HomeMy WebLinkAboutOctober 20, 20221685 CROSSTOWN BOULEVARD N.W. • ANDOVER, MINNESOTA 55304 • (763) 755-5100
FAX (763) 755-8923 • WWW.ANDOVERMN.GOV
Regular Park & Recreation Commission Meeting
October 20, 2022
6:00 P.M. Meet at Andover City Hall
1. Call to Order
2. Resident Forum
3. Approval of Minutes (08-04-22) (08-18-22)
4. Agenda Approval
5. Community Center 3rd Quarter Report/Administration
6. Park Dedication Improvement Fund 3rd Quarterly Report/Finance
Department
7. Sheriff's Report 3rd Quarter
8. Preliminary Plat Review Legacy at Peterson Farms
9. Outstanding Items
10.Other Items or Updates
11. Chairs Report
12.Adjournment
7:00 P.M. or Shortly After Workshop Session
A. Discuss Park Related Fees
1685 CROSSTOWN BOULEVARD N.W. • ANDOVER, MINNESOTA 55304 • (763) 755-5100
FAX (763) 755-8923 • WWW.ANDOVERMN.GOV
TO: Parks & Recreation Commission
ROM: Jim Dickinson, City Administrato
SUBJECT: September 2022 Andover Community Ce Update
-5
DATE: October 20, 2022
INTRODUCTION:
Attached for Commission review is the Andover Community Center (ACC) Budget Summary
Report for Budget Year 2022. The reports reflect activity through September 2022, comparative
data with September 2021 and the entire year of 2021.
September 2022 Financials
Coming off 2020 imposed COVID restrictions shutting down the entire facility mid -March of
2020, the facility was allowed to reopen in a restricted capacity early January 2021. The ACC
operated at near full capacity for close to twelve months in 2021 making current year (2022)
activities comparable to the previous year.
2022 Revenues are just slightly ahead in comparison to 2021, this is due to assorted reasons
attributed to turf usage vs ice, fieldhouse usage, vending machine use and payment timing. Ice
Rental to date is less in 2022 versus 2021 primarily due to the Sports Complex ice was not
converted to turf in 2021. The 2022 expenses are ahead of 2021 primarily in salaries and operating
costs. 2022 Full capacity reflects additional utility costs and hiring challenges which required the
use of more full-time staffing overtime hours rather than the use of part-time staffing for the first
three month of 2022. In addition, 2022 has a Capital Outlay line item where 2021 did not.
Also provided is an ACC historical perspective of actual costs dating back to 2015. This is the
reporting previously provided to the ACC Advisory Commission. This report also provides history
on debt service payments and the property tax levy assigned to debt and operations.
Aueust/September 2022 FACILITY UPDATE:
Please refer to the attached ACC Facility Update for Major Events and monthly Walking Track
activity through September. Major events are picking up as the sports seasons transition from
summer camps to the fall seasons.
PROGRAMS/ACTIVITIES-
ACC staff has been busy as we switch gears into the busy fall/winter season, but over the
summer ACC hosted several large weekend events on the main rink and the Sports Complex.
ACC had three separate Jr Hockey tryout camps and two youth hockey tournaments.
The fieldhouse hosted a week-long MN Timberwolves camp Aug 15-18 on all four courts. Fun
Fest was held early July and ACC hosted the Andover Fire Open House on Sept 17th.
The ACC has been selected to host the U.S. Hockey Hall of Fame Museum Women's Face -Off
Classic on November 7, 2022 (University of Minnesota vs. St. Cloud State University). ACC
staff are spending a lot of time preparing to help display the ACC and provide for a wonderful
experience for the teams and spectators.
ACC staff are also spending time preparing the MN Hockey Tier One Girls Invitational on Oct
21-23. Eight teams from MN along with another sixteen teams from all over the US, including
Boston, Chicago, Detroit, Philadelphia, Wisconsin, Arizona, North Dakota, California, etc.
Pickleball has been slow to return with the warm/dry weather we have had recently but we are
sure to see them once that changes. ACC has been offering pickleball lessons and skills and drills
sessions since September.
Fall ACC programs are very strong. Skating Lessons and Indoor Soccer both have well over one
hundred participants each.
High School Hockey will start up in early November with the first games later in the month.
Mn Premier Volleyball will start up in November as will Andover Athletic Association Girls
Basketball.
Election Day is hosted at the ACC for two precincts on November 8th.
CONCESSIONS -
After a Request for Proposal (RFP) process in March — May, the Council approved Crooked Lake
Concessions as our selected vendor and a lease was approved at the May 17th Council meeting.
Crooked Lake Concessions ordered and installed materials for the space.
Concessions opened mid -September and has been well received. ACC shares event schedules
monthly to help coordinate staffing and inventory needs.
Concessions is ready for the busy season.
STAFFING -
The ACC is at full complement of approved fulltime staffing.
All around, ACC staffing is currently in decent shape. ACC continues to look for additional part-
time staffing as we enter the 2022 -2023 busy season.
SCHEDULING -
Scheduling for the 2022-23 busy season is complete. ACC is in continual contact with all our user
groups to better understand how we can better address their needs. ACC also continues to look to
fill off season times and fine tune our spring turf season. Also, ACC is in the process of migrating
to new scheduling software.
ACTION REQUESTED
Informational. Commission is requested to review the staff report and attached reports.
