 259000 7009000 6509000 292509000 192509000 4,875,000 Storm Sewer Storm Sewer Improvements 07- 48300 -01 1 50,000 51,000 52,000 53,000 54,000 260,000 Storm Sewer Fund 50,000 51,000 52, 000 53,000 54,000 260,000 New Track Backhoe 08- 48300 -01 2 80,000 80,000 Storm Sewer Fund 80,000 80,000 Replacement - Elgin Street Sweeper 10- 43100 -01 1 150,000 150,000 Storm Sewer Fund 150,000 150,000 Storm Sewer Total 509000 1319000 529000 2039000 549000 490,000 Street Signs Radius Master Machine 07- 43300 -01 1 8,400 8,400 Capital Projects Levy 8,400 8,400 Replacement - Sign Truck #410 08- 43300 -01 2 75,000 75,000 Equipment Bond 75,000 75,000 Street Signs Total 89400 759000 83,400 Streets / Highways Annual Street Seal Coat Project 07- 43100 -01 1 287,632 271,328 480,438 660,377 515,760 25215,535 Construction Seal Coat Fund 41,965 31,092 176,194 65,397 14,146 328,794 R & B - Crack Seal & Seal Coat 245,667 240,236 304,244 594,980 501,614 1,886,741 Annual Street Crack Seal Project 07- 43100 -02 1 89,840 98,968 183,390 153,439 152,187 677,824 Construction Seal Coat Fund 9,114 24,498 9,095 1,967 0 44,674 R & B - Crack Seal & Seal Coat 80,726 74,470 174,295 151,472 152,187 633,150 Annual Street Mill and Overlay 07- 43100 -03 1 957,970 813,986 915,060 965,670 925,069 4,577,755 Assessments 239,492 203,496 228,765 241,417 231,267 1,144,437 12 Department Project# Priority 2007 2008 2009 2010 2011 Total R & B - Overlays 610,490 Annual Pavement Markings 07- 43100 -04 R & B - Reserve 3,433,318 Annual Curb Replacement 07- 43100 -05 R & B - Reserve 18,000 Mounted Pothole Spray Patcher 07- 43100 -06 Equipment Bond 16,000 Replacement - Dump Truck w/ Snow Removal #195 07- 43100 -07 Equipment Bond 85,000 Rail Road Quiet Zones 07- 43100 -08 Equipment Bond 43,000 Municipal State Aid Funds 210,000 Municipal State Aid Routes / New & Reconstruct 07- 43100 -09 Assessments 43,000 Federal Funds 210,000 Municipal State Aid Funds 500,000 R & B - Reserve Sewer Trunk Fund 150,000 Water Trunk Fund Intersection Upgrades 07- 43100 -10 Municipal State Aid Funds 150,000 Construct Bikeway/ Walkway Corridors 07- TRAIL -01 Trail Funds 1 Replacement - Hot Asphalt Box 08- 43100 -02 Equipment Bond 175,000 Dump Truck w /Snow Equipment 08- 43100 -04 Equipment Bond 200,000 Replacement - Dump Truck w/ Snow Removal #197 08- 43100 -05 Equipment Bond 2,950,000 Replacement - Water Tanker 09- 43100 -01 Equipment Bond Asphalt Paving Machine 09- 43100 -02 Equipment Bond 180,000 Streets / Highways Total 110,000 500,000 500,000 Water Rehabilitation of Wells 07- 48100 -01 Water Fund 500,000 Sealing of Well #1 07- 48100 -02 Water Fund 633,600 Water Main along South Coon Creek Drive 08- 48100 -01 Water Trunk Fund 71,000 Water Tower Painting 08- 48100 -02 Capital Equipment Reserve Water Trunk Fund Demolish 500,000 Gallon Water Tower 09- 48100 -01 Water Trunk Fund Construct Water Tower 09- 48100 -02 Water Revenue Bonds 146,300 WTP Reclaim Tank Addition 10- 48100 -01 Water Trunk Fund 718,478 610,490 686,295 724,253 693,802 3,433,318 1 15,000 16,000 17,000 18,000 19,000 85,000 15,000 16,000 17,000 18,000 19,000 85,000 1 40,000 41,000 42,000 43,000 44,000 210,000 40,000 41,000 42, 000 43,000 44,000 210,000 1 150,000 500,000 500,000 150,000 150,000 242,000 150,000 1 200,000 258,000 1 200,000 200,000 175,000 175,000 200,000 1 330,000 110,000 2,950,000 440,000 180,000 2,950,000 2,950,000 180,000 150,000 110,000 500,000 500,000 260,000 1 1,615,000 898,800 500,000 767,000 714,000 3,994,800 633,600 128,400 200,000 71,000 1,033,000 488,000 488,000 217,000 770,400 567,000 643,000 2,197, 400 146,300 146,300 6,500 6,500 123,600 123,600 1 175,000 175,000 275,000 625,000 175,000 175,000 275,000 625,000 1 210,000 210,000 210,000 210,000 1 40,000 40,000 40,000 40,000 2 155,000 155,000 155,000 155,000 1 200,000 200,000 200,000 200,000 2 100,000 100,000 100,000 100,000 1 90,000 90,000 90,000 90,000 490709442 298209082 291029888 296079486 293709016 13,970,914 1 45,000 45,000 50,000 50,000 55,000 245,000 45,000 45,000 50,000 50,000 55,000 245,000 2 10,000 10,000 10,000 10,000 1 795,000 795,000 795,000 795,000 1 500,000 500,000 242,000 242,000 258,000 258,000 1 175,000 175,000 175,000 175,000 1 2,950,000 25950,000 2,950,000 2,950,000 1 500,000 500,000 500,000 500,000 13 Department Water Total GRAND TOTAL Project# Priority 2007 2008 2009 2010 2011 Total 559000 193409000 391759000 5509000 559000 51175,000 595149842 799939799 991599888 799579486 492829016 34,908,031 14 City of Andover, MN Capital Plan 2007 thru 2011 DEPARTMENT SUMMARY Department 2007 2008 2009 2010 2011 Total Central Equipment 250,000 250,000 Community Center 8,000 15,000 23,000 Engineering 399,000 290,000 298,000 351,000 352,000 1,690,000 Facility Management 30,000 1,843,217 1,882,000 341,000 34,000 41130,217 Park & Rec - Operations 40,000 40,000 40,000 40,000 40,000 200,000 Park & Rec - Projects 630,000 217,000 110,000 675,000 25,000 1,657,000 Sanitary Sewer 25,000 400,000 650,000 2,250,000 1,250,000 4,575,000 Storm Sewer 50,000 51,000 52,000 53,000 54,000 260,000 Streets / Highways 3,720,442 2,425,082 1,912,888 2,607,486 2,370,016 13,035,914 Water 55,000 1,340,000 3,175,000 550,000 55,000 5,175,000 GRAND TOTAL 4,957,442 6,606,299 8,369,888 61882,486 4,180,016 30,996,131 15 City of Andover, MN Capital Plan 2007 tnru 2011 FUNDING SOURCE SUMMARY Source 2007 2008 2009 2010 2011 Total Assessments 873,092 331,896 228,765 691,417 1,302,267 3,427,437 Building Fund 515,217 515,217 Capital Equipment Reserve 242,000 242,000 Capital Projects Levy 60,000 43,000 22,000 23,000 24,000 172,000 Community Center Operations 8,000 15,000 23,000 Construction Seal Coat Fund 51,079 55,590 185,289 67,364 14,146 373,468 DNR Grant 62,500 62,500 Equipment Bond 180,000 180,000 Federal Funds 488,000 488,000 G.O. Bond 1,250,000 2,100,000 300,000 3,650,000 General Fund 10,000 57,000 50,000 58,000 50,000 225,000 Municipal State Aid Funds 542,000 1,055,400 275,000 567,000 643,000 3,082,400 Park Improvement Funds 567,500 217,000 110,000 675,000 25,000 1,594,500 R & B - Crack Seal & Seal Coat 326,393 314,706 478,539 746,452 653,801 2,519,891 R & B - Overlays 718,478 610,490 686,295 724,253 693,802 3,433,318 R & B - Pedestrian Trail 48,000 49,000 50,000 51,000 52,000 250,000 R & B - Reserve 201,300 57,000 59,000 61,000 63,000 441,300 Sewer Revenue Bonds 650,000 650,000 Sewer Trunk Fund 207,000 520,500 124,000 2,150,000 400,000 3,401,500 Storm Sewer Fund 50,000 51,000 52,000 53,000 54,000 260,000 Trail Funds 210,000 210,000 Water Fund 55,000 63,000 50,000 50,000 55,000 273,000 Water Revenue Bonds 2,950,000 2,950,000 Water Trunk Fund 299,100 1,173,500 299,000 650,000 150,000 2,571,600 GRAND TOTAL 4,957,442 6,606,299 81369,888 6,882,486 4,180,016 30,996,131 16 City of Andover, MN Capital Plan 2007 thru 2011 PROJECTS &FUNDING SOURCES BY DEPARTMENT Department Project# Priority 2007 2008 2009 2010 2011 Total Central Equipment Canopy for Fuel Island 09- 48800 -01 3 250,000 250,000 G.O. Bond 250,000 250,000 Central Equipment Total 2509000 250,000 Community Center Carpet - West Side Entrance 07- 44000 -02 2 8,000 8,000 Community Center Operations 8,000 8,000 Storage Building 10- 44000 -01 2 15,000 15,000 Community Center Operations 15,000 15,000 Community Center Total 89000 159000 23,000 t mi=ering New Development Projects 07- 41600 -01 1 351,000 241,000 248,000 300,000 300,000 15440,000 Sewer Trunk Fund 175,500 120,500 124,000 150,000 150,000 720,000 Water Trunk Fund 175,500 120,500 124,000 150,000 150,000 720,000 Pedestrian Trail Maintenance 07- 41600 -02 1 48,000 49,000 50,000 51,000 52,000 250,000 R & B - Pedestrian Trail 48,000 49,000 50,000 51,000 52,000 250,000 Engineering Total 3999000 2909000 2989000 3519000 3529000 1,690,000 Facility Management Carpet Replacement 07- 41900 -01 2 10,000 10,000 10,000 10,000 10,000 50,000 General Fund 10,000 10,000 10,000 10,000 10,000 50,000 Annual Parking Lot Maintenance 07- 41900 -02 1 20,000 21,000 22,000 23,000 24,000 110,000 Capital Projects Levy 20,000 21,000 22, 000 23,000 24,000 110,000 Surface Seal all Brick Structures 08- 41900 -01 1 40,000 40,000 Capital Projects Levy 22,000 22,000 Water Fund 18,000 18,000 Land Purchase 08- 41900 -02 1 515,217 515,217 Building Fund 515,217 515,217 Building A - Seal Floor 08- 41900 -03 1 7,000 8,000 15,000 General Fund 7,000 8,000 15,000 Salt Storage Building 08- 41900 -04 1 350,000 350,000 G.O. Bond 350,000 350,000 Recycling Building & Fence 08- 41900 -05 1 250,000 250,000 G.O. Bond 250,000 250,000 Attached Storage Building 08- 41900 -06 1 200,000 200,000 G.O. Bond 200,000 200,000 Fire St. #2 Addition and Parking Lot Improve. 08- 41900 -07 2 450,000 450,000 17 Department Project# Priority 2007 2008 2009 2010 2011 Total G.O. Bond 450,000 Addition to Storage Building & Vehicle Maint. Shop 09- 41900 -01 G.O. Bond 450,000 Pedestrian Tunnel Under Crosstown Blvd. 10- 41900 -01 G.O. Bond Facility Management Total 1,850,000 1 55,000 Park & Rec - Operations Replace /Repair Play Structures - Various Parks 07- 45000 -01 Capital Projects Levy 1 General Fund Park & Rec - Operations Total 300,000 1 125,000 Park & Rec - Projects Andover Station North Complex 07- 45001 -01 Park Improvement Funds 300,000 Terrace Park 07- 45001 -02 Park Improvement Funds 3419000 Crooked Lake Boat Landing 07- 45001 -03 DNR Grant 40,000 Park Improvement Funds 40,000 Strootman Park 07- 45001 -04 Park Improvement Funds Annual Miscellaneous Projects 07- 45001 -99 Park Improvement Funds 40,000 Forest Meadows Park 08- 45001 -01 Park Improvement Funds 40,000 Sophies South Park 08- 45001 -02 Park Improvement Funds 409000 Woodland Crossing Park 08- 45001 -03 Park Improvement Funds 200,000 Andover Lions Park 09- 45001 -01 Park Improvement Funds 25,000 Hawkridge Park Improvements 10- 45001 -01 Park Improvement Funds 25,000 Prairie Knoll Park - Phase III 10- 45001 -02 Park Improvement Funds 25,000 Park & Rec - Projects Total 25,000 Sanitary Sewer Lift Staion #1 Upgrade 07- 48200 -01 Sewer Trunk Fund Crosstown Blvd Trunk Sewer Line 08- 48200 -02 Sewer Trunk Fund Yellow Pine Lift Station 09- 48200 -01 Sewer Revenue Bonds Rural Reserve Trunk Sanitary Sewer 10- 48200 -01 Assessments Sewer Trunk Fund 1 385,000 450,000 450,000 1 35,000 1,850,000 1,850,000 1 55,000 1,850,000 1,850,000 1 300,000 300,000 1 125,000 300,000 300,000 309000 198439217 198829000 3419000 349000 4,130, 217 2 40,000 40,000 40,000 40,000 40,000 200,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 160,000 409000 409000 409000 409000 409000 200,000 1 385,000 35,000 420,000 385,000 35,000 420,000 1 55,000 55,000 55,000 55,000 1 125,000 125,000 6Z500 62, 500 62, 500 62, 500 1 40,000 40,000 40,000 40,000 1 25,000 25,000 25,000 25,000 25,000 125,000 25,000 25,000 25,000 25,000 25,000 125,000 1 25,000 25,000 25,000 25,000 1 75,000 75,000 75,000 75,000 1 57,000 57,000 57,000 57,000 1 85,000 85,000 85,000 85,000 1 500,000 500,000 500,000 500,000 1 150,000 150,000 150,000 150,000 6309000 2179000 1109000 6759000 259000 1,657,000 1 25,000 25,000 25,000 25,000 1 400,000 400,000 400,000 400,000 1 650,000 650,000 650,000 650,000 1 2,250,000 1,250,000 3,500,000 250,000 1,000,000 1,250,000 2, 000, 000 250,000 Z250,000 18 Department Project# Priority 2007 2008 2009 2010 2011 Total Sanitary Sewer Total 4009000 6509000 292509000 Storm Sewer Storm Sewer Improvements 07- 48300 -01 Storm Sewer Fund 52,000 52, 000 Storm Sewer Total 54,000 54,000 Streets / Highways 509000 Annual Street Seal Coat Project 07- 43100 -01 Construction Seal Coat Fund 549000 R & B - Crack Seal & Seal Coat 1 89,840 Annual Street Crack Seal Project 07- 43100 -02 Construction Seal Coat Fund 152,187 R & B - Crack Seal & Seal Coat 9,114 Annual Street Mill and Overlay 07- 43100 -03 Assessments 0 R & B - Overlays 80,726 Annual Pavement Markings 07- 43100 -04 R & B - Reserve 152,187 Annual Curb Replacement 07- 43100 -05 R & B - Reserve 915,060 Rail Road Quiet Zones 07- 43100 -08 Equipment Bond 239,492 Municipal State Aid Funds 228,765 Municipal State Aid Routes / New & Reconstruct 07- 43100 -09 Assessments 718,478 Federal Funds 686,295 Municipal State Aid Funds 693,802 R & B - Reserve 1 15,000 Sewer Trunk Fund 17,000 Water Trunk Fund 19,000 Intersection Upgrades 07- 43100 -10 Municipal State Aid Funds 17,000 Construct Bikeway/ Walkway Corridors 07- TRAIL -01 Trail Funds 1 40,000 Streets / Highways Total 42,000 43,000 44,000 Water Rehabilitation of Wells 07- 48100 -01 Water Fund 43,000 Sealing of Well #1 07- 48100 -02 Water Fund 110,000 Water Main along South Coon Creek Drive 08- 48100 -01 Water Trunk Fund 440,000 Water Tower Painting 08- 48100 -02 Capital Equipment Reserve Water Trunk Fund 180,000 Demolish 500,000 Gallon Water Tower 09- 48100 -01 Water Trunk Fund Construct Water Tower 09- 48100 -02 Water Revenue Bonds 898,800 259000 4009000 6509000 292509000 192509000 4,575,000 1 50,000 50,000 51,000 51,000 52,000 52, 000 53,000 53,000 54,000 54,000 260,000 260,000 509000 519000 529000 539000 549000 260,000 1 287,632 271,328 480,438 660,377 515,760 25215,535 41,965 31,092 176,194 65,397 14,146 328,794 245,667 240,236 304,244 594,980 501,614 1,886,741 1 89,840 98,968 183,390 153,439 152,187 677,824 9,114 24,498 9,095 1,967 0 44,674 80,726 74,470 174,295 151,472 152,187 633,150 1 957,970 813,986 915,060 965,670 925,069 4,577,755 239,492 203,496 228,765 241,417 231,267 1,144, 437 718,478 610,490 686,295 724,253 693,802 3,433,318 1 15,000 16,000 17,000 18,000 19,000 85,000 15,000 16,000 17,000 18,000 19,000 85,000 1 40,000 41,000 42,000 43,000 44,000 210,000 40,000 41,000 42, 000 43,000 44,000 210,000 1 330,000 110,000 440,000 180,000 180,000 150,000 110,000 260,000 1 1,615,000 898,800 767,000 714,000 3,994,800 633,600 128,400 200,000 71,000 1,033,000 488,000 488,000 217,000 770,400 56 7, 000 643,000 2,197, 400 146,300 146,300 6,500 6,500 123,600 123,600 1 175,000 175,000 275,000 625,000 175,000 175,000 275,000 625,000 1 210,000 210,000 210,000 210,000 3,7209442 294259082 199129888 296079486 293709016 13,035,914 1 45,000 45,000 50,000 50,000 55,000 245,000 45,000 45,000 50,000 50,000 55,000 245,000 2 10,000 10,000 10,000 10,000 1 795,000 795,000 795,000 795,000 1 500,000 500,000 242,000 24Z 000 258,000 258,000 1 175,000 175,000 175,000 175,000 1 2,950,000 25950,000 Z 950, 000 Z 950, 000 19 Department Project# Priority 2007 2008 2009 2010 2011 Total WTP Reclaim Tank Addition 10- 48100 -01 1 500,000 500,000 Wafer Trunk Fund 500,000 500,000 Water Total 559000 193409000 391759000 5509000 559000 5,175,000 GRAND TOTAL 499579442 696069299 893699888 698829486 491809016 30,996,131 20 Capital Plan 2007 rhru 2011 Justification I The canopy would keep the fuel pumps, gasboy equipment, operators dry and help keep sun, rain and snow damage to a minimum. It would also keep the fuel in the tanks from getting contaminated. The larger tanks will allow us to have tanker drops of 7,500 gallons of fuel, saving us money and the frequency of the drops that we now have. The tanks are approximately 18 years old and are warranted for 30 years. The pumps were installed in 1999 and are in good shape. Expenditures 2007 2008 2009 2010 2011 Total Improvement 250,000 250,000 Total 250,000 250,000 Funding Sources 2007 2008 2009 2010 2011 Total G.O. Bond 250,000 250,000 Total 250,000 250,000 Operational Impact /Other I The larger tanks will allow us to have a tanker drops of 7,500 gallons of fuel, saving us money and the frequency of the drops that we now have. Friday, October 27, 2006 21 Capital Plan City of Andover, MN Project # 07- 44000 -02 Project Name Carpet - West Side Entrance Type Improvement Useful Life 10 Years Category Improvements Description Install carpet tiles inside the west end doors. 