Attachments
CITY OF ANDOVER
Community Center Budget Summary Totals
Budget Year 2022
2021 2022
REVENUES Budget Sep YTD % Bud Audit Budget Sep YTD % Bud
Charges for services
Ice Rental
$ 668,000
$ 500,885
75%
$ 823,856
$ 729,000
$ 445,400
61%
Turf Rental
70,000
3,782
n/a
3,782
50,000
18,553
37%
Track
-
2,492
n/a
3,950
2,500
3,580
n/a
Fieldhouse Rental
270,000
156,819
58%
220,527
240,000
212,308
88%
Proshop
15,000
4,970
33%
9,606
13,000
7,724
59%
Vending
16,000
4,552
28%
7,763
15,000
15,305
102%
Advertising
50,000
74,113
148%
84,700
63,000
82,248
131%
Total Charges for services
1,089,000
747,613
69%
1,154,184
1,112,500
785,118
71%
Miscellaneous
140,000
72,634
52%
134,072
182,000
149,127
82%
Total revenues
1,229,000
820,247
67%
1,288,256
1,294,500
934,245
72%
2021
2022
EXPENDITURES
Budget
Sep YTD
% Bud
Audit
Budget
Sep YTD
% Bud
Current:
Salaries & benefits
757,753
445,838
59%
692,742
770,110
585,276
76%
Departmental
105,100
52,271
50%
82,655
97,100
66,972
69%
Operating
635,197
316,878
50%
515,308
603,233
374,098
62%
Professional services
154,375
43,892
28%
85,130
248,525
119,169
48%
Capital outlay
-
-
n/a
-
42,000
37,358
89%
( iment 1,652,425 858,879 52% 1,375,835 1,760,968 1,182,873 67%
Revenue over(under)expense (423,425) (38,632) 9% (87,579) (466,468) (248,628) 53%
Other financing sources (uses)
General Property Tax Levy
155,000
81,219
52%
154,534
155,000
81,815
53%
Investment income
-
118
n/a
2,817
-
213
n/a
Rental / Lease Pymt
638,000
634,375
99%
635,026
638,000
635,415
100%
Transfers out
(300,000)
(300,000)
100%
(300,000)
(300,000)
(300,000)
100%
Total financing sources (uses)
493,000
415,712
84%
492,377
493,000
417,443
85%
let increase (decrease) in
fund balance $ 69,575 $ 377,080 542% $ 404,798 $ 26,532 $ 168,815 6369
CITY OF ANDOVER, MINNESOTA
Andover Community Center / YMCA Historical Comparison
2015
2016
2017
2018
2019
2020
2021
2022
2022
Actual
Actual
Actual
Actual
Actual
Actual
Actual
Budget
Sep - YTD
Revenues:
Charges for services
Ice Rental
$ 400,619
$ 405,990
$
392,828
$ 435,716
$ 442,995
$ 361,796
$
823,856
$ 729,000
$ 445,400
Turf Rental
-
-
-
-
-
-
3,782
50,000
18,553
Track
-
-
-
-
-
301
3,950
2,500
3,580
Fieldhouse Rental
187,007
199,286
215,089
218,667
220,225
133,126
220,527
240,000
212,308
Proshop
9,258
9,412
9,247
8,606
9,680
4,394
9,606
13,000
7,724
Vending
9,279
8,588
9,182
7,470
8,427
6,148
7,763
15,000
15,305
Advertising
31,758
26,450
38,819
34,000
40,850
8,000
84,700
63,000
82,248
Charges for services
637,921
649,726
665,165
704,459
722,177
513,765
1,154,184
1,112,500
785,118
Miscellaneous
174,788
136,552
136,149
142,768
131,386
110,781
134,072
182,000
149,127
Total revenues
812,709
786,278
801,314
847,227
853,563
624,546
1,288,256
1,294,500
934,245
Expenditures:
Current:
Salaries & benefits
439,304
451,332
481,926
501,108
533,044
503,842
692,742
770,110
585,276
Departmental
74,949
77,945
65,612
76,448
66,570
74,809
82,655
97,100
66,972
Operating
388,492
364,935
364,242
352,067
330,084
345,588
515,308
603,233
374,098
Professional services
142,602
106,381
125,034
104,076
77,818
129,261
85,130
248,525
119,169
Capital outlay
47,859
4,900
11,442
39,888
100,000
42,000
37,358
Current
1,045,347
1,048,452
1,041,714
1,045,141
1,047,404
1,153,500
1,375,835
1,760,968
1,182,873
Revenue over under expenditures
(232,638)
(262,174)
(240,400)
(197,914)
(193,841)
(528,954)
(87,579)1