2007 thru 2011 Priority 2 - Medium Contact Comm Ctr Manager Department Community Center 5 A= k� Justification The carpet tiles would give the entrance a more finished look. In addition to keeping snow / salt / sand from making it's way down the hall during the winter months, the tiles can be replaced as they go bad without having to change the entire carpet area. Expenditures 2007 2008 2009 2010 2011 Total Improvement 8,000 8,000 Total 89000 8,000 Funding Sources 2007 2008 2009 2010 2011 Total Community Center Operations 8,000 8,000 Total 89000 8,000 Operational Impact /Other I It would save staff from having to mop or scrub the entrance area as much. It also would be safer in the winter months due to the concrete floor getting slippery. We currently have a contract to rent carpet runners in the winter and spring that would no longer be needed. Friday, October 27, 2006 22 Capital Plan 2007 rhru 2011 Justification As the Community Center continues to grow and acquire more recreational equipment, tables, chairs etc., there will be a lack of storage space. We would only buy equipment if there was a need for it in the field house and if it would help increase rental hours. Some of the equipment would be rented out to users and create additional revenues. Expenditures 2007 2008 2009 2010 2011 Total Construction 15,000 15,000 Total 15,000 15,000 Funding Sources 2007 2008 2009 2010 2011 Total Community Center Operations 15,000 15,000 Total 15,000 15,000 Operational Impact /Other I The additional space would provide storage for equipment and would need to have electricity and heat. This space would free up some space in what has already become a crowded field house storage room. Friday, October 27, 2006 23 Capital Plan City of Andover, MN 2007 thru 2011 Project # 07- 41600 -01 , Project Name New Development Projects Type Improvement Priority 1 -High Useful Life 50 Years Contact City Engineer Category New Development Projects Department Engineering � AMEMKI & Description New developments include the construction of sanitary sewer, water main, storm sewers and streets. Since the majority of the improvement projects are being privately installed by the developer, the following expenditures are the city's share for trunk water and sewer improvements. Note: All private development construction is dependent upon market conditions, plat approval and normal City development procedures. Justification The develoment phasing is identified in the City's Comprehensive Plan. Expenditures 2007 2008 2009 2010 2011 Total Construction 351,000 241,000 248,000 300,000 300,000 11440,000 Total 3519000 2419000 2489000 3009000 3009000 194409000 Funding Sources 2007 2008 2009 2010 2011 Total Sewer Trunk Fund 175,500 Water Trunk Fund 175,500 120,500 120,500 124,000 124,000 150,000 150,000 150,000 150,000 720,000 720,000 Total 3519000 2419000 2489000 3009000 300,000 194409000 Operational Impact /Other I Additional maintenance of streets, storm sewer, water main and sanitary sewer will result. Additional streets will be added for snowplowing. Friday, October 27, 2006 24 Capital Plan 2007 rhru 2011 Justification City trails are in need of general maintenance including bituminous patching, crack filling and restoration to maintain the high level of service to pedestrian walkers, bikers and roller bladers. A 5 -year capital improvement plan was prepared for the City to identify and prioritize the necessary repairs. Expenditures 2007 2008 2009 2010 2011 Total Improvement 48,000 49,000 50,000 51,000 52,000 250,000 Total 489000 499000 509000 519000 529000 2509000 Funding Sources 2007 2008 2009 2010 2011 Total R & 6 - Pedestrian Trail 48,000 49,000 50,000 51,000 52,000 250,000 Total 489000 499000 509000 519000 529000 2509000 Operational Impact /Other I As the city trail system begins to age, general maintenance such as bituminous patching, crack filling and restoration becomes a necessity. The maintenance will allow for a longer service life for the trail system throughout the city. Friday, October 27, 2006 25 Capital Plan City of Andover, MN 2007 thru 2011 Project # 07- 41900 -01 A Project Name Carpet Replacement Type Improvement Priority 2 - Medium ,fur L Useful Life 10 Years Contact PW Superintendent Category Equipment Department Facility Management Description The replacement of carpet in appropriate areas of all City buildings where deemed necessary. An annual review of all carpeted areas will be done to determine the order of replacement. Justification The buildings get a lot of use and, despite the appropriate cleaning and maintenance, the carpeted areas will need to be replaced. Expenditures 2007 2008 2009 2010 2011 Total Facility Maintenance 10,000 10,000 10,000 10,000 10,000 50,000 Total 109000 109000 109000 109000 109000 509000 Funding Sources 2007 2008 2009 2010 2011 Total General Fund 10,000 10,000 10,000 10,000 10,000 50,000 Total 109000 109000 109000 109000 109000 509000 Operational Impact /Other I The carpet replacement will be needed in order to keep the buildings in good repair. Due to heavy use, it is anticipated that all carpeted areas will need to be replaced. Friday, October 27, 2006 26 Capital Plan City of Andover, MN Project # 07- 41900 -02 Project Name Annual Parking Lot Maintenance 2007 thru 2011 Type Improvement Priority 1 -High Useful Life 10 Years Contact City Engineer Category Improvements Department Facility Management ice► Description Yearly maintenance of the City parking lots is necessary to extend their useful lives. Parking lots that need maintaining include those at the City Hall complex, Public Works, Community Center, at City parks, and at the Fire Stations. Yearly maintenance may include crack sealing, seal coating, and mill and overlays. Maintenance will generally be completed with the street zones, or on an as needed basis. Justification Completing periodic maintenance on the City parking lots, similar to City streets, will extend the overall design life of the pavement and reduce and /or prolong costly repairs. Expenditures 2007 2008 2009 2010 2011 Total Improvement 20,000 21,000 22,000 23,000 24,000 110,000 Total 209000 219000 229000 239000 249000 1109000 Funding Sources 2007 2008 2009 2010 2011 Total Capital Projects Levy 20,000 21,000 22,000 23,000 24,000 110,000 Total 209000 219000 229000 239000 249000 1109000 Operational Impact /Other I Maintaining the parking lots will result in less annual maintenance for public works and prolong the life of the pavements. Friday, October 27, 2006 27 Capital Plan City of Andover, MN 1ject # 08- 41900 -01 2007 thru 2011 Justification This is a necessary maintenance item to ensure the long term integrity of the municipal buildings. Expenditures 2007 2008 2009 2010 2011 Total Facility Maintenance 40,000 40,000 Total 40,000 40,000 Funding Sources 2007 2008 2009 2010 2011 Total Capital Projects Levy 22,000 22,000 Water Fund 18,000 18,000 Total 409000 409000 Operational Impact /Other I This will reduce the amount of long term maintenance and repair to the municipal buildings. Friday, October 27, 2006 28 Capital Plan City of Andover, MN eject # 08- 41900 -02 Useful Life Unassigned Category Improvements 2007 thru 2011 Contact PW Superintendent Department Facility Management r Bry Justification This is the last opportunity to purchase this property and keep city facilities together in one complex. Future site expansion opportunities are limited without additional property. Expenditures 2007 2008 2009 2010 2011 Total Land Acquisition 515,217 515,217 Total 515,217 515,217 Funding Sources 2007 2008 2009 2010 2011 Total Building Fund 515,217 515,217 Total 515,217 515,217 Operational Impact /Other I Large cost savings in keeping facilities together. Another large savings is having a salt storage area on the property. The recycling center would be moved away from the parks and this would help maintain cleaner parks on the complex. It would also provide a large storage area for the seal coat rock, sweeping, etc. Open land areas in Andover will soon be a thing of the past. Friday, October 27, 2006 29 Y o F Capital Improvement Plan C NT DOVE Project Name: LAND PURCHASE Z rHTINGALE F(- )x 0 ESTATES � Q HOLLOW Z = TES w c� 0 AN' O I VD city 0 Hall Park Complex #1 z �S- 1�� z z G� D r M U)i OT L w o Q a O ES cri LL � Sunshine C. <- Park Cf, 0 J m Location Map LEGEND W Right of Way Lots /Parcels ' r Water o 345 sso 1,380 Park City Limits Feet r Project Location 30 tD '�` Capital Plan City of Andover, MN Project # 08- 41900 -03 Project Name Building A - Seal Floor Type Improvement Useful Life 2 Years Category Facility Management 2007 thru 2011 Priority I -High Contact PW Superintendent Department Facility Management Description Apply a sealant to the cement floor in Building A (large garage). w. �Y Justification The cement floor in Building A spalds due to salt and traffic from daily vehicles use. Sealing of the floors should be repeated every 2 years to retain the integrity of the floor surface. Without this process, the cement floor would deteriorate and would have to be replaced. It is much more cost effective to perform the maintenance than to replace the entire floor. Expenditures 2007 2008 2009 2010 2011 Total Facility Maintenance 7,000 8,000 15,000 Total 7,000 8,000 15,000 Funding Sources 2007 2008 2009 2010 2011 Total General Fund 7,000 8,000 15,000 Total 7,000 8,000 Operational Impact /Other I Gives use a much longer life of the cement floor, than having to replace it before its life expectancy is up. 31 15,000 Friday, October 27, 2006 Capital Plan City of Andover, MN Project # 08- 41900 -04 Project Name Salt Storage Building 2007 thru 2011 Type Improvement Priority I -High Useful Life 30 Years + Contact PW Superintendent Category Facility Management Department Facility Management Description This salt storage building would be 40'x 50'x 25' high. The City would be able to purchase a season's worth of salt and keep it stored inside this structure out of the elements. We would meet all environmental specifications needed for this type of storage, with no damage to the product being stored. This facility would be built to blend in with the rest of the City complex and not a sight distraction within the campus. Justification At the present time the City purchases salt from Anoka County, which has been done since the City was first adopted. This puts us at the mercy of the county operations, causing situations such as what time someone will be there to load our trucks, do they have an adequate supply of salt needed at all times. We have had good working relations with the county, but they also would like to see us be able to store our own winter supply so they would be able to keep a larger supply of salt for county use. Cost savings is also a large part of having our own storage. We can purchase product at $10.00 to 15.00 per ton less, plus we wouldn't be paying a 15% administration fee for county personnel services. This building will pay for itself over a short period of time. Expenditures 2007 2008 2009 2010 2011 Total Construction 350,000 350,000 Total 350,000 350,000 Funding Sources 2007 2008 2009 2010 2011 Total G.O. Bond 350,000 350,000 Total 350,000 350,000 Operational Impact /Other I Having this building right here on campus will save a great deal of personnel time, trucking, and fuel costs. The salt not used could be returned to the storage building and not dumped outside where it gets wet and damaged, or becomes an environmental problem. Friday, October 27, 2006 32 Capital Plan City of Andover, MN Project # 08- 41900 -05 Project Name Recycling Building & Fence 2007 thru 2011 Type Improvement Priority 1 -High Useful Life 15 -20 Years Contact PW Superintendent Category Facility Management Department Facility Management Description Move Recycling Center from location on Tower Drive to new location located north of the water treatment facility. A new building that will be constructed of materials that will best blend in with the rest of the public works campus. This structure will have to be larger than the present one so more recycled materials can be stored inside and with less chance of the lighter materials blowing out. Also need more room for outside storage, a paved drive surface, completely fenced, better security lighting, and updated security camera's. Justification At the present location we have just plain run out of room! And the recycling center will have to be moved do to it now sits in the foot print of the new addition of the vehicle storage building. Also as clean as we try to keep this area, it is probably not the best neighbor to the Community Center and YMCA do to items that blow out of the recycling storage yard. Also it would be best to keep the large trucks off of Tower Drive for safety reason, due to narrow streets and a lot of pedestrian traffic. Expenditures 2007 2008 2009 2010 2011 Total Construction 250,000 250,000 Total 250,000 250,000 Funding Sources 2007 2008 2009 2010 2011 Total G.O. Bond 250,000 250,000 Total 250,000 250,000 Operational Impact /Other I In the new location we will most likely be able to keep a closer watch on the area. It will still be within the area of the public works so there would be no extra cost in maintenance of the grounds and with a larger area it will be more customer friendly. Friday, October 27, 2006 33 Capital Plan City of Andover, MN Project # 08- 41900 -06 Project Name Attached Storage Building Type Improvement Useful Life 25 Years Category Facility Management 2007 thru 2011 Priority 1 -High Contact PW Superintendent Department Facility Management Description Three sided attachment building 25'x 50'. This building will be used for small equipment that can be stored in all types of temperature but under a roof to protect it from the elements. It will also work as screening the facility. Expenditures 2007 2008 2009 2010 2011 Total Construction 200,000 200,000 Total 200,000 200,000 Funding Sources 2007 2008 2009 2010 2011 Total G.O. Bond 200,000 200,000 Total Operational Impact /Other 200,000 34 200,000 Friday, October 27, 2006 Capital Plan 2007 rhru 2011 Justification I The additional space to the building will allow for all vehicles to be parked in front of an exit door. The firefighters will not have to move a vehicle in order to get another one out of the building. The additional bay will also make clean up operations after an event much easier. The firefighters will not have to move vehicles out of the building in order to clean hose and equipment. The additional parking space will provide for much needed hard surface training area and more vehicle parking. Replacement of the existing parking lots is necessary due to the heavy fire vehicle traffic. Expenditures 2007 2008 2009 2010 2011 Total Equipment 35,000 35,000 Improvement 415,000 415,000 Total 4509000 4509000 Funding Sources 2007 2008 2009 2010 2011 Total G.O. Bond 450,000 450,000 Total 4509000 4509000 Operational Impact /Other I The additional space will make all fire operations more efficient at this building. Vehicles will not have to be moved in order to get others out and clean -up will be much easier and faster. Friday, October 27, 2006 35 Capital Plan City of Andover, MN 2007 thru 2011 Project # 09- 41900 -01 Project Name Addition to Storage Building & Vehicle Maint. Shop Type Improvement Priority I -High Useful Life 30 Years + Contact PW Superintendent Category Facility Management Department Facility Management Description This is an addition to the present vehicle storage building. It will be added to the north end of the present building and be the same in size, 100' x 250' with a 75'x 140' addition to the northwest side of the new vehicle storage garage for the vehicle maintenance shop. This building will be built with cement panels to match the present vehicle garage and would screen Public Works operations from the Community Center /YMCA as proposed in a joint meeting with the Mayor and City Council. Justification Due to the increase of vehicles, equipment and supplies now used by the City of Andover, this vehicle storage building and vehicle maintenance repair shop is badly needed. It is not cost effective to have vehicles or other equipment stored outside. Minnesota's four seasons are way too hard on them and it makes for a much cleaner operation. The vehicle maintenance repair shop has been needed for a long time. The area now used has doors that are not wide enough and work areas for the hydraulic hoist are way too small. Also with the amount of equipment now maintained by our staff in the area is much too small to run a completely safe operation. Expenditures 2007 2008 2009 2010 2011 Total Improvement 1,850,000 1,850,000 Total 1,850,000 1,850,000 Funding Sources 2007 2008 2009 2010 2011 Total G.O. Bond 1,850,000 1,850,000 Total 1,850,000 1,850,000 Operational Impact /Other This will impact the life of the vehicles and other equipment by being stored inside and to house our