(466,468)1
(248,6287)
Other financing sources (uses)
General Property Tax Levy
-
-
-
-
-
154,534
155,000
81,815
Investment income
(1,078)
2,190
2,779
5,780
16,107
6,793
2,817
-
213
Rental / Lease Pymt
638,220
640,303
641,691
637,150
636,803
635,629
635,026
638,000
635,415
Transfers out
(300,000)
(300,000)
(300,000)
(300,000)
(300,000)
(300,000)
(300,000)
(300,000)
(300,000)
Total financing sources (uses)
337,142
342,493
344,470
342,930
352,910
342,422
492,377
493,000
417,443
Net increase (decrease) in fund balance
104,504
80,319
104,070
145,016
159,069
(186,532)
404,798
26,532
168,815
Fund balance (deficit) - January 1
(48,364)
56,140
136,459
240,529
385,545
544,614
358,082
762,880
762,880
Fund balance (deficit) - December 31
$ 56,140
$ 136,459
$
240,529
$ 385,545
$ 544,614
$ 358,082
$
762,880
$ 789,412
$ 931,695
Fund Balance Detail:
FB - Replac Res for Common Space
$ 143,702
$ 154,449
$
179,283
$ 173,560
$ 200,606
$ 190,067
$
216,790
$ 241,790
$ 241,790
FB-Unassigned
(87,562)
(17,990)
61,246
211,985
344,008
168,015
546,090
547,622
689,905
$ 56,140
$ 136,459
$
240,529
$ 385,545
$ 544,614
$ 358,082
$
762,880
$ 789,412
$ 931,695
Debt Service Payments
2012C GO Abatement Bonds (P +1)
$
1,214,906
$
1,216,506
$ 1,213,731
$
1,211,481
$
1,208,931
$
1,215,981
$ 1,212,631
$ 1,213,931
$ 1,213,931
2019A GO Abatement Bonds (P + 1)
590,150
819,725
1,109,755
1,109,755
$
1,214,906
$
1,216, 006
$ 1,213,731
$
1,211,481
$
1,2 88,931
$
1,806,131
$ 2,032,356
$ 2,323,686
$ 2,323,686
Property Tax Levy
2012C GO Abatement Bonds
$
975,632
$
977,332
$ 974,418
$
972,055
$
969,378
$
976,780
$ 973,263
$ 974,628
$ 974,628
2019A GO Abatement Bonds
-
-
-
-
-
1,001,090
976,966
1,014,065
1,014,065
Community Center Operations
155,000
155,000
155,000
$
975,632
$
977,332
$ 974,418
$
972,055
$
969,378
$
1,977,870
$ 2,105,229
$ 2,143,693
$ 2,143,693
A N D%VER
COMMUNITY CENTER
FACILITY UPDATE
OCT-NOV 2022
OCT 8 - INDOOR SOCCER PROGRAM BEGINS
OCT 20 - 21 - NO SCHOOL DAYS
OCT 20 - MN TIMBERWOLVES CAMP
OCT 21-23 - MN HOCKEY NIT GIRLS TOURNAMENT
OCT 31 -AHS GIRLS HOCKEY SEASON BEGINS
NOV 5 -AAA GIRLS BASKETBALL
NOV 7 - US HOCKEY HALL OF FAME GAME -GOPHERS VS HUSKIES
NOV 8 - ELECTIONS
NOV 12 - AHS GIRLS HOCKEY VS. EDINA
NOV 13 - MN PREMIERE VOLLEYBALL TRYOUTS
NOV 14 - AHS BOYS HOCKEY SEASON BEGINS
NOV 19 - AHS GIRLS VS. GENTRY ACADEMY
NOV 24 -ACC CLOSED
NOV 28 - MN PREMIERE VOLLEYBALL SEASON STARTS
TRACK CHECK IN IS REQUIRED, MONDAY-FRIDAY, 6 30AM-4 30PM.
NUMBERS BELOW REFLECT THOSE CHECKED IN DURING THESE TIMES.
JAN -184
6
FEB -1960
MARCH
- 2054
APRIL -
1931
MAY-795
JUNE-454
JULY -
405
AUGUST-
389
SEPT-
5nn
FALL LEARN TO SKATE - SEPT. 18 - 7 WEEKS (103 KIDS)
FALL IN DOOR SOCCER - OCT 8 - 6 WEEKS
BEGINNER PICKLEBALL LESSONS -OCT & NOV
,vim• •' ., 1DI
1685 CROSSTOWN BOULEVARD N.W. • ANDOVER, MINNESOTA 55304 • (763) 755-5100
FAX (763) 755-8923 • WWW.ANDOVERMN.GOV
TO: Park & Recreation Commission
CC: Jason Baumunk, Streets / Parks Manager
6 FROM: Lee Brezinka, Finance Manager
SUBJECT: 2022 Third Quarter Financial Report
DATE: October 20, 2022
INTRODUCTION
Quarterly review of the Park Improvement Fund.
DISCUSSION
Attached are the Project Commitment Listing Report, Balance Sheet, and Revenue and
Expenditure Reports for the Park Improvement Fund as of September 30, 2022.
ACTION REQUESTED
Informational data provided and no formal action is needed.