vehicle maintenance mechanics. Over the years, the cost savings have been shown when the proper maintenance of our equipment can be implemented. This building will provide a safe, productive, and healthy operational area for City employees that will benefit the City of Andover for many years. Friday, October 27, 2006 36 Capital Plan City of Andover, MN Project # 10- 41900 -01 Project Name pedestrian Tunnel Under Crosstown Blvd. 2007 thru 2011 Type Improvement Priority I -High Useful Life 30 Years + Contact PW Superintendent Category Facility Management Department Facility Management Description This would be a pedestrian underpass walkway under Crosstown to accommodate pedestrian traffic from a possible development of a parking lot or other sports fields on the north side of Crosstown Boulevard that could crossunder Crosstown Boulevard to Sunshine Park Facilities or just connect to the cities trail system. Justification This item was discussed at a Council Workshop with the Public Works Department Managers February 16th 2006. For safety and for easy access for crossing Crosstown Boulevard from a future park and /or future parking lot on the north side of Crosstown Boulevard to Sunshine Park on the South side, or just getting to the city trail system the quickest and safest way will be a pedestrian underpass under Crosstown Boulevard. Expenditures 2007 2008 2009 2010 2011 Total Improvement 300,000 300,000 Total 300,000 300,000 Funding Sources 2007 2008 2009 2010 2011 Total G.O. Bond 300,000 300,000 Total 300,000 300,000 Operational Impact /Other Connecting of these area's though a trail system, or underpass will only benefit our operational impact. This underpass will also add to the safety of our personnel and equipment. That is the smaller equipment that now has to cross a very busy street, could also use the underpass. Keeping the camauses formate works well in holding down operational cost. Friday, October 27, 2006 37 Capital Plan City of Andover, MN 2007 thru 2011 Project # 07- 45000 -01 Project Name Replace/Repair Play Structures - Various Parks Type Improvement Useful Life 10 Years Category Park Improvements Priority 2 - Medium Contact PW Superintendent Department Park & Rec - Operations Description Repair to fall zones and achieve ADA accessibility. Replacement of playground equipment and other major replacements, such as short fences on ball fields, soccer goals, or any area of play that does not meet safety specifications. Justification Old equipment no longer meets ADA requirements, such as entrapments, fall zones or handicap accessibility. Working to bring the parks up to meet all safety requirements. Expenditures 2007 2008 2009 2010 2011 Total Equipment 40,000 40,000 40,000 40,000 40,000 200,000 Total 409000 409000 409000 409000 409000 2009000 Funding Sources 2007 2008 2009 2010 2011 Total Capital Projects Levy 40,000 40,000 General Fund 40,000 40,000 40,000 40,000 160,000 Total 409000 409000 409000 409000 409000 2009000 Operational Impact /Other I Less maintenance and will meet all safety requirements. 38 Friday, October 27, 2006 Capital Plan City of Andover, MN Project # 07- 45001 -01 Project Name Andover Station North Complex 2007 thru 2011 Type Improvement Priority 1 -High Useful Life 30 Years + Contact City Engineer Category Park Improvements Department Park & Rec - Projects s Description Continued development and construction of an Athletic /Park Complex south of the WDE site. With the fields due to be completed in the fall of 2006; bleachers and playground equipment will be necessary. In order to maximize the usage of the fields, lighting of the two larger fields is necessary with the possibility of lighting the third and smaller field. 2007 - $20,000 for 3 sets of bleachers, $65,000 for playground equipment and $300,000 to light the 2 larger fields and possibly the smaller field. 2008 - $35,000 for playground equipment. Note: Parking would be shared with the businesses. Justification The bleachers are necessary to allow the spectators to enjoy watching the games without having to stand for long periods of time. The playground equipment will allow families with children not playing baseball the opportunity to enjoy another activity. The lighting of the fields allows additional games and practices to be played during the evenings. Expenditures 2007 2008 2009 2010 2011 Total Improvement 385,000 35,000 420,000 Total 3859000 359000 4209000 Funding Sources 2007 2008 2009 2010 2011 Total Park Improvement Funds 385,000 35,000 420,000 Total 3859000 359000 4209000 Operational Impact /Other I Routine maintenance will be required to upkeep the field and park. Friday, October 27, 2006 39 C I T Y 0 F Capital Improvement Plan NDOVE Project Name: BALL FIELD FACILITY SOUTH OF THE WDE E /42N D AVE KS The 0 aks C/) Park z T-T IN, BENS IN G " ) OSSTM17N ESTATES H EA DC-AX'S 142NDAVE KENSIN --tTON ESTATES I . 1ADDITION Red Oaks L East Park 67-] Cf Hills & S1 PARKSIDE 13 H La k V, AT Cr. AND(AT N— LL ON K < RED 0. KS 0 . , M 11, AN[ R/ 4TH/ADD C 139TH AVE Z C) ANDOVER STATION NORTH U) 0 Z 0 U) Z RED C)AKS < I J t I H MANOR 6TH ADD Location Map w E 0 0 E G E N D IF L I City Limits o Water 0 340 680 1,360 L Park EJ i M Lots/Parcels Feet T�- 9 M �n A Project Location 40 Capital Plan City of Andover, MN Project # 07- 45001 -02 Project Name Terrace Park 2007 thru 2011 i ype improvement rriority i - nlgn —� Useful Life 25 Years Contact City Engineer Mn _ Category Park Improvements Department Park & Rec - Projects Li. I - t_ Description Install new basketball court and parking lot with concrete curb and gutter along with completing a small section of trail to provide access to the playground equipment and the other portions of the park. Justification The existing parking lot is currently gravel. Since this is located in an urban area, the parking lot should be paved and the neighborhood residents have requested a basketball court. Also, the trail to the playground area needs to be paved. This project has been recommended by the Park & Recreation Commission. Expenditures 2007 2008 2009 2010 2011 Total Improvement 55,000 55,000 Total 559000 55,000 Funding Sources 2007 2008 2009 2010 2011 Total Park Improvement Funds 55,000 55,000 Total 559000 Operational Impact /Other I Additional long -term maintenance and ultimately replacement will be necessary. 55,000 Friday, October 27, 2006 41 qC I T Y 0 F CNDOVE01 Capital Improvement Plan Project Name: TERRACE PARK LL Ll b 'CREEK L D -J a U 0 -J 7TH AVE BUN1KltK LAKL b CH,;kPm- ANS-' ---'—CHAP:N4ANS' _3 RD 1ADD 2ND ADD % I I 1:36TH E- CHAPMANS—Vo I CHAPMANS ADD ' LL 4'� I H. ADD 135TH LN'0 II 111—F -CHAPNL CHAPMANS-7� 6T14 ADD NTH ADD WVODLAN. TERRACE 3 I RD ADD Terrace Park I I I L WOODLAND / TERRACt 4TH ADD 0 M Cn > Cn I WOODLAND TERRACE 5TH ADD N L E G E N D w e E Right of Way S Lots/Parcels Water 0 310 620 1,240 Park =Emir Feet City Limits Project Location 42 �a 1611-1 `moo woo�l� US CT :-A 174 M ME All Capital Plan City of Andover, MN Project # 07- 45001 -03 Project Name Crooked Lake Boat Landing Type Improvement Useful Life 25 Years Category Park Improvements 2007 thru 2011 Priority 1 -High Contact City Engineer Department Park & Rec - Projects -1114 1WVr I.- a m Description Construct new parking lot, install new dock and dredge boat landing area. This project will go forward with the assistance of a MN DNR Matching Grant. Justification The existing parking lot is beyond its normal maintenance requirements. Surface has deteriorated and a number of pot holes have been filled up to this point. A boat dock is necessary for individuals launching their boat. Also, the boat landing has silted in and needs to be removed to allow boats to maneuver. This project has been recommended by the Park & Recreation Commission. Expenditures 2007 2008 2009 2010 2011 Total Improvement 125,000 125,000 Total 1259000 125,000 Funding Sources 2007 2008 2009 2010 2011 Total DNR Grant 62,500 62,500 Park Improvement Funds 62,500 62,500 Total 1259000 Operational Impact /Other I Normal maintenance (sealcoating, striping, etc.) will be necessary. 43 125,000 Friday, October 27, 2006 T Y o F Capital Improvement Plan CNDOVE Project Name: CROOKED LAKE BOAT LANDING IT'O'WNHOMES M LIN 'k , F EU 0F= W00DLAND Uh L'CREEK E: H AVE BUN '0s G \�O �P 1C16111 L Hal L E G E N D C� City Limits Water Park �C] Lots /Parcels Right of Way HOWARD- Project Location ►DOW/CREEI ESTATE( Mzl �i 5 0 ""'- ki'A71 LAKEVIEW TERRACE COUNTRY ,EST ADD AUD ' I SUB -102- MATT S ON & DEGARDNER CR LIB LUNDGREN i I �a 0 310 620 1,240 Feet 44 AUDI C� �C] HOWARD- 0 #'MPE. 0 ADDITI�(3N M rn 1 L�� r � r H 35TH CIR � 1 T Do r C ZP S ADD M /AV C EASfBR00 TERRACE MATT S ON & DEGARDNER CR LIB LUNDGREN i I �a 0 310 620 1,240 Feet 44 AUDI Capital Plan City of Andover, MN Project # 07- 45001 -04 Project Name Strootman Park 2007 thru 2011 Type Improvement Priority 1 -High Useful Life 25 Years Contact City Engineer - Category Park Improvements Department Park & Rec - Projects Description Reconstruct existing ballfield and replace fencing. The ballfield will be reduced in size for players generally under the age of 12. In addition, there will not be an outfield fence so the field can be used for other sports as well. Justification Current ballfield fencing does not meet League of MN Cities guidelines and needs to be replaced. This project has been recommended by the Park & Recreation Commission. Expenditures 2007 2008 2009 2010 2011 Total Improvement 40,000 40,000 Total 409000 40,000 Funding Sources 2007 2008 2009 2010 2011 Total Park Improvement Funds 40,000 40,000 Total 409000 Operational Impact /Other I Normal maintenance will be necessary. 45 40,000 Friday, October 27, 2006 C I T Y o F Capital Improvement Plan C DOVER0111Project Name: STROOTMAN PARK RI.�TR F =)REST C INDI AN 1\ IEAD M A� Strootman Park z F-- LL -A D: VER --� �N E ST C M E N Location Map LEGEND og 0 City Limits S a a Water a a PL Park 0 495 990 1,980 0 Lots /Parcels EJ Feet a Right of Way a Project Location 46 Capital Plan City of Andover, MN Project # 07- 45001 -99 Project Name Annual Miscellaneous Projects Type Improvement Useful Life Unassigned Category Park Improvements 2007 thru 2011 Priority 1 -High Contact City Engineer Department Park & Rec - Projects Description This is for unforeseen or requested miscellaneous projects that may arise during the year, requested by the public, staff, City Council or the Parks and Recreation Commission for each year. Justification This gives flexibility to the City to do certain small -sized projects that may be warranted; for example, purchase of soccer goals. This funding has been recommended by the Park & Recreation Commission. Expenditures 2007 2008 2009 2010 2011 Total Improvement 25,000 25,000 25,000 25,000 25,000 125,000 Total 259000 259000 259000 259000 259000 1259000 Funding Sources 2007 2008 2009 2010 2011 Total Park Improvement Funds 25,000 25,000 25,000 25,000 25,000 125,000 Total 259000 259000 259000 259000 259000 1259000 Operational Impact /Other I Allows the Park and Recreation Commission to address a variety of different needs throughout the year. Friday, October 27, 2006 47 Capital Plan City of Andover, MN Project # 08- 45001 -01 Project Name Forest Meadows Park Type Improvement Useful Life 15 Years Category Park Improvements 2007 thru 2011 Priority I -High Contact City Engineer Department Park & Rec - Projects Description Install additional playground equipment for 2 -5 year old users. Justification This funding has been recommended by the Park & Recreation Commission. AM Expenditures 2007 2008 2009 2010 2011 Total Improvement 25,000 25,000 Total 25,000 25,000 Funding Sources 2007 2008 2009 2010 2011 Total Park Improvement Funds 25,000 25,000 Total 25,000 Operational Impact /Other I Additional long -term maintenance and ultimately replacement will be necessary. 48 25,000 Friday, October 27, 2006 C z v o r NDOVE001 FOREST C apital Improvement Plan Project Name: FOREST MEADOWS PARK 11IEAI)(_)WS X TDE TTE BROTHERS _SDI) Forest Meadows N L E G E N D w City Limits s Water Park 0 450 900 1,800 Lots /Parcels Feet Right of Way Project Location 4 9 Capital Plan City of Andover, MN Project # 08- 45001 -02 Project Name Sophies South Park 2007 thru 2011 Type Improvement Priority I -High Useful Life 15 Years Contact City Engineer Category Park Improvements Department Park & Rec - Projects Description Install new playground equipment and basketball court. The park was dedicated as part of the development of Sophies South. Since no park exists within the general area, it was recommended to begin developing the park. Justification This funding has been recommended by the Park & Recreation Commission. Expenditures 2007 2008 2009 2010 2011 Total Improvement 75,000 75,000 Total 75,000 75,000 Funding Sources 2007 2008 2009 2010 2011 Total Park Improvement Funds 75,000 75,000 Total 75,000 Operational Impact /Other I Additional long -term maintenance and ultimately replacement will be necessary. 50 75,000 Friday, October 27, 2006 c z v o r N:D0VE001 C apital Improvement Plan Project Name: SOPHIE'S SOUTH PARK ophie's Par v N L E G E N D w E City Limits s Water Park 0 220 440 880 Lots /Parcels Feet Right of Way Project Location 51 Capital Plan City of Andover, MN eject # 08- 45001 -03 Useful Life 15 Years Category Park Improvements 2007 thru 2011 Contact City Engineer Department Park & Rec - Projects Justification The park will have a new basketball court and shelter built in 2006. To complete the park, new playground equipment is necessary for all ages from 2 - 12 years old. Expenditures 2007 2008 2009 2010 2011 Total Improvement 57,000 57,000 Total 57,000 57,000 Funding Sources 2007 2008 2009 2010 2011 Total Park Improvement Funds 57,000 57,000 Total 57,000 Operational Impact /Other I Additional long -term maintenance and ultimately replacement will be necessary. 57,000 Friday, October 27, 2006 52 C NT Y o F Capital Improvement Plan DOVE Project Name: WOODLAND CROSSINGS J m z PRAIRIE 4 COVE Z a T. 15,L N 1 8TH LN CHE C J- YF AL o rE w � 158 LJJ o CRO J OY 157TH CIR H LN sxaw�s �❑ 'sue T GLEN y <�, El GREY OAKS Location Map W LEGEND S l City Limits Water 0 235 ago sao Park r El Lots /Parcels Feet Project Location 53 '�` Capital Plan City of Andover, MN Project # 09- 45001 -01 Project Name Andover Lions Park Type Improvement Useful Life 25 Years Category Park Improvements 2007 thru 2011 Priority 1 -High Contact City Engineer Department Park & Rec - Projects Description Install outfield fencing with mow strips for ballfield and install new irrigation system. 8 foot high fencing with mow strips - $35,000 and irrigate existing ballfield - $50,000. Justification The installation of an outfield fence will allow the ball to stay in play and also give the awesome feeling when a ball is hit for a home run. Also give the players a safer playing surface by installing a irrigation system. This project has been recommended by the Park & Recreation Commission. Expenditures 2007 2008 2009 2010 2011 Total Improvement 85,000 85,000 Total 85,000 85,000 Funding Sources 2007 2008 2009 2010 2011 Total Park Improvement Funds 85,000 85,000 Total 85,000 Operational Impact /Other I Additional long -term maintenance and ultimately replacement will be necessary. 