Respectfully submitted,
City of Andover
Y-'el�e
�;r�
Lee Brezinka
Attachments: Park Improvement Fund - Project Commitment Listing
Park Improvement Fund - Balance Sheet
Park Improvement Fund - Revenues
Park Improvement Fund - Expenditures
CITY OF ANDOVER
Park Improvement Fund
Project Commitment Listing
September 30, 2022
Actual
Fund Balance $ 2,032,487.55
Collected
Additional Revenues Anticipated Budget To Date
Anticipated Park Dedication Fee - Residential $ 220,000 $ 1,347,276.00
Anticipated Park Dedication Fee - Commercial - -
Donation / Grant - _
Capital Projects Levy for Park Improvements 15,000 7,791.89
Rose Park Tower Rental 10,094.81
Interest (320.00)
235,000 1,364,842.70
Total Funds Available 2,032,487.55
Projected Commitments
Rose Park Tower Rental balance
Pine Hills North & South - Parking Lot
Oak Bluff - Basketball Court
Annual Miscellaneous Projects
Operating Transfer Out
Carryforwards/
Budget
Adjustments
64,768.75
187,000
4,245.50
10,000
-
25,000
163.143
$ 385,143
Total Dollars Allocated for Park Projects
Park Improvement Funds Available For Future Projects:
2022
Actual
54,824.44
132,986.10
92.25
163,143.00
69,014.25 351,045.79
Reserved
Amount
9,944.31
58,259.40
9,907.75
25,000.00
103,111.46
$ 1,929,376.09
10/11/2022 2022 Park Improv 3rd Qtr
Assets:
CITY OF ANDOVER
Park Improvement Fund
Balance Sheet
September 30, 2022
Current Assets
Cash - Reserved
Cash - Unreserved
Total Cash
Interest / Tax Receivable
Due from Other Governments
Total Assets
Liabilities and Fund Balance:
Liabilities
Accounts Payable
Deferred Revenue
Total Liabilities
Fund Balance
Fund Balance 12-31-21
Excess of Revenues Over (Under) Expenditures
Total Fund Balance
Total Liabilities and Fund Balance
$ 103,111.46
1,929,376.09
2,032,487.55
162.78
$ 2,032,650.33
162.78
162.78
1,018,690.64
1,013,796.91
2,032,487.55
$ 2,032,650.33
10/11/2022 2022 Park Improv 3rd Qtr
CITY OF ANDOVER
Park Improvement Fund
Revenues
September 30, 2022
Revenues:
Property Tax / Fiscal Disparities- Current
July Tax Settlement
Dec Settlement
Accrual
Subtotal
54365 - Park Dedication Fees
4660 - 175th Ave NW
Andover Crossings - Apartments
Andover Crossings - Senior Living
Shadowbrook North
Meadows of Petersen Farms
Fields of Winslow Cove
Nightingale Villas
Subtotal
56910 - Interest Income
1 st Qtr
2nd Qtr
3rd & 4th Qtr
Subtotal
58105 - Rental
Verizon Tower Rental - Rose Park
Subtotal
Miscellaneous
Budget
$ 15,000.00
$ 7,791.89
4,400.00
720,900.00
153,792.00
24, 325.00
76,450.00
261,677.00
$ 220,000.00 1,347,276.00
(1,423.00)
1,103.00
10, 094.81
10,094.81
Subtotal $ _ _
Total Revenues $ 235,000.00 $ 1,364,842.70
10/11/2022 2022 Park Improv 3rd Qtr
CITY OF ANDOVER
Park Improvement Fund
Expenditures
September 30, 2022
Expenditures:
Budget
61020 - Supplies - Operating
$ 25,000.00
Subtotal
63005 - Professional Services
WSB - Pine Hills N & S - Parking Lot
17,543.50
Subtotal
17,543.50
63010 - Contractual Services
197,000.00
Pine Hills North & South - Parking Lot
115,350.35
Rose Park Playgroung Equipment
54,824.44
Subtotal
170,174.79
63015 - Publishing
ECM - Oak Bluff - Basketball Court
92.25
ECM - Pine Hills N & S - Parking Lot
-
92.25
184.50
67101 -Operating Transfer Out
163,143.00
163,143.00
Total Expenditures
Revenues Over Expenditures
* - Miscellaneous Projects
385,143.00 351,045.79
(150,143.00) $ 1,013,796.91
10/11/2022 2022 Park Improv 3rd Qtr
DATE: October 10, 2022
FF TO : City of Andover, Parks Department
FROM: Laura Landes
Anoka County Sheriff's Office
SUBJECT: Andover Park Activity Quarterly Report
July 1 — September 30, 2022
The following is a list of reports generated by the Anoka County Sheriff's Office regarding city park
activity for the 3rd quarter.
Date: Time: Location: Case Number:
07.04 10:04 am Crooked Lake Boat Landing 22144328
A deputy was at the boat landing assisting the DNR when a male walked by. The male smelled of
marijuana. The deputy asked him if he had smoked today, and he said yes. He turned over a pipe
and a small amount of marijuana which the deputy destroyed.
07.04 8:21 pm Sunshine 22144750
A deputy was called to a possibly rabid racoon in the park. He located the animal that was
unsteadying and shaking uncontrollably. The deputy dispatched the animal.
07.05 1:13 pm Terrace 22145373
A caller reported a female possibly camping in the park. A deputy made contact with the female who
stated she was just resting because she was working at the fireworks tent nearby. She was advised
she could not be in the park after close.
07.10 12:01 pm Sunshine 22149862
A caller wanted to report that she lost her car keys at the park and wanted to be notified if anyone
turns them in.
07.14 2:39 pm Oak Bluff 22153305
Deputies responded to a suicidal female with a gun in the park. When they arrived, they were able to
talk her down and get her help.
07.22 6:26 pm Kelsey Round Lake 22160180
A caller reported a golf cart and dirt bike on the bike paths. The deputy arrived and was not able to
locate the kids. Extra patrol was conducted.