54 85,000 Friday, October 27, 2006 qC I T Y or CNDOVERM C 0 -,J Vt 4 A-Z CreeK Park Redwood Park Capital Improvement Plan Project Name: ANDOVER LIONS PARK OX: 'cif —Porvyv, WHISPERING I -ACRE I Andover Lions ill: f vix L 0 0 C-3 Sy L E G E N D W City Limits S Water Park 0 415 830 1,660 Lots/Parcels Feet Right of Way Project Location 55 UN, Capital Plan City of Andover, MN Project # 10- 45001 -01 Project Name Hawkridge Park Improvements 2007 thru 2011 Type Improvement Priority 1 -High Useful Life 30 Years Contact City Engineer Category Park Improvements Department Park & Rec - Projects Description The project includes the construction of a warming house, construction of a well w /pump and controls, installation of irrigation for the soccer and ball fields, playground equipment for children 2 -5 years of age and bleachers for sporting spectators. Storage building /bathrooms /concessions - $209,000; drill well with pump & controls - $100,000; septic system - $7,500; pave existing parking lot - $90,000; irrigation for 2 fields - $50,000; playground Equipment (2 -5 year olds) - $25,000; bleachers with concrete pads(soccer & ballfield) - $15,000; security light - $2,500; park signage and landscaping - $1,000. Justification By continuing to improve the park system in Andover, the City provides a high quality parks and recreation complex to meet the growing needs of an active community. These improvements will provide high quality athletic and recreational opportunities to the residents. A warming house provides shelter and a restroom facility that can be used year around. The well and irrigation provide for a high quality athletic surface for soccer, baseball /softball activities and water for the restroom. Playground equipment provides activities for younger children and bleachers provide a safe and comfortable place for spectators. This project has been recommended by the Park & Recreation Commission. Expenditures 2007 2008 2009 2010 2011 Total Improvement 500,000 500,000 Total 500,000 500,000 Funding Sources 2007 2008 2009 2010 2011 Total Park Improvement Funds 500,000 500,000 Total 5009000 5009000 Operational Imp act /Other The construction of a warming house and restroom facility will increase the use and enjoyment of the park. Also, the construction of the storage /warming house /restroom facility will eliminate the need to rent a portable warming house and portable bathroom. The well construction will give the ability to ice the rinks from the on -site well and will eliminate the need to "tanker" water to the site from the Public Works facility on Crosstown Blvd. The alavaround eauipment will reauire additional long -term maintenance and ultimate realacement will be necessarv. Friday, October 27, 2006 56 T Y o F Capital Improvement Plan n NDOVE Project Name: HAWKRIDGE PARK Capital Plan City of Andover, MN Project # 10- 45001 -02 Project Name prairie Knoll Park - Phase III Type Improvement Useful Life 25 Years Category Park Improvements 2007 thru 2011 Priority 1 -High Contact City Engineer Department Park & Rec - Projects Description 2010 - The parking lot would be paved including concrete curb and gutter ($150,000). F {_ Justification Prairie Knoll Park is considered a regional city park and completion would bring it into compliance with City standards due to the increased use by the associations for both soccer and football. This project has been recommended by the Park & Recreation Commission. Expenditures 2007 2008 2009 2010 2011 Total Improvement 150,000 150,000 Total 150,000 150,000 Funding Sources 2007 2008 2009 2010 2011 Total Park Improvement Funds 150,000 150,000 Total 150,000 Operational Impact /Other I Additional long -term maintenance and ultimately replacement will be necessary. 58 150,000 Friday, October 27, 2006 ?C I T Y o F Capital Improvement Plan CND0VEFAkProject Name: PRAIRIE KNOLL PARK PHASE III Capital Plan 2007 rhYu 2011 Useful Life 15 -20 Years Category Improvements Contact PW Superintendent Department Sanitary Sewer s. via 3n r. A. _ —mop.- Justification I This lift station is the most active lift station currently in use. When it was designed it was only to be a temporary lift station, but those plans have since changed. Over the past few years there have been many power outages of which some have required tempoary power to keep it in operation to avoid backups into the homes. A permanent generator at this site would be in everyones best interests. Expenditures 2007 2008 2009 2010 2011 Total Improvement 25,000 25,000 Total 259000 25,000 Funding Sources 2007 2008 2009 2010 2011 Total Sewer Trunk Fund 25,000 25,000 Total 259000 25,000 Operational Impact /Other I There would be a time savings by not having to get tempoary service to this site. It takes two employee's about an hour and a half to get to the site and hooked up for operations. There will be some operational impacts for maintenance and the cost of natural gas. There will be a maintenance contract with the suaalier to make sure the generator is always in full operation. Friday, October 27, 2006 60 T Y o F Capital Improvement Plan n NDOVE Project Name: LIFT STATION #1 IMPROVEMENTS 147TH AVE 145 fuleado.. of Round Lake Park � i 4 N . 0 � AP Q 'rO(J M L. p Pleasant Oaks Park 1 r DEHNS ADD I J Deh n's Park DEHNS 2ND ADD N Location Map w 0 o ad UJ LEGEND og 0 City Limits s a a Watera rn a 0 Park 0 295 590 1,180 -P ip, Lots /Parcels Feet a Project Location a J Lift Stations 61 Capital Plan City of Andover, MN 2007 thru 2011 Type Improvement Priority I -High Useful Life 50 Years Contact City Engineer 9 ' ~� Category Improvements Department Sanitary Sewer Description Extend sanitary sewer trunk along Crosstown Boulevard from the railroad tracks east to Prairie Road. It will be necessary to jack the sanitary sewer underneath the railroad. Justification The trunk sanitary sewer will be extended to serve properties adjacent to Crosstown Boulevard and east of Prairie Road. The extension has been recommended through the sanitary sewer report (2004 Sanitary Sewer Report). Expenditures 2007 2008 2009 2010 2011 Total Improvement 400,000 400,000 Total 400,000 400,000 Funding Sources 2007 2008 2009 2010 2011 Total Sewer Trunk Fund 400,000 400,000 Total 400,000 Operational Impact /Other I Additional routine maintenance including televising and cleaning will be required. 62 400,000 Friday, October 27, 2006 T Y o F Capital Improvement Plan n NDOVE Project Name: CROSSTOWN BLVD SEWER LINE 2008 Capital Plan City of Andover, MN Project # 09- 48200 -01 Project Name Yellow Pine Lift Station 2007 thru 2011 Type Improvement Priority I -High Useful Life 50 Years Contact PW Superintendent Category Improvements Department Sanitary Sewer, Description Install a lift station at Yellow Pine Street to divert flow from the Bluebird Street trunk line to the Pinewood trunk line. The wet well for this lift station was constructed in 2005 as a part of the Crosstown Boulevard Improvements Project. Justification This lift station will allow additional capacity in the Bluebird Street trunk line to serve adjacent properties until the year 2020. Expenditures 2007 2008 2009 2010 2011 Total Improvement 650,000 650,000 Total 650,000 650,000 Funding Sources 2007 2008 2009 2010 2011 Total Sewer Revenue Bonds 650,000 650,000 Total Operational Impact /Other I Routine monitoring and maintenance of the lift station will be required. 64 650,000 650,000 Friday, October 27, 2006 T Y o F Capital Improvement Plan N:D0VE00JProject Name: YELLOW PINE LIFT STATION Capital Plan City of Andover, MN Project # 10- 48200 -01 Project Name Rural Reserve Trunk Sanitary Sewer Type Improvement Useful Life 50 Years Category Unassigned 2007 thru 2011 Priority I -High Contact Department Sanitary Sewer Description Extension of trunk sanitary sewer from Bunker Lake Boulevard approximately parallel to Coon Crook to serve the Rural Reserve area. The sanitary sewer will be constructed through existing neighborhoods and along South Coon Creek Drive then north into the Rural Reserve Area. It is anticipated that the extension through the Rural Reserve may be constructed the following year, or as the market demands. Justification The trunk sanitary sewer will be extended to serve future development of the Rural Reserve. The timing of this extension will be market driven based upon developer' timelines for the Rural Reserve. The extension has been recommended in the Trunk Sanitary Sewer Analysis for Designated Rural Reserve Areas prepared by WSB and Associates. Expenditures 2007 2008 2009 2010 2011 Total Construction 2,250,000 1,250,000 3,500,000 Total 292509000 192509000 395009000 Funding Sources 2007 2008 2009 2010 2011 Total Assessments 250,000 1,000,000 11250,000 Sewer Trunk Fund 2,000,000 250,000 2,250,000 Total 292509000 192509000 395009000 Operational Impact /Other I Additional routine maintenance including televising and cleaning will be required. Friday, October 27, 2006 �i�rin�°rr YA Capital Plan 2007 rhru 2011 Justification Maintaining the City's storm sewer system improves water quality, improves public safety, and reduces the need for costly repairs in the future. Repairing and maintaining these systems also allows public works to focus on and comply with requirements of the NPDES program, such as pipe cleaning, inspections, and sweeping. Expenditures 2007 2008 2009 2010 2011 Total Construction 50,000 51,000 52,000 53,000 54,000 260,000 Total 509000 519000 529000 539000 549000 2609000 Funding Sources 2007 2008 2009 2010 2011 Total Storm Sewer Fund 50,000 51,000 52,000 53,000 54,000 260,000 Total 50,000 519000 529000 539000 549000 2609000 Operational Impact /Other I Repairing problem areas in the storm sewer system will reduce the yearly maintenance needs placed on the public works personnel. Friday, October 27, 2006 68 T Y o F Capital Improvement Plan n NDOVE Project Name: REPAIR AT 141 STAVE IN SMITH'S GREEN ACRES Capital Plan 2007 rhru 2011 Useful Life 7 Years Category Streets /Highways Contact City Engineer Department Streets/ Highways Justification I Seal coating will extend the useful life of roads by protecting the bituminous from oxidation due to adverse weather conditions (sun, rain, wind, snow, etc.). The prevention of oxidation will prolong the useful life of the pavement and defer the need for a costly reconstruction. Seal coating also improves the skid resistance of the roadway surface by increasing the friction between vehicle tires and the roadway. New developments requiring seal coating are not shown on the attached maps. Expenditures 2007 2008 2009 2010 2011 Total Construction 287,632 271,328 480,438 660,377 515,760 2,215,535 Total 2879632 2719328 4809438 6609377 5159760 292159535 Funding Sources 2007 2008 2009 2010 2011 Total Construction Seal Coat Fund 411965 R & 6 - Crack Seal & Seal Coa 245,667 31,092 240,236 176,194 304,244 65,397 594,980 14,146 501,614 328,794 1,886,741 Total 2879632 2719328 4809438 6609377 5159760 292159535 Operational Impact /Other I Extending the life of the street will reduce routine maintenance (Crack sealing, pot hole patching, overlays, etc.) and extend the overall design life of the pavement. Friday, October 27, 2006 70 k NTV or DOVE Capital Improvement Plan Project Name: ANNUAL STREET SEAL COAT PROJECT 2007 STREET SEAL COAT, ZONE 5 L E G E N D Right of Way Lots /Parcels Water � Park City Limits 43 Project Location 2,400 1,200 0 2,400 Feet 71 u Location Map k NT Y o F Capital Improvement Plan DOVE Project Name: ANNUAL STREET SEAL COAT PROJECT 2008 STREET SEAL COAT, ZONE 6 7� ..u� so =ell:■ �.�. ■ L E G E N D IN <1 u r 4,400 2,200 0 4,400 Feet 72 Location Map Right of Way Lots /Parcels Water � Park City Limits 43 Project Location IN <1 u r 4,400 2,200 0 4,400 Feet 72 Location Map k NT Y o F Capital Improvement Plan DOVE Project Name: ANNUAL STREET SEAL COAT PROJECT 2009 STREET SEAL COAT, ZONE 7 L E G E N D > O � 0 � 1,750 875 0 1,750 Feet 73 �d 1_ Location Map Right of Way Lots /Parcels Water Park City Limits Project Location > O � 0 � 1,750 875 0 1,750 Feet 73 �d 1_ Location Map k N' '1 O DOVEI� Capital Improvement Plan Project Name: ANNUAL STREET SEAL COAT PROJECT 2010 STREET SEAL COAT, ZONE 8 L E G E N D Right of Way Lots /Parcels Water � Park City Limits 43 Project Location 2,000 1,000 0 2,000 Feet 74 EK Location Map kT Y o F Capital Improvement Plan N'DOVETIProject Name: ANNUAL STREET SEAL COAT PROJECT 2011 STREET SEAL COAT, ZONE 9 Rx'V'U�Nn LrA. L E G E N D 2,200 1,100 0 2,200 Feet 75 K Location Map Right of Way Lots /Parcels Water � Park City Limits 43 Project Location 2,200 1,100 0 2,200 Feet 75 K Location Map Capital Plan City of Andover, MN Project # 07- 43100 -02 Project Name Annual Street Crack Seal Project 2007 thru 2011 Type Improvement Priority 1 -High Useful Life 7 Years Contact City Engineer Category Streets /Highways Department Streets/ Highways Description The project provides for sealing of the street cracks in the following maintenance zones: 2007 - Zone 6 2008 - Zone 7 2009 - Zone 8 and 9 2010 - Zone 1 2011 - Zone 2 Justification The sealing of street cracks will significantly extend the useful life of the streets. This will extend the time frame when a costly street reconstruction project will be necessary. The sealing of cracks in the street surface reduces /eliminates water from entering the road base and subgrade. This process reduces the freeze /thaw cycles of the subgrade, maintaining the integrity of the road. Crack sealing is completed in a particular zone one year prior to seal coating. This allows the crack sealing material to cure and minimize bleed through once seal coated. New developments requiring crack seal are not shown on the attached maps. Expenditures 2007 2008 2009 2010 2011 Total Construction 89,840 98,968 183,390 153,439 152,187 677,824 Total 899840 989968 1839390 1539439 1529187 6779824 Funding Sources 2007 2008 2009 2010 2011 Total Construction Seal Coat Fund 9,114 R & B - Crack Seal & Seal Coa 80,726 24,498 74,470 9,095 174,295 1,967 151,472 0 44,674 152,187 633,150 Total 899840 989968 1839390 1539439 1529187 6779824 Operational Impact /Other I Sealing the street cracks will reduce routine maintenance by eliminating the source of degradation resulting from moisture in the road subgrade. Friday, October 27, 2006 76 k NDOVE01 T Y o F Capital Improvement Plan P roject Name: ANNUAL STREET CRACK SEAL PROJECT 2007 STREET CRACK SEAL, ZONE 6 7� ,.,.� so ��Ill�ulllll� " "" ••� =ell:■ �.�. ■ L E G E N D IN u i r 4,400 2,200 0 4,400 Feet 77 Location Map Right of Way Lots /Parcels Water � Park City Limits 43 Project Location IN u i r 4,400 2,200 0 4,400 Feet 77 Location Map k NT Y o F Capital Improvement Plan DOVE Project Name: ANNUAL STREET CRACK SEAL PROJECT 2008 STREET CRACK SEAL, ZONE 7 L E G E N D w J Q Z_ F </� Z 7�0 1,750 875 0 1,750 Feet 78 i Location Map Right of Way Lots /Parcels Water � Park City Limits 43 Project Location w J Q Z_ F </� Z 7�0 1,750 875 0 1,750 Feet 78 i Location Map k NT Y o F Capital Improvement Plan DOVE Project Name: ANNUAL STREET SEAL COAT PROJECT 2009 STREET SEAL COAT, ZONE 7 L E G E N D > O � 0 � 1,750 875 0 1,750 Feet 79 �d 1_ Location Map Right of Way Lots /Parcels Water Park City Limits Project Location > O � 0 � 1,750 875 0 1,750 Feet 79 �d 1_ Location Map k N' '1 O DOVEI� Capital Improvement Plan Project Name: ANNUAL STREET SEAL COAT PROJECT 2010 STREET SEAL COAT, ZONE 8 L E G E N D Right of Way Lots /Parcels Water � Park City Limits 43 Project Location 2,000 1,000 0 2,000 Feet 61 EK Location Map kT Y o F Capital Improvement Plan N'DOVETIProject Name: ANNUAL STREET SEAL COAT PROJECT 2011 STREET SEAL COAT, ZONE 9 Rx'V'U�Nn LrA. L E G E N D 2,200 1,100 0 2,200 Feet 81 K Location Map Right of Way Lots /Parcels Water � Park City Limits 43 Project Location 2,200 1,100 0 2,200 Feet 81 K Location Map Capital Plan City of Andover, MN Project # 07- 43100 -03 Project Name Annual Street Mill and Overlay 2007 thru 2011 Type Improvement Priority 1 -High Useful Life 20 Years Contact City Engineer Category Streets /Highways Department Streets/ Highways Description The Street Mill and Overlay projects will consist of milling the existing street surface and constructing a new asphalt surface. Minor shouldering and restoration work will be included with the project. In developments that have existing bituminous curb or no curb or ditch, concrete curb and gutter will be constructed. 25% of the total project costs are assessed to the benefiting properties in each development. This program helps to maintain the integrity and value of the communities street infrastructure. Areas to be reconstructed are shown on the attached maps and are listed below. The timing of reconstruction of developments more than two years out may be revised as street conditions and ratings are reviewed on an annual basis. Additional developments may be added to the schedule or projects moved up if it is advantageous to reconstruct them in conjunction with other nearby projects. 2007 - Indian Meadows 3rd Addition, Kelsey Estates, Woodland Ridge 2008 - Northglen, Grow Oakview Estates 2009 - Stenquist Addition, Johnson's Oakmount Terrace, Ivywood Estates 2010 - Prairie Meadows, Enchanted Drive Area, Alladin Acres 2011 - Langseth- Thrane 1 st and 2nd Additions, Xenia Street / Vintage Street / 161 st Avenue Justification The streets in these neighborhoods are in excess of 20 years old and are in need of rehabilitation. The intent of this Street Mill and Overlay is to provide the community with a high quality transportation system and maintain a constant upkeep of the City's street infrastructure. Expenditures 2007 2008 2009 2010 2011 Total Construction 957,970 813,986 915,060 965,670 925,069 4,577,755 Total 9579970 8139986 9159060 9659670 9259069 495779755 Funding Sources 2007 2008 2009 2010 2011 Total Assessments 239,492 R & 6 - Overlays 718,478 203,496 610,490 228,765 686,295 241,417 724,253 231,267 693,802 1,144,437 3,433,318 Total 9579970 8139986 9159060 9659670 9259069 495779755 Operational Impact /Other I The rehabilitation of the streets will reduce the routine maintenance (Crack sealing, pot hole patching, etc..) in the area. Long term, this reconditioning will prolong the structural stability of the roadway making for a longer serviceable life. Friday, October 27, 2006 82 T Y o F Capital Improvement Plan N:DOVERMProject Name: ANNUAL MILLAND OVERLAY (2007) INDIAN MEADOWS 3RD ADD. &KELSEY ESTATES m IND IAN Dpi S5 :ADD U) Q Q KEL SE 1 2 ES RTES ANDOVER WEST FL E N Location Map 0 o g 0 00 L E G E N D S 0 0 Right of Way oo a Lots /Parcels 0 320 640 1,280 0 Water E El Feet a J Park � a City Limits 83 T Y o F Capital Improvement Plan ?CND0VEFAkProject Name: ANNUAL MILLAND OVERLAY (2007) WOODLAND RIDGE T Y o F Capital Improvement Plan ?CND0VEFAkProject Name: ANNUAL MILLAND OVERLAY (2008) NORTHGLEN 3RD ADD. &DOWNTOWN CENTER ORTHGLE 4TH ADDS ,J .J,9TH LN 1,4 `O�S7 v w c� z WOODLAND rpND L E G E N D Right of Way Lots /Parcels Water � Park City Limits a z I I I I H Y QUICKSTROM ADD D J m W Y Q LOCAL J OIL � Z ADD D O Lu 4)r P, LAM� I 7h. -1 ( Park G` U R 138TH CT VJr 142N�p��' I- 0 385 770 1,54 Feet 85 W R IN ,; K 0 i4TK z A�� I Ll 2ND ADD. WOODLA GREEK 2ND n ADD WOODLAND CREEK I J L I Cn J [., � ® UWNHI O m OF -WOO ut } LCRE J m J_ ui J �%' I 37TH AVE BUNKE I ?C I T Y o F Capital Improvement Plan CND0VEFAkProject Name: ANNUAL MILLAND OVERLAY (2008) GROW OAK VIEW ESTATES ?C I T Y o F Capital Improvement Plan CND0VEFAkProject Name: ANNUAL MILLAND OVERLAY (2009) IVYWOOD ESTATES C z v o r NDOVE001 RUM RIVER INCH ESTATES L E G E N D Right of Way Lots /Parcels Water Park City Limits C apital Improvement Plan Project Name: ANNUAL M I LL AN D OVERLAY (2009) STENQUIST ADDITION STENQUIS,T ADDITION 1 I bU 0 365 730 1,460 Feet Memo, REG LAND SURVEY NO. 072 REG-L-AND SURVEY N0�072 ?C I T Y o F Capital Improvement Plan CND0VEFAkProject Name: ANNUAL MILLAND OVERLAY (2009) JOHNSON'S OAKMOUNT TERRACE ?C I T Y o F Capital Improvement Plan CND0VEFAkProject Name: ANNUAL MILLAND OVERLAY (2010) ALLADIN ACRES & N. ENCHANTED DR AREA ?C I T Y o F Capital Improvement Plan CND0VEFAkProject Name: ANNUAL MILLAND OVERLAY (2010) PRAIRIE MEADOWS ES 171 STAVE EY\VIEW S 2ND ADD n x N DEER 70TH LN SYLVESTER OAKS co ADD 0 0 0 > PRAIRIE MEADOWS J 00 W Q Z D! TIMBER MEADOWS oBS ADD 167TH LN 6TH L N Location Map LEGEND w � o E_ o od og Right of Way s Lots /Parcels a a 0 Water 0 435 870 1,740 0 Park0 City Limits Feet a a Project Location 91 CNDOVE01 z v o r C apital Improvement Plan Project Name: ANNUAL MILLAND OVERLAY (2011) LANGSETH THRANE 1ST & 2ND ADD. � 175TH LN a_ o J J m W Y 174TH L a J z G � `O L ti�tiQ' O OLESEN -2ND LANGSETH 17 PINE ACRES ADDITION 2ND ADD LANGSETH TIIRANE LANGSETH 171 ST AVE IEW :) ADD L E G E N D Right of Way Lots /Parcels Water Park City Limits Project Location �1 0 387.5 775 1,550 Feet DEER ?C I T Y o F Capital Improvement Plan CND0VEFAkProject Name: ANNUAL MILLAND OVERLAY (2011) XENIA- VINTAGE STREET AREA Capital Plan 2007 rhru 2011 Useful Life 1 -2 Years Category Improvements Contact City Engineer Department Streets/ Highways Justification Striping is required through the local and state agencies. A reflective standard is required. Restriping annually maintains the pavement markings to the required standards. Expenditures 2007 2008 2009 2010 2011 Total Improvement 15,000 16,000 17,000 18,000 19,000 85,000 Total 159000 169000 179000 189000 199000 859000 Funding Sources 2007 2008 2009 2010 2011 Total R & 6 - Reserve 15,000 16,000 17,000 18,000 19,000 85,000 Total 159000 169000 179000 189000 199000 859000 Operational Impact /Other I The pavement markings are contracted out each year adding virtually no operational impact. Friday, October 27, 2006 94 Capital Plan City of Andover, MN Project # 07- 43100 -05 Project Name Annual Curb Replacement Type Improvement Useful Life 30 Years Category Streets /Highways 2007 thru 2011 Priority I -High Contact City Engineer Department Streets/ Highways Description Damaged and failing concrete curb and gutter throughout the City needs to be repaired or replaced to help maintain the integrity of the roadway system. Replacing damaged or failing sections of curb and gutter helps with drainage of the roadway and prolongs the life of the street system. Justification The majority of the concrete curb and gutter throughout the City is in relatively good condition. However, there are isolated areas that need rehab ilititation every year. Failing or damaged sections of concrete curb and gutter are removed and replaced. Replacing damaged sections of concrete curb and gutter maintains the integrity of and prolongs the life of the City's street infrastructure. Expenditures 2007 2008 2009 2010 2011 Total Construction 40,000 41,000 42,000 43,000 44,000 210,000 Total 409000 419000 429000 439000 449000 2109000 Funding Sources 2007 2008 2009 2010 2011 Total R & 6 - Reserve 40,000 41,000 42,000 43,000 44,000 210,000 Total 409000 419000 429000 439000 449000 2109000 Operational Impact /Other I Repairing failing or damaged sections of curb and gutter reduces the routine maintenance required by the public works department. Friday, October 27, 2006 95 Capital Plan 2007 rhru 2011 Justification Improvements are planned at the following crossings: 2007 - Andover Blvd ($90,000) & Crosstown Blvd ($90,000) 2007 - Bunker Lake Blvd ($150,000) 2008 - 161 st Avenue ($110,000) Expenditures 2007 2008 2009 2010 2011 Total Construction 330,000 110,000 440,000 Total Funding Sources 3309000 2007 1109000 2008 2009 2010 2011 4409000 Total Equipment Bond Municipal State Aid Funds 180,000 150,000 110,000 180,000 260,000 Total 3309000 1109000 4409000 Operational Impact /Other I Improvements will enhance the quality of life for residents living adjacent to the crossings, resulting in less disruptions from the trains while providing safe crossings for vehicular and pedestrian traffic. Capital Plan City of Andover, MN 2007 thru 2011 Project # 07- 43100 -09 Project Name Municipal State Aid Routes / New & Reconstruct Type Improvement Useful Life 20 Years Category Streets /Highways Description Priority 1 -High Contact City Engineer Department Streets/ Highways V The following projects are proposed to be constructed and /or rehabilitated to meet State Aid Standards. The rehabilitation projects will consist of milling the existing street surface, constructing concrete curb and gutter where it does not exist, and improving storm drainage. 2007: Hanson Blvd (133rd Avenue to 140th Lane) - $1,615,000 2008: South Coon Creek Drive (Round Lake Blvd - Crosstown) $844,200 2010: Nightingale Street (Crosstown Blvd - 161st Ave) $767,000 2011: Prairie Road (Andover Blvd - Crosstown Blvd) $714,000 Justification 2007: Hanson Boulevard (133rd Avenue - 140th Lane) - Upgrade needed to maintain roadway infrastructure and accommodate traffic volumes. Project will be let and constructed by Anoka County. Street lighting will also be installed. 2008: South Coon Creek Drive (Round Lake Blvd - Crosstown) - Upgrade needed to maintain roadway and meet State Aid Standards. Constructed concurrently with trunk water main extension. 2010: Nightingale Street (Crosstown Blvd - 161 st Ave) - Upgrade needed to maintain integrity of State Aid roadway infrastructure. 2011: Prairie Road (Andover Blvd - Crosstown Blvd) - Upgrade needed to maintain integrity of State Aid roadway infrastructure. Expenditures 2007 2008 2009 2010 2011 Total Construction 1,615,000 898,800 767,000 714,000 3,994,800 Total 196159000 8989800 7679000 7149000 399949800 Funding Sources 2007 2008 2009 2010 2011 Total Assessments 633,600 128,400 200,000 71,000 1,033,000 Federal Funds 488,000 488,000 Municipal State Aid Funds 217,000 770,400 567,000 643,000 2,197,400 R & B - Reserve 146,300 146,300 Sewer Trunk Fund 6,500 6,500 Water Trunk Fund 123,600 123,600 Total 196159000 8989800 7679000 7149000 399949800 Operational Imp act /Other Rehabilitating the roads will reduce the amount of routine maintenance along these sections of roadway and provide a safer and higher quality transportation system. Friday, October 27, 2006 T Y o F Capital Improvement Plan ?CNDOVEFAkProject Name: MUNICIPAL STATE AID ROUTES RECONSTRUCT 2007 son Red Oaks East Park WPM B O� " �/ON PKWY L E G E N D Redwood Park J m Z O U Z Q Z 2 a N o J BUNKER LAKE BLVD 0 625 1,250 2,500 Feet M Right of Way Lots /Parcels Water Park City Limits Project Location Redwood Park J m Z O U Z Q Z 2 a N o J BUNKER LAKE BLVD 0 625 1,250 2,500 Feet M C CNDOVEOI T v o r ifE P� JIn9 n %G WE - ■ , 11■ .� 1�1 ■� �■ ■■1 11� ■� ■�■Ni■ ■r��.11■1■�■ 10111111 1111 =m =moves�■ C apital Improvement Plan Project Name: MUNICIPAL STATE AID ROUTES RECONSTRUCT 2008 i ■ COpJy N L E G E N D w Right of Way s Lots /Parcels Water 0 850 1,700 3,400 Park Feet City Limits Project Location F 100 North Oaks Woods C ast Pad 5 T Y o F Capital Improvement Plan NDOVEI;Project Name: MUNICIPAL STATE AID ROUTES RECONSTRUCT 2010 C I T Y O F NDOVER111 LL D. �-T ul ANDOVER BL' C apital Improvement Plan Project Name: MUNICIPAL STATE AID ROUTES RECONSTRUCT 2011 0 w Q Prairie Knoll Park 0 ry w It Q ry n N L E G E N D W E Right of Way Lots /Parcels S Water Park o 850 1,700 3,400 City Limits Feet Project Location 102 Capital Plan City of Andover, MN eject # 07- 43100 -10 2007 thru 2011 Justification Intersection upgrades are necessary due to the increased development and demands on the transportation system, the need for safety improvements, and to comply with Anoka County Highway Department requirements. Operational Impact /Other I Improvements will improve the flow of traffic and will improve the safety of vehicles, pedestrians and bicyclists. Friday, October 27, 2006 103 Expenditures 2007 2008 2009 2010 2011 Total Construction 175,000 175,000 275,000 625,000 Total Funding Sources 1759000 2007 1759000 2008 2759000 2009 2010 6259000 2011 Total Municipal State Aid Funds 175,000 175,000 275,000 625,000 Total 1759000 1759000 2759000 6259000 Operational Impact /Other I Improvements will improve the flow of traffic and will improve the safety of vehicles, pedestrians and bicyclists. Friday, October 27, 2006 103 Capital Plan 2007 rhru 2011 Justification Improve pedestrian and multi -modal access to various destinations within and externally to the city. Expenditures 2007 2008 2009 2010 2011 Total Construction 210,000 210,000 Total 2109000 210,000 Funding Sources 2007 2008 2009 2010 2011 Total Trail Funds 210,000 210,000 Total 2109000 Operational Impact /Other I Additional long -term maintenance and snowplowing will be necessary. 210,000 Friday, October 27, 2006 105 T Y o F Capital Improvement Plan ?CND0VE1Z1AkProject Name: 2007 CROSSTOWN BLVD CONTRUCT BIKEWAY /WALKWAY CORRIDORS NIGHTINGALE U) ESTATES z X1 —r-- �HOLLOW = STATES D. w 0 N'S 0 1 VD ,pity PO N Hall Park Complex #'I � z FATES- T z r M -M 150TH LN C/) c� o � 0 C01 �-i Cf STATES c Sunshiny LL Park rr C- a J a z� HLLUZ 0 cn z PINEWOOD ESTATES IT LL LL�L� OAK SLUFF 47 -1. i - N Location Map LEGEND w og 0 F City Limits s o a Water a a 0 Park o0 0 350 700 1,400 Lots /Parcels Feet a o Right of Way a Project Location 106 7 Capital Plan City of Andover, MN Project # 07- 48100 -01 Project Name Rehabilitation of Wells 2007 thru 2011 Type Improvement Priority 1 -High Useful Life 7 Years Contact PW Superintendent Category Improvements Department Water _ Description The motor, pump and column pipe are taken out for inspection and worn parts are replaced. The well is televised to determine the depth and condition. If the well is at or close to the original drill depth everything is put back in place. The well may need to be cleaned out to the original depth if there is a substantial decrease in the depth. Justification To make sure the well is operational to what it is designed for and to correct any problems that may affect our ability to produce the amount of water needed to meet the demand. A complete inspection and maintenance overhall is performed on each well a minimum of once every seven (7) vears. Expenditures 2007 2008 2009 2010 2011 Total Improvement 45,000 45,000 50,000 50,000 55,000 245,000 Total 459000 459000 509000 509000 559000 2459000 Funding Sources 2007 2008 2009 2010 2011 Total Water Fund 45,000 45,000 50,000 50,000 55,000 245,000 Total 459000 459000 509000 509000 559000 2459000 Operational Impact /Other I This would be done at such a time that it would not affect the demand needs of the system. Typically done late fall. Friday, October 27, 2006 107 Capital Plan 2007 rhYu 2011 Justification I This well has not been used for sometime now. This particular well is 600 feet deep and is pumping a high volumne of sand when it was in operation. The well was designated as an emergency well about four years ago and was not used in this time frame. The formation of this well is very soft and would take a considerable amount of money to try and make it produce the water needed. There is no other aquifer in this area above the existing aquifer. It is also a well that is high in radium which is another reason not to use it. It would be in the best interest of the city to seal it and use the water from the treatment facility to feed this area. Money would be best spent on making the water system one system rather than the two we are currently using. Expenditures 2007 2008 2009 2010 2011 Total Improvement 10,000 10,000 Total 109000 10,000 Funding Sources 2007 2008 2009 2010 2011 Total Water Fund 10,000 10,000 Total 109000 %000 Operational Impact /Other I Money usually used to treat the water at the well head is no longer needed. There would be a power savings also as the well would be pulled and all the controlls would be eliminated from the well house. Friday, October 27, 2006 108 Capital Plan City of Andover, MN Project # 08- 48100 -01 Project Name water Main along South Coon Creek Drive Type Improvement Useful Life 50 Years Category Improvements 2007 thru 2011 Priority I -High Contact City Engineer Department Water Description Install a 12" water main along South Coon Creek Drive from 145th Avenue to Crosstown Boulevard. �: y Justification Construction of a water main along South Coon Creek Drive will allow the existing water distribution system between the east and west sides of town to be looped. The only existing connection between the two parts of town is along Bunker Lake Boulevard. Looping of the system will allow treated water to be continuously supplied to all residents in town on the water system. It will also help alleviate the pressure variance that is experienced between the east and west sides of town. Coon Creek Boulevard is scheduled for reconstruction in 2008. It would be advantageous to construct the water main concurrently with the roadway reconstruction. Expenditures 2007 2008 2009 2010 2011 Total Improvement 795,000 795,000 Total 795,000 795,000 Funding Sources 2007 2008 2009 2010 2011 Total Water Trunk Fund 795,000 795,000 Total 795,000 795,000 Operational Impact /Other I Additional maintenance and flushing requirements for the water main system will result. Construction of this system would make management of the water distribution system for the City as a whole easier by eliminating the two pressure zones. Friday, October 27, 2006 110 T Y O F CDOVE Jq aJ 4 Park I wan N in L E G E N D Right of Way Lots /Parcels Water Park City Limits Project Location C apital Improvement Plan Project Name: WATER MAIN ALONG SOUTH COON CREEK BLVD Greer Acre! 1Park c���CREE/( 1P P PP,- ki,A7 North Woods 0 750 1,500 3,000 Feet 111 North Woods Capital Plan City of Andover, MN eject # 08- 48100 -02 Useful Life 15 -20 Years Category Utilities 2007 thru 2011 Contact PW Superintendent Department Water Justification The tower is going to be in need of painting to maintain its appearance and to protect it from wear and tear. A new City logo should also be put on the tower that show's what the City of Andover is about. Expenditures 2007 2008 2009 2010 2011 Total Improvement 500,000 500,000 Total 500,000 500,000 Funding Sources 2007 2008 2009 2010 2011 Total Capital Equipment Reserve 242,000 242,000 Water Trunk Fund 258,000 258,000 Total Operational Impact /Other I This is a scheduled maintenance that should be budgeted for. 500,000 500,000 Friday, October 27, 2006 112 Capital Plan City of Andover, MN eject # 09- 48100 -01 2007 thru 2011 VI Justification The existing 500,000 gallon water tower will be demolished and replaced by a new two million gallon water tower so the City's water distribution system can be managed under one pressure zone, providing treated water to all residents on the system. Expenditures 2007 2008 2009 2010 2011 Total Improvement 175,000 175,000 Total 175,000 175,000 Funding Sources 2007 2008 2009 2010 2011 Total Water Trunk Fund 175,000 175,000 Total Operational Impact /Other I Maintenance of the existing water tower will no longer be required. 