07.23 7:59 pm Kelsey Round Lake 22161062
A caller reported a golf cart and dirt bike on the bike paths. The deputy arrived and was not able to
locate the kids.
07.31 11:05 pm Pine Hills North 22168092
A caller reported people in the park. The deputy located them and advised them the park was closed.
They left.
08.09 9:25 pm Wild Iris 22175353
Deputies responded to a call from a female who said she was attacked in the park; she was able to
call 911. When deputies arrived, a drone was put in the air to search for the suspect. No one was
located. The caller was provided with medical care and the case was referred to CID.
08.19 10:25 pm Lions Park 22183736
On routine patrol a deputy observed a suspicious vehicle in the parking lot. He smelled marijuana and
made contact with the occupant. He stated he was just doing pull-ups in the park. The vehicle was
searched, and small marijuana was located and confiscated. The male also did not have a driver's
license so a friend was called to pick him up.
08.31 7:31 pm Prairie Knoll 22193946
A deputy was called to a property damage crash that happened in the parking lot and the suspect
was unknown. There was minor damage to the vehicle.
09.08 5:14 pm Fox Meadows 22200880
A caller reported a lost female in the park who appeared to have dementia. The deputy was able to
figure out where she lived and brought her home to her husband.
09.10 8:10 pm Terrace Park 22202706
Deputies were called to a possible fight at the park. When they arrived, multiple juveniles fled. A few
didn't run and stated there was a disagreement and the fight was only verbal. Parents were notified.
09.10 9:11 pm Andover Station North Ballfields 22202754
A caller reported a possibly suicidal male at the park. Deputies made contact with him. He stated he
is going through a divorce and was depressed. He refused any help and said he would go home.
09.19 8:55 am Oak Bluff 22209455
A deputy responded to a backpack that was stolen out of an unlocked vehicle at the park.
10.02 11:38 am Hawk Ridge 22219945
A deputy observed a vehicle accelerating fast and spinning its tires in the lot. He stopped the vehicle.
When he made contact, the driver stated he was unable to transfer the title for the vehicle and it was
uninsured. Marijuana was also found in the vehicle. The vehicle was towed, and the owner cited.
cc: Commander Lenzmeier
kNT Y O F
DOVE
1685 CROSSTOWN BOULEVARD N.W. • ANDOVER, MINNESOTA 55304 • (763) 755-5100
FAX (763) 755-8923 • WWW.ANDOVERMN.GOV
TO: Park & Recreation Commissioners
CC: Dave Berkowitz, Director of Public Works/City Engineer--DD
Jason Baumunk, Parks & Streets Operations Manager
FROM: Jake Griffiths, Associate Planner
SUBJECT: Preliminary Plat Review Legacy at Petersen Farms
DATE: October 20, 2022
DISCUSSION
Legacy at Petersen Farms is a proposed residential development containing 33 rural lots and
would be the third phase of development on the Petersen Farms site. The proposed PUD
Development Plan is attached for review. The applicant is proposing a 10.66-acre outlot as open
space with a wood chip trail that would end at the northern edge of the phase. In future phases of
development, the applicant intends on extending the trail through additional open space areas and
ultimately making a connection to the Martins Meadows Open Space Preserve. Staff has
concerns regarding this trail connection to Martins Meadows as in future phases a bridge or other
solution will be needed to cross a lake. The open space would be accessed via a trail easement as
no part of the outlot boarders a public street.
During review of previous phases of development, the City Council directed that a 46-acre lot
near the lake on the site should be dedicated to the City for open space purposes containing a
trail connection. The rationale was that the open space area would help to meet development
review criteria and contribute to a higher quality, more efficient and unified development. The
PUD Development Plan only shows 31 acres of open space between this and future phases
(approximately 11 acres in this phase, and 20 acres in future phases). In making its
recommendation, the Commission should consider if 46-acres of open space dedication in this
area of the development should still be required.
ACTION REQUESTED
The Park & Recreation Commission is requested to review the proposed development and make
a recommendation to the City Council on the park dedication requirements.
5'Jake
ectfsubmitted,
Griffiths
Associate Planner
Attachments
Proposed PUD Development Plan
CC: JD Andover Holdings, LLC (Via Email)
(Complete)
(Complete)
Item
Phase 1
Phase 2
Phase 3
Future Phases Total
tea$
=a
Gross Developable Area
64 acres
100 acres
72 acres
186 acres 422 acres
,q
~ " ,
Net Developable Area
40 acres
85 acres
61 acres
119 acres 305 acres
,.-
Number of Lots
24 lots
46 lots
331ots
32 lots 1351ots
Lot Srzes
Minimum:
1.5 acres
1.5 acres
1.5 acres
1.5 acres
-
Maximum:
4.0 acres
5.0 acres
2.7 acres
15.6 acres
dJ
Average:
2.5 acres
2.0 acres
2.1 acres
8.6 acres
a
1.0-1.499 acres:
0 lots
0 lots
0 lots
0 lots 0 lots
m
0
" .""