175,000 175,000 Friday, October 27, 2006 113 Capital Plan City of Andover, MN Project # 09- 48100 -02 2007 thru 2011 Justification In order to adequately supply treated water at an acceptable pressure to the entire distribution system in Andover, a two million gallon water tower must be constructed near the water treatment plant. The existing 500,000 water tower in the southwest part of town would be demolished as part of this process. Construction of this tower and demolition of the existing 500,000 gallon tower would eliminate the low pressure zone currently in the southwest part of town. Expenditures 2007 2008 2009 2010 2011 Total Construction 2,950,000 2,950,000 Total 2,950,000 2,950,000 Funding Sources 2007 2008 2009 2010 2011 Total Water Revenue Bonds 2,950,000 2,950,000 Total 2,950,000 Operational Impact /Other I Additional maintenance and monitoring would be required of the Sewer and Water department. 2,950,000 Friday, October 27, 2006 114 Capital Plan City of Andover, MN Project # 10- 48100 -01 Project Name WTP Reclaim Tank Addition Type Improvement Useful Life 30 Years Category Improvements 2007 thru 2011 Priority 1 -High Contact PW Superintendent Department Water Description Add an additional 200,000 gallon reclaim tank and process piping to the water plant. Justification In order to maintain a certain level of operations and meet the demands of the water population, this tank would help in meeting this objective. Staff has noticed that during the high peaking months of May through September the water plant needs to backwash the filters on a daily basis. With the single reclaim tank now in operation the daily operations will run into a difficulty with backwashing filters as there is not enough room to handle the flows required to meet the needs. As the population continues to increase more of a demand is put on the system to function at a high rate of production. With an increase in tank size the operations can continue without much interuption when more room is required for backwashing of the filters. Expenditures 2007 2008 2009 2010 2011 Total Improvement 500,000 500,000 Total 500,000 500,000 Funding Sources 2007 2008 2009 2010 2011 Total Water Trunk Fund 500,000 500,000 Total 500,000 500,000 Operational Impact /Other I With additional storage for backwashing the filtering process would not need to be interupted by shutting down certain wells in order to keep the filters from over loading. With an increase in capacity the water plant filters would be able to operate fully keeping the amount of water filtered at it's highest capacity. Friday, October 27, 2006 115 This page left blank intentionally. 116 City of Andover, MN Capital Plan 2007 thru 2011 DEPARTMENT SUMMARY Department 2007 2008 2009 2010 2011 Total Central Equipment 7,000 35,000 28,000 70,000 Community Center 7,500 7,000 7,000 21,500 Elections 100,000 100,000 Engineering 51,000 51,000 Facility Management 10,000 10,000 Fire 122,000 345,000 400,000 890,000 11757,000 Park & Rec - Operations 59,500 65,500 135,000 74,000 334,000 Planning & Zoning 20,000 20,000 Sanitary Sewer 300,000 300,000 Storm Sewer 80,000 150,000 230,000 Street Signs 8,400 75,000 83,400 Streets / Highways 350,000 395,000 190,000 935,000 GRAND TOTAL 557,400 1,387,500 790,000 1,075,000 102,000 31911,900 117 118 City of Andover, MN Capital Plan 2007 thru 2011 FUNDING SOURCE SUMMARY Source 2007 2008 2009 2010 2011 Total Capital Projects Levy 18,400 100,000 118,400 Central Equipment Fund 7,000 35,000 28,000 70,000 Community Center Operations 7,500 7,000 7,000 21,500 Equipment Bond 531,500 900,500 776,000 890,000 74,000 3,172,000 Sanitary Sewer Fund 300,000 300,000 Storm Sewer Fund 80,000 150,000 230,000 GRAND TOTAL 557,400 1,387,500 790,000 1,075,000 102,000 31911,900 118 City of Andover, MN Capital Plan 2007 thru 2011 PROJECTS &FUNDING SOURCES BY DEPARTMENT Department Project# Priority 2007 2008 2009 2010 2011 Total Central Equipment Replacement - Hotsy Pressure Washer 09- 48800 -02 3 7,000 7,000 Central Equipment Fund 7,000 7,000 Replacement - Floor Sweeper 10- 48800 -01 1 35,000 35,000 Central Equipment Fund 35,000 35,000 Replacement - Service Truck 10- 48800 -02 2 28,000 28,000 Central Equipment Fund 28,000 28,000 Central Equipment Total 79000 359000 289000 70,000 Community Center Walk Behind Floor Scrubber 07- 44000 -01 1 7,500 7,500 Community Center Operations 7,500 7,500 Kitchen Equipment - Fryer /Grill 08- 44000 -01 2 7,000 7,000 Community Center Operations 7,000 7,000 Battery Pack Replacement - Zamboni 09- 44000 -01 2 7,000 7,000 Community Center Operations 7,000 7,000 Community Center Total 79500 79000 79000 21,500 Elections Voting Equipment 08- 41310 -01 1 100,000 100,000 Capital Projects Levy 100,000 100,000 Elections Total 1009000 100,000 Engineering Replacement - Blazer #11 09- 41600 -01 2 30,000 30,000 Equipment Bond 30,000 30,000 Replacement - Total Station 09- 41600 -02 1 21,000 21,000 Equipment Bond 21,000 21,000 Engineering Total 519000 51,000 Facility Management Communication Radios 07- 41900 -03 1 10,000 10,000 Capital Projects Levy 10,000 10,000 Facility Management Total 109000 10,000 Fire Rescue Truck 07- 42200 -01 1 40,000 40,000 119 Department Project# Priority 2007 2008 2009 2010 2011 Total Equipment Bond 40,000 40,000 New Mobile Data Terminals in Fire Trucks 07- 42200 -02 2 30,000 30,000 Equipment Bond 30,000 30,000 Thermal Imaging Camera 07- 42200 -03 1 14,000 14,000 Equipment Bond 14,000 14,000 Replacement - Hydraulic Rescue Equipment 07- 42200 -04 2 30,000 30,000 Equipment Bond 30,000 30,000 Hose Washer /Tester 07- 42200 -05 2 8,000 8,000 Equipment Bond 8,000 8,000 Replacement - Fire Marshall Vehicle 08- 42200 -01 2 30,000 30,000 Equipment Bond 30,000 30,000 Replacement - Fire Tanker #31 08- 42200 -02 1 295,000 295,000 Equipment Bond 295,000 295,000 Water /Ice rescue boat 08- 42200 -03 1 20,000 20,000 Equipment Bond 20,000 20,000 Replacement - Fire Engine #11 09- 42200 -01 1 400,000 400,000 Equipment Bond 400,000 400,000 Replacement - Ladder Truck #11 10- 42200 -01 1 850,000 850,000 Equipment Bond 850,000 850,000 Replacement - Fire Chief's Vehicle 10- 42200 -02 2 40,000 40,000 Equipment Bond 40,000 40,000 Fire Total 1229000 3459000 4009000 8909000 1,757,000 Park & Rec - Operations Replacement - Self- Propelled 48" Sweeper 07- 45000 -02 2 20,000 20,000 Equipment Bond 20,000 20,000 Zero Turn Mower 07- 45000 -03 1 7,500 7,500 Equipment Bond 7,500 7,500 Replacement - Toro Groundsmaster 328 07- 45000 -04 1 32,000 32,000 Equipment Bond 32,000 32,000 Truck - 3/4 Ton Crew Cab 08- 45000 -01 1 35,000 35,000 Equipment Bond 35,000 35,000 Replacement - Mower Trailer 08- 45000 -02 1 8,500 8,500 Equipment Bond 8,500 8,500 Replacement - Toro Groundmaster 08- 45000 -03 1 22,000 22,000 Equipment Bond 22,000 22,000 Replacement - Large Capacity Lawnmower 09- 45000 -01 1 112,000 112,000 Equipment Bond 112,000 112,000 Replacement - Toro Groundsmaster 09- 45000 -02 1 23,000 23,000 Equipment Bond 23,000 23,000 Replacement - Trailer 11- 45000 -01 2 9,000 9,000 Equipment Bond 9,000 9,000 Replacement - One Ton Pick Up w /Plow 11- 45000 -02 2 65,000 65,000 Equipment Bond 65,000 65,000 Park & Rec - Operations Total 599500 659500 1359000 749000 334,000 =!� tng & Zoning Replacement - Ford Taurus #15 08- 41500 -01 2 20,000 20,000 Equipment Bond 20,000 20,000 Planning & Zoning Total 209000 20,000 120 Department Project# Priority 2007 2008 2009 2010 2011 Total Sanitary Sewer New Jet/Vac Truck 08- 48200 -01 1 300,000 300,000 Sanitary Sewer Fund 300,000 300,000 Sanitary Sewer Total 3009000 300,000 Storm Sewer New Track Backhoe 08- 48300 -01 2 80,000 80,000 Storm Sewer Fund 80,000 80,000 Replacement - Elgin Street Sweeper 10- 43100 -01 1 150,000 150,000 Storm Sewer Fund 150,000 150,000 Storm Sewer Total 809000 1509000 230,000 Street Signs Radius Master Machine 07- 43300 -01 1 8,400 8,400 Capital Projects Levy 8,400 8,400 Replacement - Sign Truck #410 08- 43300 -01 2 75,000 75,000 Equipment Bond 75,000 75,000 Street Signs Total 89400 759000 83,400 Streets / Highways Mounted Pothole Spray Patcher 07- 43100 -06 1 150,000 150,000 Equipment Bond 150,000 150,000 Replacement - Dump Truck w/ Snow Removal #195 07- 43100 -07 1 200,000 200,000 Equipment Bond 200,000 200,000 Replacement - Hot Asphalt Box 08- 43100 -02 1 40,000 40,000 Equipment Bond 40,000 40,000 Dump Truck w /Snow Equipment 08- 43100 -04 2 155,000 155,000 Equipment Bond 155,000 155,000 Replacement - Dump Truck w/ Snow Removal #197 08- 43100 -05 1 200,000 200,000 Equipment Bond 200,000 200,000 Replacement - Water Tanker 09- 43100 -01 2 100,000 100,000 Equipment Bond 100,000 100,000 Asphalt Paving Machine 09- 43100 -02 1 90,000 90,000 Equipment Bond 90,000 90,000 Streets / Highways Total 3509000 3959000 1909000 935,000 GRAND TOTAL 5579400 193879500 7909000 190759000 1029000 3,911,900 121 Capital Plan City of Andover, MN Project # 09- 48800 -02 Project Name Replacement - Hotsy Pressure Washer 2007 thru 2011 Type Equipment Priority 3 -Low Useful Life 10 Years Contact PW Superintendent Category Equipment Department Central Equipment Description The existing Hotsy pressure washer is well used and becoming a high maintenance item. It has been working here for almost 15 years. Justification A new one would operate more efficiently, saving time and money by having less break downs. The new one should run on natural gas rather than on kerosene, wouldn't have to run out and buy fuel for it all the time. Expenditures 2007 2008 2009 2010 2011 Total Equipment 7,000 7,000 Total 7,000 7,000 Funding Sources 2007 2008 2009 2010 2011 Total Central Equipment Fund 7,000 7,000 Total 7,000 7,000 Operational Impact /Other I Less break downs, saving time and money. Not having to send people out to buy fuel for it would also save money. Harder to get parts for. Friday, October 27, 2006 122 Capital Plan 2007 rhru 2011 Justification The floors are not cleaned as often as they should be because the current sweeper's washing and vacuum portion is worn out and parts are getting harder to find. The sweeper works well outside because we only use the broom portion of the machine. The present machine works well for the area that we now have but if we double the area, we will need to be able to clean the area faster and do it more efficiently. Expenditures 2007 2008 2009 2010 2011 Total Equipment 35,000 35,000 Total 35,000 35,000 Funding Sources 2007 2008 2009 2010 2011 Total Central Equipment Fund 35,000 35,000 Total Operational Impact /Other I A new machine would have less maintenance issues even with using it more often. 35,000 35,000 Friday, October 27, 2006 123 Capital Plan City of Andover, MN 2007 thru 2011 Project # 10- 48800 -02 Project Name Replacement - Service Truck Type Equipment Priority 2 - Medium Useful Life 10 Years Contact PW Superintendent Category Equipment Department Central Equipment Description Replace Unit #371, a 2001 S10 Ext Cab 4x4 truck with 34,000 miles. This truck averages about 7,000 miles a year and by 2010 it will have approximately 62,000 miles. The new truck should be able to carry 3 or 4 people and also have a tailgate lift. A crew cab truck set up with some of the same options that are on the #371 would be good. Justification To assist mechanics with jobs outside the shop such as parts runs, schooling, vehicle repair and moving equipment around. Many times this vehicle is not big enough to handle the job. A newer truck would be more efficient and help us work more efficiently. The current vehicle would make a good intern or spare vehicle or kept as a runner /drop truck. Expenditures 2007 2008 2009 2010 2011 Total Vehicles 28,000 28,000 Total 289000 289000 Funding Sources 2007 2008 2009 2010 2011 Total Central Equipment Fund 28,000 28,000 Total Operational Impact /Other I A bigger vehicle would increase operating costs - fuel and maintenance. 289000 289000 Friday, October 27, 2006 124 Capital Plan City of Andover, MN Project # 07- 44000 -01 Project Name walk Behind Floor Scrubber 2007 thru 2011 Type Equipment Priority 1 -High Useful Life 5 years Contact Comm Ctr Manager Category Equipment Department Community Center Description A new walk behind floor scrubber for operations at the Community Center. Justification The floor scrubber would be used throughout the Community Center. The field house alone needs to be scrubbed every week, and at 16,000 + square feet a new floor scrubber would help. In addition to the field house, we would use the scrubber in the ice arena locker rooms and hallway, main street, and concessions lobby area. Expenditures 2007 2008 2009 2010 2011 Total Equipment 7,500 7,500 Total 79500 7,500 Funding Sources 2007 2008 2009 2010 2011 Total Community Center Operations 7,500 7,500 Total 79500 7,500 Operational Impact /Other I The floor scrubber would allow us to continue to maintain the facility at a high level. Friday, October 27, 2006 125 Capital Plan City of Andover, MN Project # 08- 44000 -01 Project Name Kitchen Equipment - Fryer /Grill 2007 thru 2011 Type Equipment Priority 2 - Medium Useful Life 15 -20 Years Contact Comm Ctr Manager Category Equipment Department Community Center Description A grill and fryer for expanding the menu at the Community Center concessions. w d� Justification When the concessions was built, the hood and steel wall guards were installed. This would be the next step in finishing off that area. The YMCA would in the end share in the cost to purchase. Expenditures 2007 2008 2009 2010 2011 Total Equipment 7,000 7,000 Total 7,000 7,000 Funding Sources 2007 2008 2009 2010 2011 Total Community Center Operations 7,000 7,000 Total 7,000 7,000 Operational Impact /Other I The additional revenues from the sales of "hot" food items would help pay the equipment off over the years. There would be some additional costs when it comes to hiring a cook to prepare the food. According to the Anoka County Health Department we are already licensed to operate a grill and frver. Friday, October 27, 2006 126 Capital Plan City of Andover, MN Project # 09- 44000 -01 Project Name Battery Pack Replacement - Zamboni Type Equipment Useful Life 7 Years Category Unassigned Description Battery Pack for the Electric Zamboni. 2007 thru 2011 Priority 2 - Medium Contact Department Community Center Justification The battery pack that drives the Zamboni has to be replaced every 5 -7 years. Over time, the batteries will hold less and less of a charge and eventually have to be replaced. Expenditures 2007 2008 2009 2010 2011 Total Vehicles 7,000 7,000 Total 7,000 7,000 Funding Sources 2007 2008 2009 2010 2011 Total Community Center Operations 7,000 7,000 Total 7,000 7,000 Operational Impact /Other I The Zamboni is a necessary part of the operation of the ice arena, and without it we would not be able to keep the facility open. The hope is that with the preventative maintenance program that is in place, we can achieve the maximum amount of time available on the battery pack before it has to be replaced. Friday, October 27, 2006 127 Capital Plan City of Andover, MN Project # 08- 41310 -01 Project Name Voting Equipment Type Equipment Priority 1 -High Useful Life 15 Years Contact City Clerk Category Equipment Department Elections Description �ew electronic voting equipment for 10 precincts. 