1.5-1.99 acres:
5 lots
33 lots
27 lots
10 lots 75 lots
Phase t
2.0-2.49 acres:
6 lots
3 lots
4 lots
8 lots 21 lots
SP..
finisheo
p\
jt
2.5+ acres:
13 lots
10 lots
2 lots
14 lots 39 lots
0
P
Lot Widths
Future
p
€k
Phases
o
_
Project Boundary
Minimum:
100 feet
100 feet
100 feet
100 feet
Maximum:
192 feet
550 feet
368 feet
562 feet
�
Upland Lot Area
�
Minimum:
1.0 acre
1.0 acre'
1.0' acres
1.3 acre
Phase 2
Average:
1.6 acres
1.3 acres
1.6 acres
32 acres
i
D r
under"!00000
constructionb ope^
Flexibility sought through PUD
-
Space O o 0 o v
f'V
Density
Density Average
Gross Density (units/acre):
0.38
0.46
0.46
0.17 0.32**
_ PhBs
rotect ou - ^
3
;�
Net Density (units/acre):
0.60
0.54
0.54
0.27 0.44
space -
�
* Rule allows 0.40 units/acre Gross Density
Community
space
_ t
`�y' i '�
Legend
�tx,,W�r r:i, ,z-
� � �'r a `,'�M* ��
:.
Fri
� 1t«tito ,l ��`. &t • . � t-- �, - .
Trail Connection to open
space
_�.
r �+
Q Parking for Martin Meadows
, a
Unsuitable
Suitable
Base
Total Area
Area
Area
Density
Tier
(Acres)
(Acres)
(Acres)
(# lots)
1
30.6
7.1
23.6
9.4
2
27.1
10.4
16.7
6.7
3
32.2
12.0
20.2
8.1
4
26.5
3.9
22.5
9.0
Total
121.7
33.5
83.0
33.2
Bonus Base
Density'
Proposed
(# lots)
Lots
14.1
9
13.4
12
24.2
9
27.0
15
78.7
45
`Bonus Base Density:
To Qualify:
Structure setbacks from the OHWL must be at least 50% greater than the minimum
setback, or,
The impact on the waterbody is reduced an equivalent amount through vegetative
I management, topography, or additional acceptable means, and the setback is at least
25% greater than the minimum setback.
t Trail Connection to open space
9 Parking for Martin Meadows
1685 CROSSTOWN BOULEVARD N.W. • ANDOVER, MINNESOTA 55304 . (763) 755-5100
FAX (763) 755-8923 • WWW.ANDOVERMN.GOV
TO: Park & Recreation Commission
CC: David D. Berkowitz, Director of Public Works/City Engineer is
FROM: Jason Baumunk, Parks & Streets Operations Manager
SUBJECT: 9.Outstanding Items
DATE: October 20th, 2022
Current items as of 10/11/2022
COMPLETED PROJECTS
• Strootman Park Playground Improvements (2022) — The new playground equipment was
installed by the neighborhood on Saturday August 27th. The remaining work was finished by
Parks staff the following week.
• Prairie Knoll Park Playground Improvements (2022) — Due to lack of volunteers the
Community Build scheduled for July 301h was canceled. Parks Department Staff installed the
equipment and had the wood fiber mulch installed.
• Oak Bluff Basketball' Court (2022) — The basketball court at Oak Bluff Park was installed and
S
finished.
• Pine Hills North and South Parking Lots (2022) — Both parking lots have been finished and
turned out great. Staff will work on improving the natural prairie plantings in the center medians
including removing the invasive trees.
ON -GOING PROJECTS —
• Prairie Knoll Hockey Rink Replacement — Parks staff has the rink built and it looks great. They
have some finish grade work inside the rink. We are currently working on options for fencing or
netting for around the boards.
ON -HOLD PROJECTS —
• Bike Youth/Trail — No updates currently.
UPDATES FROM PREVIOUS MEETINGS
• Movie in the Park — August 261h, 2022 — The movie Encanto was shown. An estimated 250-300
people attended. The event was very well received with requests of doing more movie dates in 2023.
• Playground Replacement Cost Study — Staff was directed to figure what an average total increase
of cost of playground replacements over the last five years. Comparing playground replacement cost
it difficult due to the vast difference in prices depending on features and design. Below is the most
accurate comparison number we can put together.
o Equipment Cost — 45% increase from 5 years ago.
o Wood Fiber Mulch — 60% increase from 5 years ago.
o Freight Cost — 30% increase from 5 years ago. Calculated using shipping cost at the end of
2021.
OTHER ITEMS OF INTEREST —
• Update of Pedestrian Trails:
❖ 2023 -- Kelsey Round Lake Park Trail. Test piles will be done soon, and then design
will begin on the boardwalk replacement. This will be similar to the boardwalk
along Crosstown Blvd installed on helical piers.
❖ Trail Segment 1 - Crosstown Boulevard to 1591h Ave. Engineering staff is currently
working through the design and easement acquisition with the property owners. If
easement acquisition goes well, construction will occur in 2023. This trail was
planned to connect from Xeon and Crosstown Blvd. to 1591h Ave and Crosstown
Blvd. Council direction is to build the trail on the south side of Crosstown Blvd
from Bluebird St to Prairie Rd, then north up Crosstown Blvd on the east side to
1591h Ave.
❖ Coon Creek Restoration Project —Work has been completed.
If you have any questions or comments regarding any of the items mentioned above or any items relating
to parks or projects, feel free to contact Jason Baumunk or Dave Berkowitz at the City. Staff recommends
the Commission continue reviewing the City Council meeting minutes that you receive by e-mail as to
discussions of various projects the City Council has been working on or is considering.