2007 thru 2011 Justification A Federal mandate to comply with HAVA - Help America Vote Act. The current equipment is non - compliant. z s A� .ems MMI Expenditures 2007 2008 2009 2010 2011 Total Equipment 100,000 100,000 Total 100,000 100,000 Funding Sources 2007 2008 2009 2010 2011 Total Capital Projects Levy 100,000 100,000 Total Operational Impact /Other I Continued storage and maintenance of all the equipment. 100,000 128 100,000 Friday, October 27, 2006 Capital Plan 2007 rhru 2011 Useful Life 10 Years Category Equipment Contact City Engineer Department Engineering Justification This vehicle is an Engineering Tech inspection vehicle and needs to be available for inspections and surveying. Expenditures 2007 2008 2009 2010 2011 Total Equipment 30,000 30,000 Total 30,000 30,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 30,000 30,000 Total Operational Impact /Other I Lower maintenance costs and downtime. 30,000 30,000 Friday, October 27, 2006 129 Capital Plan City of Andover, MN Project # 09- 41600 -02 Project Name Replacement - Total Station 2007 thru 2011 Type Equipment Priority 1 -High Useful Life 10 years Contact City Engineer Category Equipment Department Engineering Description Replace the existing Total Station, which is approximately 8 years old and utilizes outdated software. The Engineering Department utilizes the Total Station to stake construction projects (curb and gutter, sewer, water main, etc) and to complete topographic surveys for design purposes. The Total Station is used almost on a daily basis during the construction season by the Engineering Department. Replacement of the Total Station would be approximately every 10 years upon purchase of a new unit. Justification The hardware and software associated with the Total Station becomes more obsolete every year. It would be beneficial to replace this unit while it still has some trade value towards purchase of a new unit. Expenditures 2007 2008 2009 2010 2011 Total Equipment 21,000 21,000 Total 21,000 21,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 21,000 21,000 Total 21,000 21,000 Operational Impact /Other I Upgrading the unit will allow for increased efficiency by the Engineering Department as new hardware and software technologies are incorporated into the surveying discipline. Friday, October 27, 2006 130 Capital Plan City of Andover, MN Project # 07- 41900 -03 Project Name Communication Radios 2007 thru 2011 Type Equipment Priority 1 -High Useful Life 10 Years Contact PW Superintendent Category Equipment Department Facility Management Description The city has a need for three 800 mhz communication radios to be used in emergency situations between the Civil Defense person, Public Works Superintendent, Fire Chief and the Sheriffs Department. Justification Central Communications changed to the new frequency a few years back and the old system will be discontinued. Expenditures 2007 2008 2009 2010 2011 Total Equipment 10,000 10,000 Total 109000 10,000 Funding Sources 2007 2008 2009 2010 2011 Total Capital Projects Levy 10,000 10,000 Total 109000 10,000 Operational Impact /Other I Without the ability to communicate between departments, we slow down the response time that is so critical when dealing with emergencies. Friday, October 27, 2006 131 Capital Plan 2007 rhru 2011 City of Andover, MN Justification Currently the grass truck at St. #2 is responding to all medical calls but is not equipped to handle all emergencies. Another smaller truck designated and equipped strictly for medical calls would be more efficient and economical, thus preserving the bigger grass rig and extending its useful life. Of the fire department responses, approximately 60% of the calls are now medical related. With the medical gear currently stored on the grass truck, the equipment is always getting wet or damaged by fire type responses. The goal of having one specific vehicle at each station designec for medical responses will help to keep the appropriate equipment in the right locations always available for medical calls. The proposed truck will have a fiberglass body with plenty of storage space so that we will also be able to store and transport hydraulic rescue equipment on the vehicle as needed. The grass trucks will last us longer as they will be used strictly for wildfires and transportation of hose and equipment from fire scenes. The medical gear and equipment will also be less likely to become contaminated by fire and have to be thrown away or cleaned before we have a chance to use it. All three stations have a higher percentage of medical responses and it is important that we have the appropriate vehicles to perform the job. Expenditures 2007 2008 2009 2010 2011 Total Vehicles 40,000 40,000 Total 409000 40,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 40,000 40,000 Total 409000 409000 Operational Impact /Other A smaller truck would be more efficient and economical and would also extend the useful life of the grass rig. By having a designated vehicle for medical responses, the fire department will be able to carry more of the appropriate medical equipment and not have to be concerned about contamination from grass fires or other types of fire incidents that we may respond to. The "medical " vehicles will also be kept in town and not in other cities as thev may be now when called for mutual aid assistance for wildfires. Friday, October 27, 2006 132 Capital Plan City of Andover, MN Project # 07- 42200 -02 Project Name New Mobile Data Terminals in Fire Trucks Type Equipment Useful Life 5 years Category Equipment 2007 thru 2011 Priority 2 - Medium Contact Fire Chief Department Fire Description Installation of mobile data terminals (MDT's) in fire trucks. e e Justification By including MDTs in fire vehicles, firefighters will be able to access important data and information from the Anoka County Communications Center and fire stations. As an example, known hazardous conditions will be identified while responding to the incident. Expenditures 2007 2008 2009 2010 2011 Total Equipment 30,000 30,000 Total 309000 30,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 30,000 30,000 Total 309000 30,000 Operational Impact /Other I The installation of MDTs will improve communications and data capabilities. The opportunity to view important information prior to arriving at the scene will make the firefighters jobs much safer. Friday, October 27, 2006 133 Capital Plan City of Andover, MN 2007 thru 2011 Project # 07- 42200 -03 Project Name � Thermal Imaging Camera T ice.. Type Equipment Priority 1 -High Useful Life 5 years Contact Fire Chief Category Equipment Department Fire Description The thermal imaging camera is new technology that will greatly increase firefighters ability to locate heat sources in a structure. The camera is designed to be used to find human bodies in fire situations where it is near impossible to see because of the smoke and fire encountered during a structure fire. The camera will also be used to find hot spots in walls and /or floors during the extinguishment process. Justification Firefighters will be much more effective in performing search and rescue of victims who could not get out of the structure for some reason. The camera will also be very helpful in identifying internal hot spots that may not be visible. Expenditures 2007 2008 2009 2010 2011 Total Equipment 14,000 14,000 Total 149000 14,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 14,000 14,000 Total 149000 14,000 Operational Impact /Other I The camera will potentially save lives of victims who may not be visible by conventional methods or means. Firefighters can scan a room from one location looking for a victim and move to the next room much faster. Friday, October 27, 2006 134 Capital Plan City of Andover, MN Project # 07- 42200 -04 Project Name Replacement - Hydraulic Rescue Equipment Type Equipment Useful Life 10 years Category Equipment 2007 thru 2011 Priority 2 - Medium Contact Fire Chief Department Fire Description Replace one (and possibly two) hydraulic rescue tools used for extrication and heavy rescue work. Justification The current equipment is approximately 13 years old and is somewhat heavier than the new types of equipment. The new hydraulic tools also have more capacity for pushing, pulling, and cutting activities. Expenditures 2007 2008 2009 2010 2011 Total Equipment 30,000 30,000 Total 309000 30,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 30,000 30,000 Total 309000 30,000 Operational Impact /Other I The hydraulic rescue equipment is necessary to provide the fastest and most efficient means to extricate trapped parties. The lighter weight and stronger tools will make the rescue work much less stressful for the firefighters to perform. Friday, October 27, 2006 135 Capital Plan City of Andover, MN Project # 07- 42200 -05 Project Name Hose Washer /Tester Type Equipment Useful Life 20 Years Category Equipment 2007 thru 2011 Priority 2 - Medium Contact Fire Chief Department Fire Description The hose washer /tester can be used to wash hose as necessary and also to conduct the annual required hose tests. K Justification The hose washer will save time after the incident has ended in that the firefighters will be able to wash hose much faster after each incident. The tester will be use to conduct the annual hose testing where each section of hose is required to be tested to a certain pressure for a certain period of time. The tester will allow the fire department to keep the pumpers in service instead of committing them for the testing process. Expenditures 2007 2008 2009 2010 2011 Total Equipment 8,000 8,000 Total 89000 8,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 8,000 8,000 Total 89000 8,000 Operational Impact /Other I The new washer /tester will aid in making our jobs of getting the trucks back into service much easier after the fire events. The washer can clean hose much faster than firefighters scrubbing hose with a brush or broom. The hose is required to be tested annually, and with the proposed tester at least five sections can be tested at a time instead of doing each section individuallv. Friday, October 27, 2006 136 Capital Plan 2007 rhru 2011 Justification I The Fire Marshal's vehicle is anticipated to have approximately 65,000 miles on it by the year 2008, and the ability to respond to an emergency with a dependable vehicle needs to be considered. There have been more maintenance issues with this vehicle, and although most have been minor, the occurrences are increasing and the costs will also start to increase as the vehicle gets older. Expenditures 2007 2008 2009 2010 2011 Total Vehicles 30,000 30,000 Total 30,000 30,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 30,000 30,000 Total Operational Impact /Other 30,000 30,000 The new vehicle will be used for day to day inspections and also emergency responses when the Fire Marshal is available to assist at the incident including medical calls. It is crucial that the Fire Marshals vehicle be in good operating order to perform all of the functions needed. This vehicle is also used to help conduct all of the fire investigations and the appropriate equipment needs to be stored in the vehicle. The fire department needs to have a very dependable vehicle to perform all of the functions listed. Friday, October 27, 2006 137 Capital Plan City of Andover, MN Project # 08- 42200 -02 Project Name Replacement - Fire Tanker #31 Type Equipment Useful Life 20 Years Category Equipment Priority 1 -High Contact Fire Chief Department Fire 2007 thru 2011 Description Replace fire tanker #31, a 1991 International / Alexis tanker with 7,700 miles. Justification This vehicle will be seventeen years old in 2008 and will most certainly need a major refurbishment or replacement. It would be recommended to replace and sell the existing vehicle as is so that our fire department will benefit from new vehicle technology that should last us for the next twenty years. The maintenance costs are starting to increase and the body work needed should be evaluated. The new tanker will have high technology flow meters, automated pump controls, a more efficient engine that creates less pollution in the station and on the road. Expenditures 2007 2008 2009 2010 2011 Total Equipment 295,000 295,000 Total 295,000 295,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 295,000 295,000 Total Operational Impact /Other 295,000 295,000 The new technology will allow firefighters to perform their jobs in a more efficient and safe manner. The newer technology will allow for just one operator to staff the vehicle for water shuttles to and from the fire scenes. Currently, we need at least two firefighters to operate the tanker properly. The newer controls and gauges will also help to make the vehicle much easier to pump and dump water as needed. Other items that will be improved include; electronic dump chutes for water control, inside cab controls for operator ease, larger pump that can be I.S.O. certified, better emergency lighting for responding to the scene, more storage room, roll up doors for safer access on the scene, pre plumbed suppressant foam supply, electronic /hydraulic dump tank lowering device, and the room needed for a second portable tank. Friday, October 27, 2006 138 Capital Plan 2007 rhru 2011 Justification Andover does not currently have a rescue boat. The boat would be used to perform ice and water rescues. The boat will make these specific types of rescues safer for all responders. The boat will allow firefighters to perform rescue work rather than waiting for a boat to arrive and perform recovery work. Expenditures 2007 2008 2009 2010 2011 Total Equipment 20,000 20,000 Total 20,000 20,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 20,000 20,000 Total 20,000 20,000 Operational Impact /Other Boat will make an easier and safer rescue for all responders and parties being rescued. The boat will save lives and make it safer for firefighters who have to enter the water or crawl on the ice. The current method of having firefighters wear wet suits and try to swim or crawl on the ice to the victim is not very safe or recommended if we can avoid it. The boat will hela aet the rescuer and victim out of the situation faster and safer. Friday, October 27, 2006 139 Capital Plan City of Andover, MN eject # 09- 42200 -01 2007 thru 2011 Justification Engine # I 1 and three other major pieces of equipment are scheduled to be replaced in the next few years. The current engine is working fine but is starting to have more day to day repairs. As with any vehicle that is 16 years old, some parts can be harder to find and take longer to receive for needed repairs. The fire department can not afford to have vehicles down for extended periods of time. Expenditures 2007 2008 2009 2010 2011 Total Vehicles 400,000 400,000 Total 400,000 400,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 400,000 400,000 Total Operational Impact /Other 400,000 400,000 The new technology will allow firefighters to respond and conduct fire suppression activities, rescue operations, and other required activities in a safer and more efficient manner. The maintenance costs can be lowered as well. Some of the new technology items include increasing the capability to transport more firefighters to the scene, internal plumbed foam suppressant system, climate controlled cab can be used for firefighter rehabilitation, much better visibility when driving to emergencies, better maneuverability, and new designs make it much easier to enter and exit the cab area. In addition the new emergency lighting standards will make it easier to see the truck while responding and also while parked at the scene. Friday, October 27, 2006 140 Capital Plan City of Andover, MN Project # 10- 42200 -01 Project Name Replacement -Ladder Truck #11 Type Equipment Useful Life 20 Years Category Equipment Priority 1 -High Contact Fire Chief Department Fire 2007 thru 2011 I�• e F4L rim - Description Replace ladder truck # 11, a 1991 Pierce 75' ladder truck with 