Note: If you have any items that you would like to add to the list, let me know at the meeting.
eekly Parks Maintenance Update
10/07/2022
• Trash and recycling at all locations was serviced.
• The Prairie Knoll hockey rink rebuild continued. The boards are all up, dirt work mostly done and
netting options are being looked at.
• Mowing is down to once a week for the athletic fields.
09/30/2022
• Trash and recycling at all locations was serviced.
• The Prairie Knoll hockey rink rebuild continued now the corner steel has been delivered.
• Irrigation work was worked on in multiple projects. City Hall parking lots, Pine Hills North, Oak
Bluff Basketball court, and Veterans Memorial parking addition.
• Oak Bluff basketball pole and backboard we installed, and the restoration work completed. Lines
will be painted at that project will be finished.
• Fall fertilizer application was finished.
• Restoration work around the Veterans Memorial parking area and Martin St. concrete ped ramp
repairs was completed.
09/23/2022
• Trash and recycling at all locations was serviced.
• The Prairie Knoll hockey rink rebuild continued.
• Irrigation work was worked on in multiple projects. City Hall parking lots, Pine Hills North, Oak
Bluff Basketball court, and Veterans Memorial parking addition.
• Oak Bluff basketball hoop base was set. Pole and backboard should be installed the following week.
• Fall fertilizer application was started.
09/ 16/2022
• Trash and recycling at all locations was serviced.
• The Prairie Knoll hockey rink rebuild started this week. Side post are going in and dirt work being
done.
• We had another major breakdown of a Jacobsen mower this week. Mower is at Turfworks waiting
on repairs.
• Irrigation work was done on multiple projects. City Hall parking lots, Pine Hills North, Oak Bluff
Basketball court, and Veterans Memorial parking addition.
Respectfully submitted,
Jason Baumunk
1685 CROSSTOWN BOULEVARD N.W. • ANDOVER, MINNESOTA 55304 • (763) 755-5100
FAX (763) 755-8923 • WWW.ANDOVERMN.GOV
TO: Park & Recreation Commissioners
CC: Dave Berkowitz, Director of Public Works/City Engineer��
Jason Baumunk, Parks & Streets Operations Manager
FROM: Jake Griffiths, Associate Planner
SUBJECT: A. Discuss Park Related Fees
DATE: October 20, 2022
DISCUSSION
Staff has been working on various updates to the City's field use guidelines, parks related fee
schedule and park reservation process over the past few months. During the meeting staff will
provide a verbal update on progress so far and seek feedback from the Commission on a number
of topics.
ctfully su itted,
Jake Griffiths
Associate Planner
PARKAND RECREATION COMMISSIONMEETING —AUGUST 4, 2022
MINUTES
The Regular Bi-Monthly Meeting of the Andover Park and Recreation Commission was called
to order by Chairperson Lindahl on August 4, 2022 6:00 p.m., at the Andover City Hall, 1685
Crosstown Boulevard NW, Andover, Minnesota.
Commissioners Present
Commissioners Absent:
Also Present:
RESIDENT FOR UM
Chairperson Jim Lindahl, Commissioners Kristin Lackie,
Sophia Newton, Shane Stenzel, and Reuben Ustimchuck
Tracy Strombeck and Jake Widmyer
Parks & Streets Operations Manager, Jason Baumunk
Public Works Director/City Engineer, Dave Berkowitz
City Administrator, Jim Dickinson
Others
No one appeared before the Commission.
APPROVAL OF MINUTES
June 16, 2022 Regular Meeting
Motion by Lackie, seconded by Newton, to approve the June 16, 2022 Regular Meeting minutes
as presented. Motion passed 4 ayes, 1 present (Stenzel), 2 absent (Strombeck and Widmyer).
APPROVAL OFAGENDA
Motion by Newton, seconded by Stenzel, to approve the agenda as presented. Motion passed 5
ayes and 2 absent (Strombeck and Widmyer).
COMMUNITY CENTER 2ND QUARTER REPORT/ADMINISTRATION
Regular Andover Park & Recreation Commission Meeting
Minutes —August 4, 2022
Page 2
The Park and Recreation Commission is requested to hear a presentation on the 2nd quarter
performance OF the Andover Community Center. City Administrator Dickinson summarized
the 2nd Quarter Report as presented in the staff report. Mr. Dickinson stated there are fewer
events, but the facility is still busy with summer camps. He explained the turf rental window is
short and staff will be strategic about when it is installed. Mr. Dickinson stated Crooked Lake
Concessions is prepping the concession stand with a soft opening in early September. The
Community Center will be looking for part-time staff for the 2022-2023 busy season. Mr.
Dickinson announced the US Hockey Hall of Fame is hosting the Women's Fall Classic at the
Community Center with the Minnesota Gophers playing the St. Cloud State Huskies.
Commissioner Stenzel asked if there were requests for ice when the turf was in. Mr. Dickinson
stated there were requests.
PARKDEDICATIONIMPROVEMENT FUND 2ND QUARTERLYREPORT/FINANCE
The Parks and Recreation Commission is requested to receive a report on the Park Dedication
Improvement Fund for the first quarter. Parks & Streets Operations Manager Baumunk stated
there has been a big influx of funds into the Park Dedication Fund due to development projects.
Commissioner Stenzel recommended allocating the funds to projects soon. Chairperson
Lindahl asked for the item to be on a September agenda.
SHERIFF'S REPORT — 2ND QUARTER
The Park and Recreation Commission is requested to receive the Anoka County Sheriff's
Department report for calls to Andover Parks for the second quarter of 2022. Parks & Streets
Operations Manager Baumunk reviewed the Sheriff's report and stated residents have been a
good job watching the parks.
OUTSTANDING ITEMS
1. Completed Projects: Rose Park Playground and Prairie Knoll. The Community Builds
were not successful. Community Builds are scheduled for Saturdays at 7:00 a.m. and
take 4-5 hours with around 10 committed adult volunteers.
2. On -going Projects: Strootman Park design approved and install date in late August.
Prairie Knoll hockey rink replacement in late August.
3. On -Hold Projects: Bike/Youth Trail
4. Updates from Previous Meetings:
a. Movie in the Park (Encanto) scheduled for August 26, 2022.
b. SilverCrest Senior Development moving along
c. Playground Replacement Cost Study — staff is preparing
5. Other Items of Interest:
Regular Andover Park & Recreation Commission Meeting
Minutes —August 4, 2022
Page 3
• Pedestrian Trails:
i. Kelsey Round Lake Park Trail has DNR grant for 2023
ii. Trail Segment 1 — Crosstown Boulevard to 1591" Ave in design process
iii. Coon Creek Restoration Project has started up again.
• August 18 meeting at Prairie Knoll Park at 6:00 p.m.
• Staff are looking at the field use application process to make it easier for
customers and staff
6. Parks Maintenance Update: presented in the staff report.
CHAIR'S REPORT
Commissioner Newton stated the landscaping around Veterans Memorial looks nice.
Commissioner Stenzel stated the parks look great.
Chairperson Lindahl stated football will be starting soon and the parks will be busy again.
ADJOURNMENT
Motion by Newton, seconded by Lackie, to adjourn the meeting at 6:30 p.m. Motion passed
unanimously.
Respectfully Submitted,
Shari Kunza, Recording Secretary
Timesaver Off Site Secretarial, Inc.
PARK AND RECREATION WORKSHOP MEETING —AUGUST 18, 2022
MINUTES
The Workshop Meeting of the Andover Park and Recreation Commission was called to order
by Chairperson Lindahl on August 18, 2022 6:00 p.m., at the Prairie Knoll Park, 14800 Prairie
Road NW, Andover, Minnesota.
Commissioners Present: Chairperson Jim Lindahl, Commissioners Kristin Lackie,
Sophia Newton, Shane Stenzel, Tracy Strombeck, Reuben
Ustimchuck, and Jake Widmyer
Commissioners Absent:
Also Present: Parks & Streets Operations Manager, Jason Baumunk
Others
DISCUSS FUTURE PARK IMPROVEMENTS
The Park and Recreation Commission is requested to start discussions on future park
improvements due to the rapid growth of the Park Dedication Fund. Parks & Streets Operations
Manager Baumunk stated there is $960,000 in the fund with more revenue expected this year.
The Commission reviewed the future facilities chart and recommended:
• Pine Hills North
o Add a larger shelter
o Disc golf course
o Finish landscaping
o Multi -purpose building
o Work towards a keyless system
o Push the playground back a few years
• Sunshine Park
o Revision of the shelter with bathrooms
o Mr. Baumunk informed the Commission the MN Selects Fastpitch tournament
was at Sunshine Park this past weekend with over 700 girls.
0 Parking was an issue
Regular Andover Park & Recreation Commission Workshop Meeting
Minutes —August 18, 2022
Page 2
■ Mr. Baumunk met with Heather, the fastpitch director, and had no idea
it would be this big.
■ The Commission asked if there was a tournament fee because someone
made a lot of money. The Commission asked about adding a gate fee to
tournaments and discussed charging fees for youth sports.
■ Mr. Baumunk stated if the City hosts the tournament next year, they will
hold the opening ceremony at the high school.
• The Commission would like to allocate funds to each zone in the City
• Kelsey Round Lake Park
The Commission discussed:
o Overlook will be replaced
o The value of a boardwalk
o Natural play features and additional benches
o Complete trail connections
o Add cross country skiing trails
The Commission will continue to discuss placing items in the CIP and attaching years at a future
meeting.
DISCUSS FIELD USE SCHEDULE REVISIONS
The Commission is requested to discuss revisions to the field use process. Mr. Baumunk stated
staff are meeting bi-weekly to revamp field use process. He explained the forms will get easier
to complete and he would like the schedules to be online. He stated the fee schedule will need
to be revised as well. Mr. Baumunk noted that youth sports are not charged a fee and they
contribute funds to improve parks. The Commission discussed who should be in control of the
field schedules. The Commission suggested having the associations take one field off the
schedule to be used by the public each week during prime time. Mr. Baumunk stated he
received a schedule from baseball and it was comprised of 15 excel spreadsheets. He is looking
for software that can provide one master schedule. Mr. Baumunk is concerned about the amount
of staff time needed to schedule fields and monitor the schedules.
ADJOURNMENT
The meeting adjourned at 7:02 p.m.
Respectfully Submitted,
Shari Kunza, Recording Secretary
TimeSaver Off Site Secretarial, Inc.