15,800 miles. The new ladder truck would be a 100 foot aerial platform, which includes a bucket at the end of the ladder for firefighter safety. The 100 foot reach will allow for the fire department to perform rescue and suppression activities in buildings that we can not currently reach. Justification The city is required by the I.S.O. to have this type of vehicle available for use because of the building heights allowed in Andover. The new platform style truck versus the current straight ladder will be much safer for firefighter activities and fire suppression activities. It should be noted that the newest aerial truck equipment and technologies are better than what we are now using. The new vehicles have safety sensors and weight distribution gauges that will keep the operators from making mistakes while operating the truck that could be very costly or dangerous. The newer buildings in Andover are getting taller with more green space between the building and a hard surface making it much more difficult to reach some of them because of the height restrictions of the current ladder truck. Expenditures 2007 2008 2009 2010 2011 Total Equipment 850,000 850,000 Total 850,000 850,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 850,000 850,000 Total 8509000 8509000 Operational Impact /Other The use of an aerial device can be very dangerous if not performed properly. A new platform truck will allow firefighters to perform the most dangerous of activities as required from time to time, and know that they have the right piece of equipment to do the job. The larger and taller buildings now being built in Andover will require this type of equipment. The current ladder truck has been fairly dependable with not many major repairs needed. The maintenance costs are going up for this vehicle and the trade in value may be going down as the truck gets older. The new bucket style of truck will also much safer conditions for firefighters performing suppression activities. The new ladder truck can be equipped to have pre - plumbed breathing air in the bucket for extended use and also high intensity lighting mounted on the bucket will greatly increase site visibility. Firefighters will no longer have to carry heavy equipment up the ladder but rather can swing the bucket down to the ground to pick it up. The larger cab design will allow for transporting more firefighters and also can be used for rehabilitation of staff when needed. The bucket design will also allow for two master stream devices mounted near the top of the bucket to be used for extinguishment for very large types of fires. The over head visibility at the scene will also help the incident commander make vital decisions re2ardin2 the tactics and strategies to be used. Friday, October 27, 2006 141 Capital Plan City of Andover, MN Project # 10- 42200 -02 Project Name Replacement - Fire Chiefs Vehicle Type Equipment Useful Life 10 Years Category Equipment 2007 thru 2011 Priority 2 - Medium Contact Fire Chief Department Fire Description Replacement of Fire Chief s vehicle, a 2002 Tahoe with approximately 34,000. Justification In order to keep the first line emergency responding vehicles in the proper operating conditions, it is important to replace equipment when needed. The current vehicle has worked very well and should be evaluated for repair history and maintenance costs as the replacement date gets closer. Expenditures 2007 2008 2009 2010 2011 Total Equipment 40,000 40,000 Total 40,000 40,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 40,000 40,000 Total Operational Impact /Other 40,000 40,000 The Chief s vehicle is used by the Chief to respond to emergency incidents. The vehicle has to be in good shape and able to provide safe and protective transportation when responding to all types of incidents. The vehicle also carries all of the Chief s protective gear and equipment needed to help conduct fire investigations. The Chief regularly uses the vehicle to conduct interviews while on the scene with property owners and also uses the truck to provide a place for fire victims to sit out of the elements while they are waiting for relatives or the Red Cross to respond to the scene. Friday, October 27, 2006 142 Capital Plan 2007 rhru 2011 Justification The current machine has a lot of hours on it and is costing us more each year to repair and maintain as a front line unit. Expenditures 2007 2008 2009 2010 2011 Total Equipment 20,000 20,000 Total 209000 20,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 20,000 20,000 Total 209000 Operational Impact /Other I A more cost efficient machine with less breakdowns. 20,000 Friday, October 27, 2006 143 Capital Plan City of Andover, MN 2007 thru 2011 Project # 07- 45000 -03 - .�� ;.s F.: ;. Project Name Zero Turn Mower Type Equipment Priority 1 -High Useful Life 10 Years Contact PW Superintendent Category Equipment Department Park & Rec - Operations �i 41 - - Description A zero turn mower to be used by the Parks Department for mowing operations at the Community Center, City Hall and Public Works facilities. Justification This mower is smaller than the normal six foot mowers and has a zero turn operation allowing it to trim and turn in smaller areas. Expenditures 2007 2008 2009 2010 2011 Total Equipment 7,500 7,500 Total 79500 7,500 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 7,500 7,500 Total 79500 7,500 Operational Impact /Other I This machine can be used in more isolated areas and eliminate trimming with a hand mower and less clean up. Saving time, personnel and money. Friday, October 27, 2006 144 Capital Plan City of Andover, MN Project # 07- 45000 -04 Project Name Replacement - Toro Groundsmaster 328 2007 thru 2011 Type Equipment Priority 1 -High Useful Life 10 Years Contact PW Superintendent Category Equipment Department Park & Rec - Operations Description Replace Unit #560, a 1992 Toro Groundmaster 328 with cab, a 72" discharge deck and snow blower and has approximately 1,600 hours. The Parks Department would like to replace it with a 4 -wheel drive model, which is helpful in moving snow and mowing on hilly and wet terrain. The current machine would replace one of the older units in another department. Justification This unit is used year round and maintenance costs are rising. The cost to operate this unit increased $.58 per hour this last year. This unit used around the Community Center, City Hall and Public Works facilities. Expenditures 2007 2008 2009 2010 2011 Total Equipment 32,000 32,000 Total 329000 32,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 32,000 32,000 Total 329000 32,000 Operational Impact /Other I An additional unit with a cab will help during winter operations. The 4 -wheel drive unit will be more efficient with its time rather than spinning its tires and getting stuck. Friday, October 27, 2006 145 Capital Plan City of Andover, MN Project # 08- 45000 -01 Project Name Truck- 3/4 Ton Crew Cab 2007 thru 2011 Type Equipment Priority 1 -High Useful Life 10 Years Contact PW Superintendent Category Equipment Department Park & Rec - Operations Description Large pick up truck to haul mowers, equipment and personnel to job sites around the city. It would be similar to Unit 502 which has worked great. This would be an addition to the fleet. Justification To haul more equipment and personnel to various job sites saving time. Expenditures 2007 2008 2009 2010 2011 Total Vehicles 35,000 35,000 Total 35,000 35,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 35,000 35,000 Total 35,000 35,000 Operational Impact /Other I Save time and money by hauling a number of people out to the job site in one vehicle rather than two or more. A second rig would be extremly helpful during the spring, summer and fall months when all of the part -time help is here. Friday, October 27, 2006 146 Capital Plan 2007 rhru 2011 Justification This trailer has already been sandblasted and painted once before because of rust and is now starting to show its age. In addition, this trailer has higher siderails making it diffucult to load and unload equipment. Expenditures 2007 2008 2009 2010 2011 Total Equipment 8,500 8,500 Total 8,500 8,500 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 8,500 8,500 Total 8,500 Operational Impact /Other I Save time and money in hauling equipment around the city on a proven multi use trailer. 8,500 Friday, October 27, 2006 147 Capital Plan City of Andover, MN Project # 08- 45000 -03 Project Name Replacement - Toro Groundmaster 2007 thru 2011 Type Equipment Priority 1 -High Useful Life 10 Years Contact PW Superintendent Category Equipment Department Park & Rec - Operations Description Replace Unit #550, a 1998 Toro Groundmaster mower with 2,700 hours. Justification The maintenance cost are substantially higher than any of the other mowers. This machine is spending more and more time in the shop being repaired rather than mowing and being productive. Expenditures 2007 2008 2009 2010 2011 Total Equipment 22,000 22,000 Total 22,000 22,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 22,000 22,000 Total Operational Impact /Other I More time being productive, saving time and money. 22,000 148 22,000 Friday, October 27, 2006 Capital Plan 2007 rhru 2011 Justification Maintenance costs are starting to accumulate and it should be traded in while it still has some value. Maintenance costs rose $1.37 per hour over the previous year. Expenditures 2007 2008 2009 2010 2011 Total Equipment 112,000 112,000 Total 112,000 112,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 112,000 112,000 Total Operational Impact /Other I Higher maintenance cost, possibly more break downs and lower trade -in value. 112,000 112,000 Friday, October 27, 2006 149 Capital Plan City of Andover, MN Project # 09- 45000 -02 Project Name Replacement - Toro Groundsmaster 2007 thru 2011 Type Equipment Priority 1 -High Useful Life 10 Years Contact PW Superintendent Category Equipment Department Park & Rec - Operations Description Replace Unit #559, a 1999 Toro Groundsmaster 328 with 1,600 hours. Justification These units are run year round and average about 300 hours a year!! With the additional parks that are added each year, the average hour that each machine puts on will increase. Expenditures 2007 2008 2009 2010 2011 Total Equipment 23,000 23,000 Total 23,000 23,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 23,000 23,000 Total 23,000 Operational Impact /Other I Possibility of more costly breakdowns in the future along with higher everyday maintenance issues. 150 23,000 Friday, October 27, 2006 Capital Plan 2007 rhru 2011 Justification This is the main trailer for the Parks Department. It was the first and only trailer that was designed for hauling mowers and it has worked out great. We would like to purchase another one just like it. Expenditures 2007 2008 2009 2010 2011 Total Equipment 93000 9,000 Total 99000 99000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 9,000 93000 Total Operational Impact /Other I More parks can only mean moving more equipment to them. 99000 99000 Friday, October 27, 2006 151 Capital Plan City of Andover, MN Project # 11- 45000 -02 Project Name Replacement - One Ton Pick Up w/Plow 2007 thru 2011 Type Equipment Priority 2 - Medium Useful Life 10 Years Contact PW Superintendent Category Equipment Department Park & Rec - Operations Description Replace Unit # 599, a 2000 F450 1 -ton with 37,000 miles. These trucks are on the move all year and average about 6,000 miles per year. Justification This truck is used everyday; hauling material, equipment, people and also plowing snow in the winter. The plowing of snow puts a lot of wear and tear on the engine, transmission and other drive line components. Expenditures 2007 2008 2009 2010 2011 Total Vehicles 65,000 65,000 Total 659000 659000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 65,000 65,000 Total 659000 659000 Operational Impact /Other I Being that this is a front line unit, we need to know that we can count on it everyday. Cost to operate it have only gone up $.22 per mile last year put those costs will continue to rise in the coming years. With preventative maintenance, we might be able to extend its useful life. Friday, October 27, 2006 152 Capital Plan 2007 rhru 2011 Justification By year 2008, this vehicle will have 75,000 miles on it. This vehicle could be used as an intern vehicle or for city employees attending seminars /training. Expenditures 2007 2008 2009 2010 2011 Total Equipment 20,000 20,000 Total 20,000 20,000 Funding Sources 2007 2008 2009 2010 2011 Total Equipment Bond 20,000 20,000 Total 20,000 20,000 Operational Impact /Other I Will decrease maintenance costs and improve productivity. This car could be kept and used for interns and possibly replace an older unit. Friday, October 27, 2006 153 Capital Plan City of Andover, MN Project # 08- 48200 -01 Project Name New JetNac Truck 2007 thru 2011 Type Equipment Priority 1 -High Useful Life 15 -20 Years Contact PW Superintendent Category Equipment Department Sanitary Sewer Description This is a combination jet /vac unit, Model 2115 Positive Displacement Unit (PD Unit) used for cleaning sanitary and storm sewers. This unit will carry up to 2000 gallons of water and 600 feet of jetting hose. Justification Approximately 13 miles or 15% of the sanitary sewer system is trunk mains with diameters of 12" - 36 ". These trunk mains are flowing near capacity in some areas at the present time. By removing the sedimentation in these pipes the flow line will drop giving more room for additional flows. In turn this could put on hold the addition of the designated lift station to by pass certain areas for a year or more. Without the addition of this new PD Unit, the trunk lines could still be cleaned by blocking the flow in the main which will cause a backup in the system until the pipes are cleaned. This would be done in sections at a time to try and avoid a maj or backup into basements. This is not the best way to do the maintenance but would work with some risk. This type of unit can also clean flared end sections in back yards and sedimentation ponds within a reasonable distance. This would allow some areas to be cleaned without having to enter properties with equipment that will do some type of damage to yards saving money in yard restoration. Expenditures 2007 2008 2009 2010 2011 Total Equipment 300,000 300,000 Total 300,000 300,000 Funding Sources 2007 2008 2009 2010 2011 Total Sanitary Sewer Fund 300,000 300,000 Total 3009000 3009000 OperationalImpact/Other I This truck will help save time with cleaning of the system. It will also allow the system to be cleaned under heavy flows which cannot be done with the machine currently being used. This type of VAC truck will allow the operators to clean more of the system without having to stop because the truck cannot handle the flows. It would save time by not having to plug mains and risk backups into basements because of some unforeseen difficulty. The older machine would be used in the storm sewer department which would enable the maintenance department to clean both sanitary and storm sewers at the same time which will help satisfy some of the rciuirements for the NPDES. Friday, October 27, 2006 154 Capital Plan City of Andover, MN Project # 08- 48300 -01 Project Name New Track Backhoe 2007 thru 2011 Type Equipment Priority 2 - Medium Useful Life 15 -20 Years Contact PW Superintendent Category Equipment Department Storm Sewer Description �ew larger backhoe to be used to clean out ditches and storm ponds. Justification Present equipment is not large enough and cannot reach far enough for cleaning out storm water ponds and ditches. Expenditures 2007 2008 2009 2010 2011 Total Equipment 80,000 80,000 Total 80,000 80,000 Funding Sources 2007 2008 2009 2010 2011 Total Storm Sewer Fund 80,000 80,000 Total 80,000 80,000 Operational Impact /Other This new machine will allow the department to clean areas that require a larger unit. The machine presently being used is to small and cannot get to some areas of the system. More of the system could be cleaned without hiring a contractor. This could also be used in other departments such as for water main repairs, park projects, etc. Friday, October 27, 2006 155